Pre-Occupancy Services Commissioning Quiz
56 Questions
2 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

Which document attests to the truth of a fact in construction?

  • Guaranty
  • Maintenance
  • Certificate of Substantial Performance (correct)
  • Holdback
  • What is a three-party agreement that guarantees the performance of an obligation?

  • Certificate
  • Lien
  • Guaranty (correct)
  • Post-occupancy Evaluation
  • What is the term used to describe a set of requirements that must be satisfied prior to achieving a financial milestone?

  • Holdback
  • Ready-for-Takeover (correct)
  • Certificate
  • Lien
  • Which party is responsible for reviewing defects and deficiencies during the warranty period on behalf of the client?

    <p>The architect</p> Signup and view all the answers

    When should the architect arrange a review of the project?

    <p>On the anniversary date of the one-year warranty</p> Signup and view all the answers

    What happens if the contractor fails to rectify a warranty item in a reasonable time?

    <p>The client's rights under the bonding and insurance provisions may be reviewed</p> Signup and view all the answers

    During the commissioning process, the architect's responsibility is to communicate the design intent to the building constructor and the building operator.

    <p>True</p> Signup and view all the answers

    Which stage of the project does Pre-occupancy Services Commissioning typically begin?

    <p>Pre-design stage</p> Signup and view all the answers

    What is the purpose of commissioning in the construction process?

    <p>All of the above</p> Signup and view all the answers

    What does the component verification process involve?

    <p>Verifying compliance with specifications for each construction element</p> Signup and view all the answers

    According to the text, when does the warranty period commence?

    <p>On the date of total completion</p> Signup and view all the answers

    What does the architect do once all deficiencies have been corrected and all work under the contract has been completed?

    <p>Issues a final certificate for payment</p> Signup and view all the answers

    What does the architect prepare when issuing the release of the holdback certificate?

    <p>A certificate for the release of remaining statutory holdback monies</p> Signup and view all the answers

    What is the purpose of a letter of assurance?

    <p>To certify that a building has been constructed in compliance with the building code</p> Signup and view all the answers

    Which of the following is NOT a part of the architect's basic services during the project close-out phase?

    <p>Ensuring substantial performance of the building systems</p> Signup and view all the answers

    What is the purpose of commissioning in the construction project close-out phase?

    <p>To ensure substantial performance of the building systems</p> Signup and view all the answers

    Which of the following is true about post-occupancy evaluation?

    <p>It is conducted at six- or 12-month intervals</p> Signup and view all the answers

    What are takeover procedures in the construction project close-out phase?

    <p>Procedures for the orderly takeover and transition of the building project by the owner</p> Signup and view all the answers

    Which of the following is an example of conditional occupancy?

    <p>When a building is considered safe but a portion of the project is incomplete</p> Signup and view all the answers

    What is the purpose of commissioning in the construction process?

    <p>To transform the design of a facility into a fully integrated and operating system</p> Signup and view all the answers

    What is the role of the authority having jurisdiction in the occupancy process?

    <p>To issue an occupancy permit</p> Signup and view all the answers

    What is the recommended action for architects at the final step of a project?

    <p>To achieve unconditional (full) occupancy to close out the project</p> Signup and view all the answers

    Which of the following is a regulatory requirement for achieving 'ready-for-takeover' in a construction project?

    <p>Completion of final cleaning and waste removal</p> Signup and view all the answers

    What is the purpose of the certificate of substantial performance in a construction project?

    <p>To indicate that work has been substantially performed</p> Signup and view all the answers

    What is the warranty period start point in a CCDC 2 stipulated price contract?

    <p>Ready-for-takeover</p> Signup and view all the answers

    What can the contractor do to apply for an early release of the holdback related to a subcontractor's work?

    <p>Submit a certificate of substantial performance</p> Signup and view all the answers

    Which organization has adopted the term 'ready-for-takeover' in its standard contract forms?

    <p>The CCDC</p> Signup and view all the answers

    What is one of the prerequisites to attaining 'Ready-for-Takeover' of the Work?

    <p>Certification of substantial performance by the consultant</p> Signup and view all the answers

    What may the architect review to understand the definition of substantial performance?

    <p>The lien legislation</p> Signup and view all the answers

    When does the warranty period for a project commence in the case of a CCDC 2 stipulated price contract?

