Questions and Answers
What is the main focus of Week 03 in the PMGT3623 course?
What is the main focus of Week 03 in the PMGT3623 course?
- Implementation of Project Network Diagram using Microsoft Project
- Define and Sequence Project Tasks
- Project Network Diagram (Discrete Approach) (correct)
- Complex Task Allocation Approach
Which method is mentioned as a part of the Project Network Diagram covered in Week 03?
Which method is mentioned as a part of the Project Network Diagram covered in Week 03?
- Precedence Diagramming Method (correct)
- Gantt Chart Method
- Critical Path Method
- Critical Chain Method
What percent weight does the final exam carry in the PMGT3623 assessments?
What percent weight does the final exam carry in the PMGT3623 assessments?
- 50%
- 40% (correct)
- 20%
- 30%
What is one limitation of the discrete approach to Project Network Diagrams?
What is one limitation of the discrete approach to Project Network Diagrams?
Which week includes a Knowledge Test in the PMGT3623 course schedule?
Which week includes a Knowledge Test in the PMGT3623 course schedule?
The project duration and critical path are topics covered in which week?
The project duration and critical path are topics covered in which week?
What is required for the Group Assignment Report Submission in PMGT3623?
What is required for the Group Assignment Report Submission in PMGT3623?
What is the first task in the Building Gate and Fence Project?
What is the first task in the Building Gate and Fence Project?
What is the total duration of the critical path A → C → F → G?
What is the total duration of the critical path A → C → F → G?
Which activity has a duration of 1 month?
Which activity has a duration of 1 month?
Which of the following activities does not depend on another activity?
Which of the following activities does not depend on another activity?
What is the duration of Activity E?
What is the duration of Activity E?
Which activity leads directly to Activity F?
Which activity leads directly to Activity F?
Which activities are dependent on Activity D?
Which activities are dependent on Activity D?
What is the relationship between Activities E and J?
What is the relationship between Activities E and J?
What can happen to the critical path if the performance of one of its tasks improves?
What can happen to the critical path if the performance of one of its tasks improves?
What defines a near-critical path?
What defines a near-critical path?
Which task has the longest duration in the critical path example provided?
Which task has the longest duration in the critical path example provided?
What issue arises from using a discrete approach for task duration allocation in complex projects?
What issue arises from using a discrete approach for task duration allocation in complex projects?
In the provided content, which of the following is a critical path?
In the provided content, which of the following is a critical path?
What does the task notation 'A(4)' signify?
What does the task notation 'A(4)' signify?
What does a probabilistic outcome imply about task completion times?
What does a probabilistic outcome imply about task completion times?
What is implied by the term 'deterministic approach' in task duration allocation?
What is implied by the term 'deterministic approach' in task duration allocation?
Which of the following is NOT a characteristic of a critical path?
Which of the following is NOT a characteristic of a critical path?
According to the task layout presented, which near-critical path can also be considered valid?
According to the task layout presented, which near-critical path can also be considered valid?
How confident can we be about completing a task within a specific timeframe, according to the content?
How confident can we be about completing a task within a specific timeframe, according to the content?
What is a critical path?
What is a critical path?
What can affect the duration of a critical path task?
What can affect the duration of a critical path task?
During project execution, how can a near-critical path change?
During project execution, how can a near-critical path change?
Why might a discrete approach be acceptable for simple projects?
Why might a discrete approach be acceptable for simple projects?
What does Total Slack represent?
What does Total Slack represent?
Which path consists of tasks that have a slack time of 0?
Which path consists of tasks that have a slack time of 0?
Why is slack time crucial for project managers?
Why is slack time crucial for project managers?
How does slack time contribute to project flexibility?
How does slack time contribute to project flexibility?
What characterizes a near-critical path?
What characterizes a near-critical path?
What effect does a task with little or no slack time have on a project?
What effect does a task with little or no slack time have on a project?
Which equation correctly represents Total Slack?
Which equation correctly represents Total Slack?
What role does slack time play in resource allocation?
What role does slack time play in resource allocation?
What do tasks on the critical path imply about project delays?
What do tasks on the critical path imply about project delays?
If Float (H) in a project is calculated as 12 - 9, what is the value?
