Podcast
Questions and Answers
What is the main focus of Week 03 in the PMGT3623 course?
What is the main focus of Week 03 in the PMGT3623 course?
Which method is mentioned as a part of the Project Network Diagram covered in Week 03?
Which method is mentioned as a part of the Project Network Diagram covered in Week 03?
What percent weight does the final exam carry in the PMGT3623 assessments?
What percent weight does the final exam carry in the PMGT3623 assessments?
What is one limitation of the discrete approach to Project Network Diagrams?
What is one limitation of the discrete approach to Project Network Diagrams?
Signup and view all the answers
Which week includes a Knowledge Test in the PMGT3623 course schedule?
Which week includes a Knowledge Test in the PMGT3623 course schedule?
Signup and view all the answers
The project duration and critical path are topics covered in which week?
The project duration and critical path are topics covered in which week?
Signup and view all the answers
What is required for the Group Assignment Report Submission in PMGT3623?
What is required for the Group Assignment Report Submission in PMGT3623?
Signup and view all the answers
What is the first task in the Building Gate and Fence Project?
What is the first task in the Building Gate and Fence Project?
Signup and view all the answers
What is the total duration of the critical path A → C → F → G?
What is the total duration of the critical path A → C → F → G?
Signup and view all the answers
Which activity has a duration of 1 month?
Which activity has a duration of 1 month?
Signup and view all the answers
Which of the following activities does not depend on another activity?
Which of the following activities does not depend on another activity?
Signup and view all the answers
What is the duration of Activity E?
What is the duration of Activity E?
Signup and view all the answers
Which activity leads directly to Activity F?
Which activity leads directly to Activity F?
Signup and view all the answers
Which activities are dependent on Activity D?
Which activities are dependent on Activity D?
Signup and view all the answers
What is the relationship between Activities E and J?
What is the relationship between Activities E and J?
Signup and view all the answers
What can happen to the critical path if the performance of one of its tasks improves?
What can happen to the critical path if the performance of one of its tasks improves?
Signup and view all the answers
What defines a near-critical path?
What defines a near-critical path?
Signup and view all the answers
Which task has the longest duration in the critical path example provided?
Which task has the longest duration in the critical path example provided?
Signup and view all the answers
What issue arises from using a discrete approach for task duration allocation in complex projects?
What issue arises from using a discrete approach for task duration allocation in complex projects?
Signup and view all the answers
In the provided content, which of the following is a critical path?
In the provided content, which of the following is a critical path?
Signup and view all the answers
What does the task notation 'A(4)' signify?
What does the task notation 'A(4)' signify?
Signup and view all the answers
What does a probabilistic outcome imply about task completion times?
What does a probabilistic outcome imply about task completion times?
Signup and view all the answers
What is implied by the term 'deterministic approach' in task duration allocation?
What is implied by the term 'deterministic approach' in task duration allocation?
Signup and view all the answers
Which of the following is NOT a characteristic of a critical path?
Which of the following is NOT a characteristic of a critical path?
Signup and view all the answers
According to the task layout presented, which near-critical path can also be considered valid?
According to the task layout presented, which near-critical path can also be considered valid?
Signup and view all the answers
How confident can we be about completing a task within a specific timeframe, according to the content?
How confident can we be about completing a task within a specific timeframe, according to the content?
Signup and view all the answers
What is a critical path?
What is a critical path?
Signup and view all the answers
What can affect the duration of a critical path task?
What can affect the duration of a critical path task?
Signup and view all the answers
During project execution, how can a near-critical path change?
During project execution, how can a near-critical path change?
Signup and view all the answers
Why might a discrete approach be acceptable for simple projects?
Why might a discrete approach be acceptable for simple projects?
Signup and view all the answers
What does Total Slack represent?
What does Total Slack represent?
Signup and view all the answers
Which path consists of tasks that have a slack time of 0?
Which path consists of tasks that have a slack time of 0?
Signup and view all the answers
Why is slack time crucial for project managers?
Why is slack time crucial for project managers?
Signup and view all the answers
How does slack time contribute to project flexibility?
How does slack time contribute to project flexibility?
Signup and view all the answers
What characterizes a near-critical path?
What characterizes a near-critical path?
Signup and view all the answers
What effect does a task with little or no slack time have on a project?
What effect does a task with little or no slack time have on a project?
Signup and view all the answers
Which equation correctly represents Total Slack?
Which equation correctly represents Total Slack?
Signup and view all the answers
What role does slack time play in resource allocation?
What role does slack time play in resource allocation?
Signup and view all the answers
What do tasks on the critical path imply about project delays?
What do tasks on the critical path imply about project delays?
Signup and view all the answers
If Float (H) in a project is calculated as 12 - 9, what is the value?
If Float (H) in a project is calculated as 12 - 9, what is the value?
Signup and view all the answers
What is the purpose of performing a forward pass in project management?
What is the purpose of performing a forward pass in project management?
Signup and view all the answers
Which of the following formulas is used to calculate the Early Finish (EF) date?
Which of the following formulas is used to calculate the Early Finish (EF) date?
