Project Management: Earned Value Management Quiz
10 Questions
3 Views

Project Management: Earned Value Management Quiz

Created by
@RazorSharpSynecdoche

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

What is the schedule performance index (SPI) value for the project mentioned in the text?

  • 0.86 (correct)
  • 3:24
  • 1.12
  • 4:08
  • What does a schedule performance index (SPI) value less than 1 indicate about the project's progress?

  • On schedule
  • Completed the project
  • Behind schedule (correct)
  • Ahead of schedule
  • What action would be taken to bring the project back on track based on the SPI value mentioned in the text?

  • Apply schedule crashing (correct)
  • Reduce the project scope
  • Fast tracking
  • Update the risk register
  • What does a cost performance index (CPI) value greater than 1 indicate about the project's progress?

    <p>Under budget</p> Signup and view all the answers

    Which technique involves performing activities in parallel to speed up the project timeline?

    <p>Apply fast tracking</p> Signup and view all the answers

    What does a cost performance index (CPI) value of 1.12 suggest about the project's budget?

    <p>Under budget</p> Signup and view all the answers

    What is one way to interpret a schedule performance index (SPI) value greater than 1?

    <p>Ahead of schedule</p> Signup and view all the answers

    What is the primary reason for choosing schedule crashing to get a project back on track?

    <p>To allocate more resources and money</p> Signup and view all the answers

    What is another term for working on different items in sequence rather than in parallel?

    <p>Sequential processing</p> Signup and view all the answers

    How would reducing the project scope potentially help in getting a project back on track?

    <p>By focusing on critical deliverables only</p> Signup and view all the answers

    Study Notes

    Project Performance Indices

    • SPI (Schedule Performance Index) measures the project's progress against its schedule.
    • SPI < 1 indicates the project is behind schedule.
    • CPI (Cost Performance Index) > 1 indicates the project is under budget.

    Bringing the Project Back on Track

    • A low SPI value indicates the need to get the project back on track.
    • Schedule crashing can be used to get a project back on track by adding more resources to critical tasks.
    • The primary reason for choosing schedule crashing is to reduce the project duration.

    Project Scheduling Techniques

    • Fast tracking involves performing activities in parallel to speed up the project timeline.
    • Phasing is another term for working on different items in sequence rather than in parallel.

    Project Recovery Strategies

    • Reducing the project scope can help get a project back on track by eliminating non-essential tasks.
    • A high CPI value (e.g. 1.12) suggests the project is currently under budget.
    • An SPI value > 1 suggests the project is ahead of schedule.

    Studying That Suits You

    Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

    Quiz Team

    Description

    Test your knowledge of project management by evaluating the earned value management scenario given. Learn about schedule performance index (SPI) and cost performance index (CPI) values to make decisions for bringing a project back on track.

    More Like This

    Use Quizgecko on...
    Browser
    Browser