Project Scheduling and Network Diagram

EvaluativeGadolinium avatar
EvaluativeGadolinium
·
·
Download

Start Quiz

Study Flashcards

5 Questions

What is the duration of Activity 3 - 7?

5 months

Which activity has the longest duration in the project's schedule?

3 - 6

Which of the following is NOT an activity in the project's time schedule?

2 - 6

What is the total duration for the given activities if performed sequentially?

38 months

Which of the following activity pairs have the same duration?

1 - 3 and 1 - 1

Study Notes

Project Time Schedule

  • A project has a defined schedule with 10 activities and their corresponding durations in months.

Activity Durations

  • Activity 1-1: 2 months
  • Activity 1-3: 2 months
  • Activity 1-4: 1 month
  • Activity 2-5: 4 months
  • Activity 3-6: 8 months
  • Activity 3-7: 5 months
  • Activity 4-6: 3 months
  • Activity 5-8: 1 month
  • Activity 6-9: 5 months
  • Activity 7-8: 4 months
  • Activity 8-9: 3 months

Requirements for Network Construction and Computation

  • Calculate the Early Start Time (EST) and Late Start Time (LST) for each activity.
  • Calculate the Early Finish Time (EFT) and Late Finish Time (LFT) for each activity.
  • Determine the total float for each activity.
  • Identify the critical path and its duration.

This quiz deals with calculating project schedules and network diagrams, including activity durations and dependency relationships. It requires understanding of project management concepts and techniques.

Make Your Own Quizzes and Flashcards

Convert your notes into interactive study material.

Get started for free
Use Quizgecko on...
Browser
Browser