Project hierarchy has each of these elements in a coordinated way to achieve the overall goal of the bigger project: Sub-projects, Sub-missions, Sub-expansions, Sub-developments.

Understand the Problem

The question seems incomplete but is asking about the elements involved in project hierarchy that need to be managed in a coordinated way to achieve the overall goal of the project.

Answer

Work Breakdown Structure (WBS)

The correct term is 'Work Breakdown Structure (WBS),' which divides a project into hierarchical levels, including sub-projects for coordinated management and achievement of overall project goals.

Answer for screen readers

The correct term is 'Work Breakdown Structure (WBS),' which divides a project into hierarchical levels, including sub-projects for coordinated management and achievement of overall project goals.

More Information

A Work Breakdown Structure (WBS) is crucial in project management for organizing and dividing major deliverables and project work into smaller, manageable components.

Tips

A common mistake is dividing the project based on tasks rather than deliverables, which can lead to confusion in planning and execution.

AI-generated content may contain errors. Please verify critical information

Thank you for voting!