Earned Value Management (EVM) Overview
24 Questions
0 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

What does the Estimate At Completion (EAC) represent?

  • Total planned value for the project
  • The estimated total cost of the project upon completion (correct)
  • The estimated cost to complete the remaining work
  • The ratio of remaining work to funds remaining
  • How is the Cost Performance Indicator (CPI) calculated?

  • CPI = AC / EV
  • CPI = EV / AC (correct)
  • CPI = EV + AC
  • CPI = PV / EV
  • What does a negative Schedule Variance (SV) indicate?

  • The project has exceeded its budget
  • The project is ahead of schedule
  • The project is behind schedule (correct)
  • The project is on schedule
  • If the Actual Cost (AC) is $1200 and the Earned Value (EV) is $800, what does this imply about the project costs?

    <p>The project is over budget</p> Signup and view all the answers

    What is the planned value (PV) for the completion of side 1 of the project?

    <p>$1000</p> Signup and view all the answers

    What does the To-Complete Performance Index (TCPI) indicate?

    <p>It represents the cost efficiency required to complete the remaining work to meet a budget target</p> Signup and view all the answers

    What is the overall project completion status indicated after Week 1?

    <p>20%</p> Signup and view all the answers

    What does the Schedule Performance Indicator (SPI) of 0.8 signify?

    <p>Work is behind schedule compared to planned value</p> Signup and view all the answers

    What is the primary purpose of Earned Value Management (EVM)?

    <p>To provide a health check on project performance</p> Signup and view all the answers

    Which of the following is NOT a prerequisite for implementing EVM?

    <p>Risk management plan</p> Signup and view all the answers

    What does Schedule Variance (SV) measure?

    <p>The difference between earned value and planned value</p> Signup and view all the answers

    Which of the following correctly defines Earned Value (EV)?

    <p>The estimated monetary value of the work accomplished</p> Signup and view all the answers

    What does Cost Performance Index (CPI) indicate?

    <p>The ratio of earned value to actual costs</p> Signup and view all the answers

    Which step is NOT involved in the application of EVM?

    <p>Create stakeholder communication plan</p> Signup and view all the answers

    What does Budget At Completion (BAC) represent?

    <p>The total budget for all project work</p> Signup and view all the answers

    Which of the following is a measure of schedule efficiency?

    <p>Schedule Performance Index (SPI)</p> Signup and view all the answers

    What is the formula used to calculate the Cost Performance Index (CPI)?

    <p>CPI = EV / AC</p> Signup and view all the answers

    What does an SPI value greater than 1 indicate?

    <p>The project is ahead of schedule</p> Signup and view all the answers

    Which limitation of Earned Value Management (EVM) suggests that project quality might not be adequately captured?

    <p>No indication of Project Quality</p> Signup and view all the answers

    In a project with an SPI of 1.03 and a CPI of 0.81, what does the CPI indicate?

    <p>The project is over budget</p> Signup and view all the answers

    What does the To-Complete Performance Index (TCPI) help determine?

    <p>The budget needed to complete the remaining work</p> Signup and view all the answers

    If a project has an actual cost of $20,000 and an earned value of $18,000, what is the CPI?

    <p>0.8</p> Signup and view all the answers

    What does a Schedule Variance (SV) of zero indicate about a project?

    <p>The project is perfectly on schedule</p> Signup and view all the answers

    What is one reason why EVM may be difficult to implement in R&D projects?

    <p>Such projects often have poorly defined outcomes</p> Signup and view all the answers

    Study Notes

    Earn Value Management (EVM)

    • EVM is a project management technique used to track project progress and performance
    • Time is not regarded as time but cost, time is money
    • EVM helps in project health check, schedule performance, cost performance, forecasting, issue identification (estimation problems, scope creep, inefficiency), and communication
    • Pre-requisites for EVM include a well-defined scope, detailed work breakdown structure (WBS), project management schedule, and management support

    EVM Steps

    • Define work to be done
    • Assign a monetary value to the work
    • Apply earning values (e.g., 0/100, 20/80, 25/75, 50/50)
    • Execute project and measure progress

