Pre-Occupancy Services Commissioning
26 Questions
0 Views

Pre-Occupancy Services Commissioning

Created by
@WorthwhilePyrite5473

Questions and Answers

Which document attests that the contract between the owner and the contractor is substantially complete?

  • Guaranty
  • Holdback
  • Definitions Certificate
  • Certificate of Substantial Performance (correct)
  • What is a three-party agreement in which a third party guarantees the performance of an obligation to the second party in the event of default of the first party?

  • Holdback
  • Guaranty (correct)
  • Certificate of Substantial Performance
  • Definitions Certificate
  • What is the act of keeping a building system, process, or property in proper and efficient working condition?

  • Ready-for-Takeover
  • Maintenance (correct)
  • Lien
  • Post-occupancy Evaluation
  • Which stage of a project does Pre-occupancy Services Commissioning typically begin at?

    <p>Pre-design stage</p> Signup and view all the answers

    According to the text, who is responsible for reviewing defects and deficiencies during the warranty period on behalf of the client?

    <p>The architect</p> Signup and view all the answers

    What should the architect do prior to the anniversary date of the one-year warranty?

    <p>Arrange a review of the project</p> Signup and view all the answers

    What is the purpose of commissioning in the construction process?

    <p>To achieve quality assurance</p> Signup and view all the answers

    What is the potential consequence of failure to verify during systems testing?

    <p>Delays and claims</p> Signup and view all the answers

    What may the architect do if the contractor fails to rectify a warranty item in a reasonable time?

    <p>Review the client's rights under the bonding and insurance provisions in the contract</p> Signup and view all the answers

    When can a building operator training program be started?

    <p>After conditional acceptance is established</p> Signup and view all the answers

    Which type of completion is often used on small projects when the time between substantial performance and total completion is short?

    <p>Deemed total completion</p> Signup and view all the answers

    Who prepares and issues the final certificate for payment?

    <p>Architect</p> Signup and view all the answers

    What is the purpose of the holdback monies?

    <p>To release monies previously invoiced for</p> Signup and view all the answers

    What is the purpose of a letter of assurance in some jurisdictions?

    <p>To certify that the building has been constructed in compliance with the building code</p> Signup and view all the answers

    According to the CCDC, which term is used to describe a list of factors that, once satisfied, result in project completion?

    <p>Ready-for-takeover</p> Signup and view all the answers

    What is a regulatory requirement of the contractor, rather than a contractual requirement?

    <p>Substantial performance</p> Signup and view all the answers

    Which of the following is NOT a prerequisite to attaining Ready-for-Takeover of the Work according to CCDC 2 2020?

    <p>The delivery to the Owner of such operations and maintenance documents reasonably necessary for immediate operation and maintenance, as required by the Contract Documents.</p> Signup and view all the answers

    What is the purpose of publishing a certificate of substantial performance in a construction trade newspaper?

    <p>To notify subcontractors and suppliers of the project's completion</p> Signup and view all the answers

    Which of the following is NOT a type of building occupancy mentioned in the text?

    <p>Final Occupancy</p> Signup and view all the answers

    What is the purpose of commissioning in the context of building construction?

    <p>To verify that the facility design and construction meet the client's objectives and requirements</p> Signup and view all the answers

    When does unconditional occupancy occur?

    <p>When the building is compliant with the life and safety portion of the building code</p> Signup and view all the answers

    What is the role of the authority having jurisdiction in the issuance of an occupancy permit?

    <p>To issue the occupancy permit or authorize conditional or phased occupancy</p> Signup and view all the answers

    Which of the following is NOT a part of the architect's basic services during the close-out phase of a construction project?

    <p>Post-occupancy evaluation</p> Signup and view all the answers

    What is the purpose of commissioning in the context of a construction project?

    <p>To ensure that new building systems perform according to the documented design intent and the owner's operational needs</p> Signup and view all the answers

    Which of the following is true about commissioning and takeover in the context of a construction project?

    <p>Commissioning starts when a project nears construction completion, while takeover starts when a project is completed</p> Signup and view all the answers

    What is the purpose of post-occupancy evaluation in the context of a construction project?

    <p>To investigate and assess the performance of completed buildings</p> Signup and view all the answers

    More Quizzes Like This

    Pre-Occupancy Services Commissioning
    26 questions
    Pre-Occupancy Services Commissioning Quiz
    56 questions
    Pre-Occupancy Services Commissioning Quiz
    26 questions
    Pre-occupancy Services Commissioning
    26 questions
    Use Quizgecko on...
    Browser
    Browser