Funding agreements with the Service materiel comments should be developed late in the alternative development process to ensure that the amounts, timing and responsibilities are de... Funding agreements with the Service materiel comments should be developed late in the alternative development process to ensure that the amounts, timing and responsibilities are detailed, accurate and up-to-date.
Understand the Problem
The question is a true or false statement regarding the development of funding agreements in relation to service materiel comments during the alternative development process.
Answer
False
The statement is False.
Answer for screen readers
The statement is False.
More Information
Funding agreements are typically developed early in the process to ensure proper planning and alignment with the program's goals and funding requirements.
Tips
A common mistake is assuming that delaying agreement development will reflect the most current information, but early development helps avoid misalignment with project objectives.