FPM Week 7 - Cost Estimation
48 Questions
0 Views

FPM Week 7 - Cost Estimation

Created by
@FasterMistletoe

Questions and Answers

What is the purpose of aggregating cost estimates by Work Packages?

  • To determine the project's overall profit margin
  • To manage resource allocation across the project
  • To create a project timeline and schedule activities
  • To link cost estimates to financial systems through Control Accounts (correct)
  • Which of the following is NOT included in the project management plan?

  • Cost management plan
  • Agreements (correct)
  • Resource management plan
  • Scope baseline
  • What document contains the results of risk analysis and response planning?

  • Risk register (correct)
  • Scope statement
  • Project schedule
  • Cost estimates
  • What should be checked to ensure that constraints are met in the budget?

    <p>If the total budget falls within the approved financial limits</p> Signup and view all the answers

    What is a primary purpose of creating a cost baseline as an S-curve?

    <p>To visually represent projected costs against time</p> Signup and view all the answers

    Which of the following costs may be added to the budget during cost aggregation?

    <p>Management reserves</p> Signup and view all the answers

    Which item is included in the Basis of Estimates document?

    <p>Background and supporting details for cost estimates</p> Signup and view all the answers

    What is a common component of indirect costs that should be added to the budget?

    <p>Overheads</p> Signup and view all the answers

    What does a larger number of dots indicate in the context of estimation?

    <p>Larger item size indication</p> Signup and view all the answers

    Which T-shirt size would likely be chosen for the user story about creating a user profile?

    <p>XXL</p> Signup and view all the answers

    How should user stories be selected for a sprint?

    <p>Prioritizing highest value until capacity is reached</p> Signup and view all the answers

    What method can be used to quantify a team's capacity in a sprint?

    <p>Story points or ideal days</p> Signup and view all the answers

    What is recommended at the end of each sprint regarding team capacity?

    <p>Review and aim to increase capacity</p> Signup and view all the answers

    What is the significance of using the Fibonacci sequence in estimation?

    <p>It provides a consistent scaling for story points</p> Signup and view all the answers

    Why are T-shirt sizes used in estimating tasks?

    <p>They simplify the communication about task size</p> Signup and view all the answers

    What is the main purpose of selecting user stories for a sprint based on value?

    <p>To maximize team efficiency and impact</p> Signup and view all the answers

    What is the purpose of Lee reviewing session feedback from other attendees?

    <p>To determine the best sessions to listen to via recordings</p> Signup and view all the answers

    What does Andre need to manage effectively during the event?

    <p>A personalized agenda</p> Signup and view all the answers

    Which item was identified as having the largest T-shirt size in the product backlog?

    <p>Secure Payment Processing</p> Signup and view all the answers

    What is one of the objectives of the Homepage item in the product backlog?

    <p>To highlight key event details and encourage registration</p> Signup and view all the answers

    What feature is included in the product backlog to assist attendees in navigating the event location?

    <p>Venue Information and Maps</p> Signup and view all the answers

    Which of the following tasks is classified as 'XS' in T-shirt sizing?

    <p>FAQ Section</p> Signup and view all the answers

    What aspect of the website project does the Responsive Design item address?

    <p>Guaranteeing a smooth experience on different devices</p> Signup and view all the answers

    What is the goal behind implementing social media integration in the event website?

    <p>To allow attendees to connect with peers and share updates</p> Signup and view all the answers

    What is a major challenge faced by virtual teams?

    <p>Different cultures</p> Signup and view all the answers

    Which step comes first in the problem-solving process?

    <p>Identify the problem</p> Signup and view all the answers

    What is the purpose of an issue log in project management?

    <p>To help understand unexpected resource requirements</p> Signup and view all the answers

    Which resource selection might typically be considered the baseline for assessing quality and time costs?

    <p>Basic marketing specialist</p> Signup and view all the answers

    Using video communications in virtual teams can help to mitigate which of the following challenges?

    <p>Lack of face-to-face communications</p> Signup and view all the answers

    What is the primary function of team performance assessments?

    <p>To assess current team performance</p> Signup and view all the answers

    What should be considered when solving a problem to ensure ethical choices?

    <p>Ethical considerations of the solution</p> Signup and view all the answers

    What is one recommended approach to improving communication in virtual teams?

