Pre-Occupancy Services Commissioning
26 Questions
0 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to Lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

Which document attests that the contract between the owner and the contractor is substantially complete?

  • Guaranty
  • Holdback
  • Definitions Certificate
  • Certificate of Substantial Performance (correct)

What is a three-party agreement in which a third party guarantees the performance of an obligation to the second party in the event of default of the first party?

  • Holdback
  • Guaranty (correct)
  • Certificate of Substantial Performance
  • Definitions Certificate

What is the act of keeping a building system, process, or property in proper and efficient working condition?

  • Ready-for-Takeover
  • Maintenance (correct)
  • Lien
  • Post-occupancy Evaluation

Which stage of a project does Pre-occupancy Services Commissioning typically begin at?

<p>Pre-design stage (B)</p> Signup and view all the answers

According to the text, who is responsible for reviewing defects and deficiencies during the warranty period on behalf of the client?

<p>The architect (B)</p> Signup and view all the answers

What should the architect do prior to the anniversary date of the one-year warranty?

<p>Arrange a review of the project (A)</p> Signup and view all the answers

What is the purpose of commissioning in the construction process?

<p>To achieve quality assurance (D)</p> Signup and view all the answers

What is the potential consequence of failure to verify during systems testing?

<p>Delays and claims (D)</p> Signup and view all the answers

What may the architect do if the contractor fails to rectify a warranty item in a reasonable time?

<p>Review the client's rights under the bonding and insurance provisions in the contract (D)</p> Signup and view all the answers

When can a building operator training program be started?

<p>After conditional acceptance is established (B)</p> Signup and view all the answers

Which type of completion is often used on small projects when the time between substantial performance and total completion is short?

<p>Deemed total completion (B)</p> Signup and view all the answers

Who prepares and issues the final certificate for payment?

<p>Architect (B)</p> Signup and view all the answers

What is the purpose of the holdback monies?

<p>To release monies previously invoiced for (D)</p> Signup and view all the answers

What is the purpose of a letter of assurance in some jurisdictions?

<p>To certify that the building has been constructed in compliance with the building code (C)</p> Signup and view all the answers

According to the CCDC, which term is used to describe a list of factors that, once satisfied, result in project completion?

<p>Ready-for-takeover (B)</p> Signup and view all the answers

What is a regulatory requirement of the contractor, rather than a contractual requirement?

<p>Substantial performance (B)</p> Signup and view all the answers

Which of the following is NOT a prerequisite to attaining Ready-for-Takeover of the Work according to CCDC 2 2020?

<p>The delivery to the Owner of such operations and maintenance documents reasonably necessary for immediate operation and maintenance, as required by the Contract Documents. (D)</p> Signup and view all the answers

What is the purpose of publishing a certificate of substantial performance in a construction trade newspaper?

<p>To notify subcontractors and suppliers of the project's completion (A)</p> Signup and view all the answers

Which of the following is NOT a type of building occupancy mentioned in the text?

<p>Final Occupancy (D)</p> Signup and view all the answers

What is the purpose of commissioning in the context of building construction?

<p>To verify that the facility design and construction meet the client's objectives and requirements (C)</p> Signup and view all the answers

When does unconditional occupancy occur?

<p>When the building is compliant with the life and safety portion of the building code (A)</p> Signup and view all the answers

What is the role of the authority having jurisdiction in the issuance of an occupancy permit?

<p>To issue the occupancy permit or authorize conditional or phased occupancy (D)</p> Signup and view all the answers

Which of the following is NOT a part of the architect's basic services during the close-out phase of a construction project?

<p>Post-occupancy evaluation (A)</p> Signup and view all the answers

What is the purpose of commissioning in the context of a construction project?

<p>To ensure that new building systems perform according to the documented design intent and the owner's operational needs (D)</p> Signup and view all the answers

Which of the following is true about commissioning and takeover in the context of a construction project?

<p>Commissioning starts when a project nears construction completion, while takeover starts when a project is completed (D)</p> Signup and view all the answers

What is the purpose of post-occupancy evaluation in the context of a construction project?

<p>To investigate and assess the performance of completed buildings (C)</p> Signup and view all the answers

More Like This

Pre-Occupancy Services Commissioning Quiz
56 questions
Pre-Occupancy Services Commissioning Quiz
26 questions
Pre-Occupancy Services Commissioning
30 questions
Pre-occupancy Services Commissioning
26 questions
Use Quizgecko on...
Browser
Browser