Signup and view all the answers
What does the backward pass method primarily help to determine?
What does the backward pass method primarily help to determine?
Signup and view all the answers
When multiple predecessors exist for a successor task, what date should the Early Start (ES) for the successor be based on?
When multiple predecessors exist for a successor task, what date should the Early Start (ES) for the successor be based on?
Signup and view all the answers
What happens to the Late Start (LS) of a predecessor when it has multiple successors?
What happens to the Late Start (LS) of a predecessor when it has multiple successors?
Signup and view all the answers
What determines the critical path in a project?
What determines the critical path in a project?
Signup and view all the answers
How is slack time in a project defined?
How is slack time in a project defined?
Signup and view all the answers
In project management, what is a common requirement for identifying the critical path?
In project management, what is a common requirement for identifying the critical path?
Signup and view all the answers
What indicates that a project has no defined critical path?
What indicates that a project has no defined critical path?
Signup and view all the answers
Which of the following formulas is used to calculate the Late Finish (LF)?
Which of the following formulas is used to calculate the Late Finish (LF)?
Signup and view all the answers
What does the term 'float time' refer to?
What does the term 'float time' refer to?
Signup and view all the answers
Why is the critical path crucial for project managers?
Why is the critical path crucial for project managers?
Signup and view all the answers
What is established first when performing project scheduling?
What is established first when performing project scheduling?
Signup and view all the answers
In a project network diagram, which aspect does not affect the critical path?
In a project network diagram, which aspect does not affect the critical path?
Signup and view all the answers
Study Notes
PMGT3623 Scheduling - Week 3
- Topic: Project Network Diagram (Discrete Approach)
Acknowledgement of Country
- Acknowledges the Traditional Owners of Australia and their continuing connection to land, water, and culture.
- Acknowledges connection to the Gadigal people of the Eora Nation.
PMGT3623 Overview - Week 3
- Week 3 Topic: Project Network Diagram (Discrete Approach)
PMGT3623 Assessments
- Weekly Participation: 10%, W2-W6; W9-W10 (Best 6 out of 7)
- Knowledge Test: 20%, W7
- Group Assignment Presentation (Part A): 10%, W12 and W13
- Group Assignment Report Submission (Part B): 20%, Friday of W13 (By 11:59 pm)
- Final Exam: 40%, Exam Week
Topics Covered - Week 3: Project Network Diagram (Discrete Approach)
- What is a Project Network Diagram?
- Different approaches to the Project Network Diagram
- Precedence Diagramming Method
- Other Approaches
- Project Duration, Critical Path and Near-Critical Path
- Limitation of Discrete Approach to Project Network Diagram
Network Diagram
-
Building Gate and Fence Project:
- First task: Dig Holes
- Buy Wood and Buy Gate can start after Dig Holes. -Erect Fence requires Buy Wood -Buy Paint requires Buy Gate -Erect Gate requires Erect Fence and Buy Paint -Paint Fence requires Erect Gate -Paint Gate requires Paint Fence -Network diagrams are visual representations of a project's schedule. -Illustrates logical events leading to project completion. -Used to plan and track projects from start to finish. -Represent critical path and project scope. -Used for ease of readability to show activity sequence, and parallel activities, and connections between activities.
-
Rules of Thumb for Network Diagrams:
- Starting point
- Ending point -Predecessors for all activities (except the start point) -Successors for all activities (except the endpoint) -No loops or hangers
Precedence Diagramming Method (PDM)
- Node represents activity
- Also known as activity-on-node (AON) diagrams
Other Approaches for Network Diagram
- Arrow Diagramming Method
- Critical Chain Approach
- Line of Balance Approach
- Advanced Work Package Approach
- Beeline Diagramming Method
- Chronographic Modeling Approach
- Timeboxing
- Kanban
Critical Path
- Critical Path: The sequence of activities that determine the duration of the project. It's the longest path through the project.
- Forward Pass: Identifies early start (ES) and early finish (EF) dates.
- Backward Pass: Identifies the late start (LS) and late finish (LF) dates. -Use formulas (ES + duration = EF) and (EF + lag = ES, EF – lead = ES) for successors.
- Important for project managers to calculate slack times -Tasks on the critical path have a slack of 0
Slack Time (Float Time)
- Amount of time a task can be delayed without delaying project completion or subsequent task start.
- Total Slack = Late Finish – Early Finish or Total Slack = Late Start – Early Start
Near-Critical Path
- One or more paths in the project that are not initially critical but may become critical due to events like longer durations or improved performance of non-critical tasks. -Probabilistic outcome of task/task duration plays a major variable.
Review Questions
- Differences between critical and near-critical paths
- Network diagrams with zero critical paths or zero near-critical paths
- Calculation of task slack time, and its importance for project managers.
- Tasks with zero slack
- Loops in a network diagram
- Rules of thumb for drawing network diagrams
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Related Documents
Description
Test your knowledge on the Project Network Diagram as covered in PMGT3623 Week 3. This quiz will explore different approaches to creating network diagrams, critical paths, and project duration analysis. Enhance your understanding of key concepts that are crucial for successful project management.