If Float (H) in a project is calculated as 12 - 9, what is the value?
What is the purpose of performing a forward pass in project management?
What is the purpose of performing a forward pass in project management?
Which of the following formulas is used to calculate the Early Finish (EF) date?
Which of the following formulas is used to calculate the Early Finish (EF) date?
What does the backward pass method primarily help to determine?
What does the backward pass method primarily help to determine?
When multiple predecessors exist for a successor task, what date should the Early Start (ES) for the successor be based on?
When multiple predecessors exist for a successor task, what date should the Early Start (ES) for the successor be based on?
What happens to the Late Start (LS) of a predecessor when it has multiple successors?
What happens to the Late Start (LS) of a predecessor when it has multiple successors?
What determines the critical path in a project?
What determines the critical path in a project?
How is slack time in a project defined?
How is slack time in a project defined?
In project management, what is a common requirement for identifying the critical path?
In project management, what is a common requirement for identifying the critical path?
What indicates that a project has no defined critical path?
What indicates that a project has no defined critical path?
Which of the following formulas is used to calculate the Late Finish (LF)?
Which of the following formulas is used to calculate the Late Finish (LF)?
What does the term 'float time' refer to?
What does the term 'float time' refer to?
Why is the critical path crucial for project managers?
Why is the critical path crucial for project managers?
What is established first when performing project scheduling?
What is established first when performing project scheduling?
In a project network diagram, which aspect does not affect the critical path?
In a project network diagram, which aspect does not affect the critical path?
Flashcards
Project Network Diagram
Project Network Diagram
A visual representation of project tasks and their dependencies, used to plan and track project progress.
Precedence Diagramming Method
Precedence Diagramming Method
A method for creating a project network diagram where tasks are connected based on their dependencies.
Project Duration
Project Duration
The total time required to complete all the tasks in the project.
Critical Path
Critical Path
Signup and view all the flashcards
Near-Critical Path
Near-Critical Path
Signup and view all the flashcards
Discrete Approach
Discrete Approach
Signup and view all the flashcards
Task Dependencies
Task Dependencies
Signup and view all the flashcards
Building Gate and Fence Project
Building Gate and Fence Project
Signup and view all the flashcards
Forward Pass
Forward Pass
Signup and view all the flashcards
Backward Pass
Backward Pass
Signup and view all the flashcards
Early Start (ES)
Early Start (ES)
Signup and view all the flashcards
Early Finish (EF)
Early Finish (EF)
Signup and view all the flashcards
Late Start (LS)
Late Start (LS)
Signup and view all the flashcards
Late Finish (LF)
Late Finish (LF)
Signup and view all the flashcards
Slack Time
Slack Time
Signup and view all the flashcards
Network Diagram
Network Diagram
Signup and view all the flashcards
Project Management
Project Management
Signup and view all the flashcards
Task Duration
Task Duration
Signup and view all the flashcards
Dependencies
Dependencies
Signup and view all the flashcards
Successors
Successors
Signup and view all the flashcards
Predecessors
Predecessors
Signup and view all the flashcards
Lag
Lag
Signup and view all the flashcards
Lead
Lead
Signup and view all the flashcards
What is Slack?
What is Slack?
Signup and view all the flashcards
Slack on Critical Path
Slack on Critical Path
Signup and view all the flashcards
Slack for Resource Allocation
Slack for Resource Allocation
Signup and view all the flashcards
Slack and Risk
Slack and Risk
Signup and view all the flashcards
Slack and Project Flexibility
Slack and Project Flexibility
Signup and view all the flashcards
Probabilistic Outcome
Probabilistic Outcome
Signup and view all the flashcards
Impact of Delay on Near-Critical Path
Impact of Delay on Near-Critical Path
Signup and view all the flashcards
Managing Near-Critical Paths
Managing Near-Critical Paths
Signup and view all the flashcards
Critical Path Shortening
Critical Path Shortening
Signup and view all the flashcards
Near-Critical Path Promotion
Near-Critical Path Promotion
Signup and view all the flashcards
Project Network Diagram: Task Dependencies
Project Network Diagram: Task Dependencies
Signup and view all the flashcards
Why are Near-Critical Paths important?
Why are Near-Critical Paths important?
