Earned Value Management (EVM) Overview
24 Questions
0 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to Lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

What does the Estimate At Completion (EAC) represent?

  • Total planned value for the project
  • The estimated total cost of the project upon completion (correct)
  • The estimated cost to complete the remaining work
  • The ratio of remaining work to funds remaining

How is the Cost Performance Indicator (CPI) calculated?

  • CPI = AC / EV
  • CPI = EV / AC (correct)
  • CPI = EV + AC
  • CPI = PV / EV

What does a negative Schedule Variance (SV) indicate?

  • The project has exceeded its budget
  • The project is ahead of schedule
  • The project is behind schedule (correct)
  • The project is on schedule

If the Actual Cost (AC) is $1200 and the Earned Value (EV) is $800, what does this imply about the project costs?

<p>The project is over budget (C)</p> Signup and view all the answers

What is the planned value (PV) for the completion of side 1 of the project?

<p>$1000 (C)</p> Signup and view all the answers

What does the To-Complete Performance Index (TCPI) indicate?

<p>It represents the cost efficiency required to complete the remaining work to meet a budget target (A)</p> Signup and view all the answers

What is the overall project completion status indicated after Week 1?

<p>20% (A)</p> Signup and view all the answers

What does the Schedule Performance Indicator (SPI) of 0.8 signify?

<p>Work is behind schedule compared to planned value (B)</p> Signup and view all the answers

What is the primary purpose of Earned Value Management (EVM)?

<p>To provide a health check on project performance (C)</p> Signup and view all the answers

Which of the following is NOT a prerequisite for implementing EVM?

<p>Risk management plan (A)</p> Signup and view all the answers

What does Schedule Variance (SV) measure?

<p>The difference between earned value and planned value (C)</p> Signup and view all the answers

Which of the following correctly defines Earned Value (EV)?

<p>The estimated monetary value of the work accomplished (C)</p> Signup and view all the answers

What does Cost Performance Index (CPI) indicate?

<p>The ratio of earned value to actual costs (C)</p> Signup and view all the answers

Which step is NOT involved in the application of EVM?

<p>Create stakeholder communication plan (A)</p> Signup and view all the answers

What does Budget At Completion (BAC) represent?

<p>The total budget for all project work (D)</p> Signup and view all the answers

Which of the following is a measure of schedule efficiency?

<p>Schedule Performance Index (SPI) (D)</p> Signup and view all the answers

What is the formula used to calculate the Cost Performance Index (CPI)?

<p>CPI = EV / AC (B)</p> Signup and view all the answers

What does an SPI value greater than 1 indicate?

<p>The project is ahead of schedule (C)</p> Signup and view all the answers

Which limitation of Earned Value Management (EVM) suggests that project quality might not be adequately captured?

<p>No indication of Project Quality (C)</p> Signup and view all the answers

In a project with an SPI of 1.03 and a CPI of 0.81, what does the CPI indicate?

<p>The project is over budget (A)</p> Signup and view all the answers

What does the To-Complete Performance Index (TCPI) help determine?

<p>The budget needed to complete the remaining work (B)</p> Signup and view all the answers

If a project has an actual cost of $20,000 and an earned value of $18,000, what is the CPI?

<p>0.8 (B)</p> Signup and view all the answers

What does a Schedule Variance (SV) of zero indicate about a project?

<p>The project is perfectly on schedule (A)</p> Signup and view all the answers

What is one reason why EVM may be difficult to implement in R&D projects?

<p>Such projects often have poorly defined outcomes (B)</p> Signup and view all the answers

Flashcards

What's EVM used for?

Evaluates a project's health by analyzing its schedule, cost performance, and other crucial factors like estimations, scope creep, inefficiencies, communication, and required corrective actions.

Planned Value (PV)

The budget allocated for work planned to be completed by a specific point in time.

Earned Value (EV)

The budget value of the work actually completed at a certain point in time.

Actual Cost (AC)

The actual amount spent on completing the work up to a defined point in time.

Signup and view all the flashcards

Schedule Variance (SV)

The difference between the Earned Value (EV) and the Planned Value (PV). A positive value indicates being ahead of schedule, while a negative value means falling behind.

Signup and view all the flashcards

Cost Variance (CV)

The difference between the Earned Value (EV) and the Actual Cost (AC). A positive value indicates coming in under budget, while a negative value means going over budget.

Signup and view all the flashcards

Schedule Performance Index (SPI)

The ratio of Earned Value (EV) to Planned Value (PV). A value greater than 1 indicates being ahead of schedule, while a value less than 1 means falling behind schedule.

Signup and view all the flashcards

Cost Performance Index (CPI)

The ratio of Earned Value (EV) to Actual Cost (AC). A value greater than 1 indicates being under budget, while a value less than 1 means going over budget.

Signup and view all the flashcards

Estimate To Complete (ETC)

The estimated cost to complete all the remaining work on a project, an activity, or a WBS component.

Signup and view all the flashcards

Estimate At Completion (EAC)

The estimated total cost of a project, an activity, or a WBS component, when all the work is completed.

Signup and view all the flashcards

To-Complete Performance Index (TCPI)

The cost performance that must be achieved on the remaining work to meet a BAC (or EAC) target. It is the ratio of "remaining work" to the "funds remaining."

Signup and view all the flashcards

Budget At Completion (BAC)

The total planned value for the project.