    <p>At substantial performance</p> Signup and view all the answers

    Which party guarantees the performance of an obligation in a three-party agreement?

    <p>The third party</p> Signup and view all the answers

    What is the purpose of a holdback in a construction contract?

    <p>To ensure the contractor's performance</p> Signup and view all the answers

    What is the purpose of a post-occupancy evaluation?

    <p>To assess the performance of a building after it has been occupied</p> Signup and view all the answers

    Which of the following is NOT a service provided by the architect during the project close-out phase?

    <p>Design and construction documents</p> Signup and view all the answers

    What is the purpose of commissioning in the construction project close-out phase?

    <p>To ensure the building systems perform according to the design intent</p> Signup and view all the answers

    When does the warranty period for a project commence in the case of a CCDC 2 stipulated price contract?

    <p>At project completion</p> Signup and view all the answers

    What is the role of the authority having jurisdiction in the occupancy process?

    <p>To review and approve the building design</p> Signup and view all the answers

    During the warranty period, the architect may conduct periodic reviews of the project to confirm that

    <p>the client's personnel understand the operations manuals</p> Signup and view all the answers

    What action may the architect take if the contractor fails to rectify a warranty item in a reasonable time?

    <p>Review the client's rights under the bonding and insurance provisions</p> Signup and view all the answers

    When should the architect arrange a review of the project?

    <p>Before the anniversary date of the one-year warranty</p> Signup and view all the answers

    Which of the following is NOT a factor leading to 'ready-for-takeover' in a construction project?

    <p>Final cleaning and waste removal</p> Signup and view all the answers

    What is one of the prerequisites to attaining 'Ready-for-Takeover' of the Work according to CCDC 2 2020?

    <p>Certification of substantial performance by the consultant</p> Signup and view all the answers

    What may the architect review to understand the definition of substantial performance?

    <p>The provincial or territorial lien legislation</p> Signup and view all the answers

    When does the warranty period for a project commence in the case of a CCDC 2 stipulated price contract?

    <p>Upon achieving 'ready-for-takeover'</p> Signup and view all the answers

    Which document does the architect prepare and issue once all deficiencies have been corrected and all work under the contract has been completed?

    <p>Certificate of Final Completion</p> Signup and view all the answers

    What is the purpose of a letter of assurance in the construction process?

    <p>To verify compliance with building codes and regulations</p> Signup and view all the answers

    When does the warranty period for a project commence in the case of a CCDC 2 stipulated price contract?

    <p>On the date of total completion</p> Signup and view all the answers

    What is the purpose of commissioning in the construction process?

    <p>To confirm that the building systems perform according to the design intent</p> Signup and view all the answers

    During the commissioning process, what is the architect's responsibility?

    <p>To communicate the design intent to the building constructor and the building operator</p> Signup and view all the answers

    What is the purpose of the component verification process?

    <p>To highlight variances from the specifications</p> Signup and view all the answers

    What can happen if verification and testing are not properly conducted during the commissioning process?

    <p>All of the above</p> Signup and view all the answers

    When does the contractor's schedule for the timing, sequencing, and proving of systems require regular commissioning meetings?

    <p>After all components within the system are accepted and deficiencies are corrected</p> Signup and view all the answers

    Which of the following is true about conditional occupancy?

    <p>It occurs when a building is considered safe but a portion of the project is incomplete with respect to the construction documents submitted for the building permit.</p> Signup and view all the answers

    What is the purpose of commissioning in the construction process?

    <p>To transform the design of a facility into a fully integrated and operating system.</p> Signup and view all the answers

    What is the role of the authority having jurisdiction in the occupancy process?

    <p>To issue the occupancy permit or notice of final inspection.</p> Signup and view all the answers

    What is the purpose of a commissioning agent in the construction process?

    <p>To verify that both the facility design and the resulting construction satisfy the client's objectives and requirements.</p> Signup and view all the answers

    More Like This

    Contract Administration Essentials
    30 questions
    R 2017 - 4
    37 questions

    R 2017 - 4

    AstoundedHamster avatar
    AstoundedHamster
    Psychology Goals and Constructs Quiz
    74 questions
    Use Quizgecko on...
    Browser
    Browser