    <p>Spend more time communicating</p> Signup and view all the answers

    Which tool helps record past project experiences to benefit future phases?

    <p>Lessons learned register</p> Signup and view all the answers

    In resource management, what does a work performance report encompass?

    <p>Results from schedule, cost, quality control, and scope validation</p> Signup and view all the answers

    What is the highest priority user story listed for Andre?

    <p>Seeing a personalized agenda</p> Signup and view all the answers

    Which Fibonacci value corresponds to the user story of Lee entering a discount code?

    <p>3</p> Signup and view all the answers

    What total story points are allocated combined for Andre's stories about creating a profile and paying?

    <p>24</p> Signup and view all the answers

    Which user story has a priority of 4?

    <p>Paying with a credit card</p> Signup and view all the answers

    What feature is described as needed by Lee regarding security?

    <p>Password protection</p> Signup and view all the answers

    Which user story has the least priority according to the content?

    <p>Creating a profile</p> Signup and view all the answers

    How many story points are assigned to Lee's request to review session feedback?

    <p>8</p> Signup and view all the answers

    What does Andre need to manage his time effectively according to his user story?

    <p>A personalized agenda</p> Signup and view all the answers

    What is the team capacity for story points mentioned in the context?

    <p>40</p> Signup and view all the answers

    Which Fibonacci number is used to estimate the effort for Andre's ability to provide feedback?

    <p>13</p> Signup and view all the answers

    What benefit does Lee gain from entering a discount code?

    <p>Reduces costs</p> Signup and view all the answers

    Which feature allows Lee to find his next session via phone?

    <p>Link to the program agenda</p> Signup and view all the answers

    What user story has the highest Fibonacci value assigned?

    <p>Creating a user profile</p> Signup and view all the answers

    What does the user story for Andre state regarding managing cash flow?

    <p>Paying with a credit card</p> Signup and view all the answers

    Study Notes

    Cost Management Overview

    • Develop and manage budget through a project management plan, comprising a cost management plan, resource management plan, and scope baseline.
    • Aggregate cost estimates by work packages using control accounts that connect to financial systems.
    • Risk response costs, overhead costs, contingency reserves, management reserves, and profit for external work may be added to the budget.

    Risk Contingency and Overheads

    • Include risk contingency and indirect costs when estimating the total budget.
    • Ensure the final budget adheres to predetermined constraints.
    • Create a cost baseline represented as an S-curve for effective tracking.

    Inputs for Budgeting

    • Project documents must contain a basis of estimates, detailed cost estimates, project schedule, resource calendar, and risk register.
    • Agreements related to contracts or other cost elements are essential to budget formulation.

    Relative Estimating Techniques

    • T-shirt sizing method is used for estimating effort or complexity for user stories (XS, S, M, L, XL, XXL).
    • Relative sizing can be performed using the Fibonacci sequence to establish story points for tasks or user stories.
    • Team capacity can be quantified using story points or ideal days, optimizing sprint planning accordingly.

    Sprint Selection Criteria

    • Selection of backlog items for a sprint should prioritize the highest value until team capacity is reached.
    • Review team capacity at the end of each sprint to identify improvements.

    Managing Virtual Teams

    • Virtual teams face challenges such as cultural differences, communication barriers, different time zones, and technological issues.
    • Effective communication, clarity, and video interactions can mitigate challenges in virtual collaboration.

    Resource Management Tools

    • Utilize issue logs to track unexpected resource needs and lessons learned registers to inform future project phases.
    • Clearly define team assignments and responsibilities to enhance project focus.
    • Work performance reports provide insights into resource needs based on controls of schedule, cost, and quality.

    Problem-Solving Framework

    • Address issues methodically: identify, define, investigate, analyze, solve, and verify solutions.
    • Maintain an ethical approach when evaluating and implementing solutions to problems.

    Resource Assignment Considerations

    • When selecting marketing specialists, evaluate options based on experience and availability, considering time costs and quality of work.
    • Baselines are designed to ensure a balanced approach in resource selection that meets project requirements.

    Studying That Suits You

    Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

    Quiz Team

    Description

    This quiz focuses on the essential aspects of project cost management, including the creation of control accounts, risk contingency considerations, and establishing a cost baseline using an S-curve. It also emphasizes the importance of project management plans and ensuring budget constraints are met.