A project manager notices a significant delay in the completion of project tasks. After investigation, it is revealed that some team members lack the required skills for certain as... A project manager notices a significant delay in the completion of project tasks. After investigation, it is revealed that some team members lack the required skills for certain aspects of the project. What type of control measure should the project manager implement?
Understand the Problem
The question is asking about an appropriate control measure that a project manager should take in response to team members lacking the required skills for project tasks, considering the options provided.
Answer
Provide training for team members.
The project manager should implement feedforward control by providing relevant training for team members.
Answer for screen readers
The project manager should implement feedforward control by providing relevant training for team members.
More Information
Feedforward control anticipates problems before they occur by taking preventive measures such as skill development.
Tips
A common mistake is to adjust the timeline without addressing the root cause, which may lead to repeated delays.