PMGT3623 Scheduling - Week 3 Quiz
54 Questions
0 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

What is the main focus of Week 03 in the PMGT3623 course?

  • Implementation of Project Network Diagram using Microsoft Project
  • Define and Sequence Project Tasks
  • Project Network Diagram (Discrete Approach) (correct)
  • Complex Task Allocation Approach
  • Which method is mentioned as a part of the Project Network Diagram covered in Week 03?

  • Precedence Diagramming Method (correct)
  • Gantt Chart Method
  • Critical Path Method
  • Critical Chain Method
  • What percent weight does the final exam carry in the PMGT3623 assessments?

  • 50%
  • 40% (correct)
  • 20%
  • 30%
  • What is one limitation of the discrete approach to Project Network Diagrams?

    <p>It can overlook variability in task durations.</p> Signup and view all the answers

    Which week includes a Knowledge Test in the PMGT3623 course schedule?

    <p>Week 7</p> Signup and view all the answers

    The project duration and critical path are topics covered in which week?

    <p>Week 3</p> Signup and view all the answers

    What is required for the Group Assignment Report Submission in PMGT3623?

    <p>Submission by 11:59 pm on a Friday of Week 13</p> Signup and view all the answers

    What is the first task in the Building Gate and Fence Project?

    <p>Dig holes</p> Signup and view all the answers

    What is the total duration of the critical path A → C → F → G?

    <p>12 months</p> Signup and view all the answers

    Which activity has a duration of 1 month?

    <p>Activity D</p> Signup and view all the answers

    Which of the following activities does not depend on another activity?

    <p>Activity A</p> Signup and view all the answers

    What is the duration of Activity E?

    <p>4 months</p> Signup and view all the answers

    Which activity leads directly to Activity F?

    <p>Activity C</p> Signup and view all the answers

    Which activities are dependent on Activity D?

    <p>Activities G and H</p> Signup and view all the answers

    What is the relationship between Activities E and J?

    <p>They are independent</p> Signup and view all the answers

    What can happen to the critical path if the performance of one of its tasks improves?

    <p>It could become shorter.</p> Signup and view all the answers

    What defines a near-critical path?

    <p>It's a path that can become critical with slight changes.</p> Signup and view all the answers

    Which task has the longest duration in the critical path example provided?

    <p>Task B</p> Signup and view all the answers

    What issue arises from using a discrete approach for task duration allocation in complex projects?

    <p>It can result in wrong or biased estimations</p> Signup and view all the answers

    In the provided content, which of the following is a critical path?

    <p>A→C→F→G</p> Signup and view all the answers

    What does the task notation 'A(4)' signify?

    <p>Task A has a duration of 4 days.</p> Signup and view all the answers

    What does a probabilistic outcome imply about task completion times?

    <p>There is a level of uncertainty in the completion times</p> Signup and view all the answers

    What is implied by the term 'deterministic approach' in task duration allocation?

    <p>It assumes a fixed duration for tasks</p> Signup and view all the answers

    Which of the following is NOT a characteristic of a critical path?

    <p>Delays in this path do not affect the project completion time.</p> Signup and view all the answers

    According to the task layout presented, which near-critical path can also be considered valid?

    <p>A→D→I</p> Signup and view all the answers

    How confident can we be about completing a task within a specific timeframe, according to the content?

    <p>It is highly probable but not guaranteed</p> Signup and view all the answers

    What is a critical path?

    <p>The longest path through a project that dictates project duration</p> Signup and view all the answers

    What can affect the duration of a critical path task?

    <p>Improvement in task performance.</p> Signup and view all the answers

    During project execution, how can a near-critical path change?

    <p>It may become a critical path</p> Signup and view all the answers

    Why might a discrete approach be acceptable for simple projects?

    <p>Simple projects have less variability</p> Signup and view all the answers

    What does Total Slack represent?

    <p>The difference between late and early finish times.</p> Signup and view all the answers

    Which path consists of tasks that have a slack time of 0?

    <p>Critical path</p> Signup and view all the answers

    Why is slack time crucial for project managers?

    <p>It identifies the potential risks in scheduling.</p> Signup and view all the answers

    How does slack time contribute to project flexibility?

    <p>By allowing adjustments without delaying the project.</p> Signup and view all the answers

    What characterizes a near-critical path?

    <p>It can become critical if durations change.</p> Signup and view all the answers

    What effect does a task with little or no slack time have on a project?

    <p>It can increase the project's schedule risk.</p> Signup and view all the answers

    Which equation correctly represents Total Slack?

    <p>Total Slack = Late Start - Early Start</p> Signup and view all the answers

    What role does slack time play in resource allocation?

    <p>It helps prioritize critical tasks over non-critical tasks.</p> Signup and view all the answers

    What do tasks on the critical path imply about project delays?

    <p>Delays in these tasks will cause delays in the entire project.</p> Signup and view all the answers

    If Float (H) in a project is calculated as 12 - 9, what is the value?

    <p>3</p> Signup and view all the answers

    What is the purpose of performing a forward pass in project management?

    <p>To set the earliest start and finish dates for tasks.</p> Signup and view all the answers

    Which of the following formulas is used to calculate the Early Finish (EF) date?

    <p>ES + duration = EF</p> Signup and view all the answers

    What does the backward pass method primarily help to determine?