    EVM Terms

    • Planned Value (PV): Budgeted Cost of Work Scheduled (BCWS), estimated monetary value of planned work at a specific point in time
    • Earned Value (EV): Budgeted Cost of Work Performed (BCWP), estimated monetary value of completed work
    • Actual Cost (AC): Actual Cost of Work Performed (ACWP), actual cost spent on the completed work.
    • Schedule Variance (SV): difference between earned value (EV) and planned value (PV)
    • Cost Variance (CV): difference between earned value (EV) and actual cost (AC)
    • Schedule Performance Index (SPI): ratio of earned value (EV) to planned value (PV), measures schedule efficiency
    • Cost Performance Index (CPI): ratio of earned value (EV) to actual cost (AC), measures cost efficiency
    • Budget at Completion (BAC): Budget for the entire project, total planned value
    • Estimate to Complete (ETC): estimated cost to complete remaining work
    • Estimate At Completion (EAC): estimated total cost of the project when all work is complete
    • To-Complete Performance Index (TCPI): Ratio of remaining work to remaining budget needed to meet a target

    Definitions

    • Planned Value (PV): Estimated monetary value of planned work at a given time
    • Earned Value (EV): The estimated monetary value of the work that has been accomplished
    • Actual Cost (AC): The actual costs incurred for the work accomplished

    Schedule and Cost Performance

    • Schedule Variance (SV): EV - PV
    • Schedule Performance Index (SPI): EV / PV
    • Cost Variance (CV): EV - AC
    • Cost Performance Index (CPI): EV / AC

    EV Plot

    • A graph showing the relationship between earned value, planned value, and actual cost over time

    Forecasts

    • Estimate To Complete (ETC): Estimation of the remaining costs to complete a project
    • Estimate At Completion (EAC): Estimation of the total cost to complete a project

    EAC (Re-estimate)

    • Original estimate is flawed
    • Requires additional resources/time to complete the project
    • Adjusted total cost will reflect additional time and resources allocated

    EAC (atypical)

    • Slippage due to special events (new requirements)
    • Adjusted estimate based on additional time and resources

    EAC (typical)

    • Current performance to continue
    • Additional time is required as per the revised schedule and revised estimate to complete the project

    ETC (considering CPI and SPI)

    • Project needs to meet the deadline
    • Add more resources
    • Estimate to complete the project

    Estimate At Completion (EAC) Formulas

    • Original estimate is flawed, adjusted estimate due to new factors
    • Remaining work to be performed at original budgeted rate
    • Remaining work to be performed at current CPI, different scenario
    • The project needs to meet the deadline

    To-Complete Performance Index (TCPI)

    • Future cost performance to achieve target BAC or EAC
    • TCPI = Remaining Work / Remaining Budget
    • TCPI based on BAC
    • TCPI based on EAC

    Limitations of EVM

    • Mental block: Time vs cost, focus on cost
    • Earn schedule (ES) can be a remedy if the project finishes behind schedule
    • No indication of Project Quality, or Customer Satisfaction
    • Requires well-defined Scope, WBS, and Schedule
    • Difficult to implement for dynamic work (like R&D projects)
    • Benefits are proportional to the size / complexity of the project

    Questions

    • Question 1: CPI of a project, given planned, actual and earned values
    • Question 2: Why a sponsor is concerned about the project progress, given SPI and CPI
    • Question 3: Related to project management and cost calculations of developing and installing drivers

    Studying That Suits You

    Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

    Quiz Team

    Related Documents

    Earn Value Management PDF

    Description

    This quiz covers the essential concepts and steps of Earned Value Management (EVM) in project management. Learn about key terms like Planned Value, Earned Value, and Actual Cost, and understand the prerequisites for effective EVM implementation. Test your knowledge on how EVM can enhance project performance tracking and forecasting.

    More Like This

    Earned Value (EV) Quiz
    6 questions

    Earned Value (EV) Quiz

    RapturousWilliamsite avatar
    RapturousWilliamsite
    Project Management Deliverables Quiz
    5 questions
    Use Quizgecko on...
    Browser
    Browser