Signup and view all the flashcards

EAC (Re-estimate)

A method to calculate EAC that relies on a re-estimate of the project's remaining work, factoring in past performance and forecasted changes.

Signup and view all the flashcards

EAC (Typical)

A method to calculate EAC that uses the current CPI to predict remaining costs, assuming the current performance will continue.

Signup and view all the flashcards

EAC (Atypical)

A calculation of EAC using both CPI and SPI, accounting for any possible changes in performance.

Signup and view all the flashcards

EVM limitations - well-defined Scope, WBS, and Schedule required

The project must be carefully defined with a clear scope, breakdown structure, and schedule for EVM to be effectively applied.

Signup and view all the flashcards

EVM limitations - Project quality and customer satisfaction

EVM struggles to capture and measure project quality and customer satisfaction, making it only a partial reflection of project success.

Signup and view all the flashcards

Study Notes

Earn Value Management (EVM)

  • EVM is a project management technique used to track project progress and performance
  • Time is not regarded as time but cost, time is money
  • EVM helps in project health check, schedule performance, cost performance, forecasting, issue identification (estimation problems, scope creep, inefficiency), and communication
  • Pre-requisites for EVM include a well-defined scope, detailed work breakdown structure (WBS), project management schedule, and management support

EVM Steps

  • Define work to be done
  • Assign a monetary value to the work
  • Apply earning values (e.g., 0/100, 20/80, 25/75, 50/50)
  • Execute project and measure progress

EVM Terms

  • Planned Value (PV): Budgeted Cost of Work Scheduled (BCWS), estimated monetary value of planned work at a specific point in time
  • Earned Value (EV): Budgeted Cost of Work Performed (BCWP), estimated monetary value of completed work
  • Actual Cost (AC): Actual Cost of Work Performed (ACWP), actual cost spent on the completed work.
  • Schedule Variance (SV): difference between earned value (EV) and planned value (PV)
  • Cost Variance (CV): difference between earned value (EV) and actual cost (AC)
  • Schedule Performance Index (SPI): ratio of earned value (EV) to planned value (PV), measures schedule efficiency
  • Cost Performance Index (CPI): ratio of earned value (EV) to actual cost (AC), measures cost efficiency
  • Budget at Completion (BAC): Budget for the entire project, total planned value
  • Estimate to Complete (ETC): estimated cost to complete remaining work
  • Estimate At Completion (EAC): estimated total cost of the project when all work is complete
  • To-Complete Performance Index (TCPI): Ratio of remaining work to remaining budget needed to meet a target

Definitions

  • Planned Value (PV): Estimated monetary value of planned work at a given time
  • Earned Value (EV): The estimated monetary value of the work that has been accomplished
  • Actual Cost (AC): The actual costs incurred for the work accomplished

Schedule and Cost Performance

  • Schedule Variance (SV): EV - PV
  • Schedule Performance Index (SPI): EV / PV
  • Cost Variance (CV): EV - AC
  • Cost Performance Index (CPI): EV / AC

EV Plot

  • A graph showing the relationship between earned value, planned value, and actual cost over time

Forecasts

  • Estimate To Complete (ETC): Estimation of the remaining costs to complete a project
  • Estimate At Completion (EAC): Estimation of the total cost to complete a project

EAC (Re-estimate)

  • Original estimate is flawed
  • Requires additional resources/time to complete the project
  • Adjusted total cost will reflect additional time and resources allocated

EAC (atypical)

  • Slippage due to special events (new requirements)
  • Adjusted estimate based on additional time and resources

EAC (typical)

  • Current performance to continue
  • Additional time is required as per the revised schedule and revised estimate to complete the project

ETC (considering CPI and SPI)

  • Project needs to meet the deadline
  • Add more resources
  • Estimate to complete the project

Estimate At Completion (EAC) Formulas

  • Original estimate is flawed, adjusted estimate due to new factors
  • Remaining work to be performed at original budgeted rate
  • Remaining work to be performed at current CPI, different scenario
  • The project needs to meet the deadline

To-Complete Performance Index (TCPI)

  • Future cost performance to achieve target BAC or EAC
  • TCPI = Remaining Work / Remaining Budget
  • TCPI based on BAC
  • TCPI based on EAC

Limitations of EVM

  • Mental block: Time vs cost, focus on cost
  • Earn schedule (ES) can be a remedy if the project finishes behind schedule
  • No indication of Project Quality, or Customer Satisfaction
  • Requires well-defined Scope, WBS, and Schedule
  • Difficult to implement for dynamic work (like R&D projects)
  • Benefits are proportional to the size / complexity of the project

Questions

  • Question 1: CPI of a project, given planned, actual and earned values
  • Question 2: Why a sponsor is concerned about the project progress, given SPI and CPI
  • Question 3: Related to project management and cost calculations of developing and installing drivers

Studying That Suits You

Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

Quiz Team

Related Documents

Earn Value Management PDF

Description

This quiz covers the essential concepts and steps of Earned Value Management (EVM) in project management. Learn about key terms like Planned Value, Earned Value, and Actual Cost, and understand the prerequisites for effective EVM implementation. Test your knowledge on how EVM can enhance project performance tracking and forecasting.

More Like This

Earned Value (EV) Quiz
6 questions

Earned Value (EV) Quiz

RapturousWilliamsite avatar
RapturousWilliamsite
Project Management Deliverables Quiz
5 questions
FPM Week 10 - Reporting and Metrics
50 questions
Use Quizgecko on...
Browser
Browser