    <p>The latest start and finish dates for tasks.</p> Signup and view all the answers

    When multiple predecessors exist for a successor task, what date should the Early Start (ES) for the successor be based on?

    <p>The latest EF date of all predecessors.</p> Signup and view all the answers

    What happens to the Late Start (LS) of a predecessor when it has multiple successors?

    <p>Use the earliest LS date of the successors.</p> Signup and view all the answers

    What determines the critical path in a project?

    <p>The longest path through the project that defines the shortest time to complete it.</p> Signup and view all the answers

    How is slack time in a project defined?

    <p>Time that can be delayed without affecting the project schedule.</p> Signup and view all the answers

    In project management, what is a common requirement for identifying the critical path?

    <p>Performing both forward and backward passes.</p> Signup and view all the answers

    What indicates that a project has no defined critical path?

    <p>Some tasks do not connect throughout the network.</p> Signup and view all the answers

    Which of the following formulas is used to calculate the Late Finish (LF)?

    <p>LF - duration = LS</p> Signup and view all the answers

    What does the term 'float time' refer to?

    <p>Time a task can slip without affecting the project timeline.</p> Signup and view all the answers

    Why is the critical path crucial for project managers?

    <p>It indicates the longest duration and helps prioritize tasks.</p> Signup and view all the answers

    What is established first when performing project scheduling?

    <p>Identifying task dependencies.</p> Signup and view all the answers

    In a project network diagram, which aspect does not affect the critical path?

    <p>Number of resources allocated to tasks.</p> Signup and view all the answers

    Study Notes

    PMGT3623 Scheduling - Week 3

    • Topic: Project Network Diagram (Discrete Approach)

    Acknowledgement of Country

    • Acknowledges the Traditional Owners of Australia and their continuing connection to land, water, and culture.
    • Acknowledges connection to the Gadigal people of the Eora Nation.

    PMGT3623 Overview - Week 3

    • Week 3 Topic: Project Network Diagram (Discrete Approach)

    PMGT3623 Assessments

    • Weekly Participation: 10%, W2-W6; W9-W10 (Best 6 out of 7)
    • Knowledge Test: 20%, W7
    • Group Assignment Presentation (Part A): 10%, W12 and W13
    • Group Assignment Report Submission (Part B): 20%, Friday of W13 (By 11:59 pm)
    • Final Exam: 40%, Exam Week

    Topics Covered - Week 3: Project Network Diagram (Discrete Approach)

    • What is a Project Network Diagram?
    • Different approaches to the Project Network Diagram
      • Precedence Diagramming Method
      • Other Approaches
    • Project Duration, Critical Path and Near-Critical Path
    • Limitation of Discrete Approach to Project Network Diagram

    Network Diagram

    • Building Gate and Fence Project:
      • First task: Dig Holes
      • Buy Wood and Buy Gate can start after Dig Holes. -Erect Fence requires Buy Wood -Buy Paint requires Buy Gate -Erect Gate requires Erect Fence and Buy Paint -Paint Fence requires Erect Gate -Paint Gate requires Paint Fence -Network diagrams are visual representations of a project's schedule. -Illustrates logical events leading to project completion. -Used to plan and track projects from start to finish. -Represent critical path and project scope. -Used for ease of readability to show activity sequence, and parallel activities, and connections between activities.
    • Rules of Thumb for Network Diagrams:
      • Starting point
      • Ending point -Predecessors for all activities (except the start point) -Successors for all activities (except the endpoint) -No loops or hangers

    Precedence Diagramming Method (PDM)

    • Node represents activity
    • Also known as activity-on-node (AON) diagrams

    Other Approaches for Network Diagram

    • Arrow Diagramming Method
    • Critical Chain Approach
    • Line of Balance Approach
    • Advanced Work Package Approach
    • Beeline Diagramming Method
    • Chronographic Modeling Approach
    • Timeboxing
    • Kanban

    Critical Path

    • Critical Path: The sequence of activities that determine the duration of the project. It's the longest path through the project.
    • Forward Pass: Identifies early start (ES) and early finish (EF) dates.
    • Backward Pass: Identifies the late start (LS) and late finish (LF) dates. -Use formulas (ES + duration = EF) and (EF + lag = ES, EF – lead = ES) for successors.
    • Important for project managers to calculate slack times -Tasks on the critical path have a slack of 0

    Slack Time (Float Time)

    • Amount of time a task can be delayed without delaying project completion or subsequent task start.
    • Total Slack = Late Finish – Early Finish or Total Slack = Late Start – Early Start

    Near-Critical Path

    • One or more paths in the project that are not initially critical but may become critical due to events like longer durations or improved performance of non-critical tasks. -Probabilistic outcome of task/task duration plays a major variable.

    Review Questions

    • Differences between critical and near-critical paths
    • Network diagrams with zero critical paths or zero near-critical paths
    • Calculation of task slack time, and its importance for project managers.
    • Tasks with zero slack
    • Loops in a network diagram
    • Rules of thumb for drawing network diagrams

    Studying That Suits You

    Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

    Quiz Team

    Related Documents

    Description

    Test your knowledge on the Project Network Diagram as covered in PMGT3623 Week 3. This quiz will explore different approaches to creating network diagrams, critical paths, and project duration analysis. Enhance your understanding of key concepts that are crucial for successful project management.

    More Like This

    Use Quizgecko on...
    Browser
    Browser