Pre-Occupancy Services Commissioning
26 Questions
0 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to Lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

Which professional is responsible for preparing a certificate in the construction industry?

  • Engineer
  • Owner
  • Contractor
  • Architect (correct)

What is a certificate of substantial performance?

  • A document attesting to the truth of a fact
  • A certificate issued under the lien legislation (correct)
  • A percentage of monetary amount held as security
  • A three-party agreement guaranteeing performance

What is the purpose of a holdback in a construction contract?

  • To assess the performance of a building
  • To satisfy a debt owed to the property owner
  • To guarantee performance of an obligation
  • To provide security for a certain period (correct)

Who is responsible for reviewing defects and deficiencies during the warranty period on behalf of the client?

<p>The architect (C)</p> Signup and view all the answers

When should the architect arrange a review of the project?

<p>After the anniversary date of the one-year warranty (C)</p> Signup and view all the answers

What may the architect review if the contractor fails to rectify a warranty item in a reasonable time?

<p>The client's rights under the bonding and insurance provisions (B)</p> Signup and view all the answers

Which stage of a project does Pre-occupancy Services Commissioning begin at?

<p>Pre-design stage (B)</p> Signup and view all the answers

What is the purpose of commissioning in the construction process?

<p>To verify and test the building's systems (C)</p> Signup and view all the answers

What is the role of the commissioning agent in the bid documents?

<p>To prepare checklists for the verification of each construction element (D)</p> Signup and view all the answers

What can happen if verification and testing are not properly conducted during construction?

<p>Delays and claims (D)</p> Signup and view all the answers

Which phase of a construction project is often considered just as important as the design and construction documents?

<p>Post-occupancy evaluation (B)</p> Signup and view all the answers

What is the purpose of commissioning in a construction project?

<p>To ensure new building systems perform according to design intent (B)</p> Signup and view all the answers

Which phase starts when a construction project nears completion?

<p>Takeover procedures (D)</p> Signup and view all the answers

What is the responsibility of the architect during the warranty period of a construction project?

<p>To review defects and deficiencies and notify the contractor (D)</p> Signup and view all the answers

Which of the following is true about the warranty period in this case?

<p>The warranty period starts on the date of total completion. (D)</p> Signup and view all the answers

When does the final certificate for payment get issued?

<p>When all deficiencies have been corrected and all work under the contract is completed. (A)</p> Signup and view all the answers

What is the purpose of the certificate for the release of remaining statutory holdback monies?

<p>To authorize payment of the holdback amount. (A)</p> Signup and view all the answers

What is the purpose of the letter of assurance?

<p>To ensure compliance with the building code. (B)</p> Signup and view all the answers

Which of the following is a situation in which occupancy of a building may occur before the completion of the entire project?

<p>Phased Occupancy (A)</p> Signup and view all the answers

What is the role of the authority having jurisdiction in the issuance of an occupancy permit?

<p>To issue an occupancy permit only for buildings that meet the permit conditions or substantial building code compliance (C)</p> Signup and view all the answers

What is the purpose of commissioning in the construction process?

<p>To verify that the facility design and construction satisfy the client's objectives and requirements (A)</p> Signup and view all the answers

What additional services may be justified for phased occupancies in a construction project?

<p>Commissioning services (D)</p> Signup and view all the answers

Which organization has adopted the term 'ready-for-takeover' in its standard contract forms?

<p>CCDC (D)</p> Signup and view all the answers

What is one of the factors leading to 'ready-for-takeover'?

<p>All of the above (D)</p> Signup and view all the answers

What may the contractor apply for under the terms and conditions of CCDC 2 – Stipulated Price Contract?

<p>Early release of the holdback related to both subcontractor's and supplier's work (D)</p> Signup and view all the answers

What serves as formal notification to all subcontractors and suppliers who have the right to place a lien on the project?

<p>The publication date of the certificate (C)</p> Signup and view all the answers

More Like This

Pre-Occupancy Services Commissioning
26 questions
Pre-Occupancy Services Commissioning Quiz
56 questions
Pre-Occupancy Services Commissioning Quiz
26 questions
Pre-occupancy Services Commissioning
26 questions