Signup and view all the flashcards
What is a critical path?
What is a critical path?
Signup and view all the flashcards
Impact of task duration reduction
Impact of task duration reduction
Signup and view all the flashcards
How to Identify Near-Critical Paths
How to Identify Near-Critical Paths
Signup and view all the flashcards
Why Discrete Approach is Limited
Why Discrete Approach is Limited
Signup and view all the flashcards
Comparing Discrete & Probabilistic
Comparing Discrete & Probabilistic
Signup and view all the flashcards
Why Probabilistic Outcome is Important
Why Probabilistic Outcome is Important
Signup and view all the flashcards
Study Notes
PMGT3623 Scheduling - Week 3
- Topic: Project Network Diagram (Discrete Approach)
Acknowledgement of Country
- Acknowledges the Traditional Owners of Australia and their continuing connection to land, water, and culture.
- Acknowledges connection to the Gadigal people of the Eora Nation.
PMGT3623 Overview - Week 3
- Week 3 Topic: Project Network Diagram (Discrete Approach)
PMGT3623 Assessments
- Weekly Participation: 10%, W2-W6; W9-W10 (Best 6 out of 7)
- Knowledge Test: 20%, W7
- Group Assignment Presentation (Part A): 10%, W12 and W13
- Group Assignment Report Submission (Part B): 20%, Friday of W13 (By 11:59 pm)
- Final Exam: 40%, Exam Week
Topics Covered - Week 3: Project Network Diagram (Discrete Approach)
- What is a Project Network Diagram?
- Different approaches to the Project Network Diagram
- Precedence Diagramming Method
- Other Approaches
- Project Duration, Critical Path and Near-Critical Path
- Limitation of Discrete Approach to Project Network Diagram
Network Diagram
- Building Gate and Fence Project:
- First task: Dig Holes
- Buy Wood and Buy Gate can start after Dig Holes. -Erect Fence requires Buy Wood -Buy Paint requires Buy Gate -Erect Gate requires Erect Fence and Buy Paint -Paint Fence requires Erect Gate -Paint Gate requires Paint Fence -Network diagrams are visual representations of a project's schedule. -Illustrates logical events leading to project completion. -Used to plan and track projects from start to finish. -Represent critical path and project scope. -Used for ease of readability to show activity sequence, and parallel activities, and connections between activities.
- Rules of Thumb for Network Diagrams:
- Starting point
- Ending point -Predecessors for all activities (except the start point) -Successors for all activities (except the endpoint) -No loops or hangers
Precedence Diagramming Method (PDM)
- Node represents activity
- Also known as activity-on-node (AON) diagrams
Other Approaches for Network Diagram
- Arrow Diagramming Method
- Critical Chain Approach
- Line of Balance Approach
- Advanced Work Package Approach
- Beeline Diagramming Method
- Chronographic Modeling Approach
- Timeboxing
- Kanban
Critical Path
- Critical Path: The sequence of activities that determine the duration of the project. It's the longest path through the project.
- Forward Pass: Identifies early start (ES) and early finish (EF) dates.
- Backward Pass: Identifies the late start (LS) and late finish (LF) dates. -Use formulas (ES + duration = EF) and (EF + lag = ES, EF – lead = ES) for successors.
- Important for project managers to calculate slack times -Tasks on the critical path have a slack of 0
Slack Time (Float Time)
- Amount of time a task can be delayed without delaying project completion or subsequent task start.
- Total Slack = Late Finish – Early Finish or Total Slack = Late Start – Early Start
Near-Critical Path
- One or more paths in the project that are not initially critical but may become critical due to events like longer durations or improved performance of non-critical tasks. -Probabilistic outcome of task/task duration plays a major variable.
Review Questions
- Differences between critical and near-critical paths
- Network diagrams with zero critical paths or zero near-critical paths
- Calculation of task slack time, and its importance for project managers.
- Tasks with zero slack
- Loops in a network diagram
- Rules of thumb for drawing network diagrams
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Related Documents
Description
Test your knowledge on the Project Network Diagram as covered in PMGT3623 Week 3. This quiz will explore different approaches to creating network diagrams, critical paths, and project duration analysis. Enhance your understanding of key concepts that are crucial for successful project management.