What is the duration of Activity 3 - 7?
What is the duration of Activity 3 - 7?
Which activity has the longest duration in the project's schedule?
Which activity has the longest duration in the project's schedule?
Which of the following is NOT an activity in the project's time schedule?
Which of the following is NOT an activity in the project's time schedule?
What is the total duration for the given activities if performed sequentially?
What is the total duration for the given activities if performed sequentially?
Signup and view all the answers
Which of the following activity pairs have the same duration?
Which of the following activity pairs have the same duration?
Signup and view all the answers
Study Notes
Project Time Schedule
- A project has a defined schedule with 10 activities and their corresponding durations in months.
Activity Durations
- Activity 1-1: 2 months
- Activity 1-3: 2 months
- Activity 1-4: 1 month
- Activity 2-5: 4 months
- Activity 3-6: 8 months
- Activity 3-7: 5 months
- Activity 4-6: 3 months
- Activity 5-8: 1 month
- Activity 6-9: 5 months
- Activity 7-8: 4 months
- Activity 8-9: 3 months
Requirements for Network Construction and Computation
- Calculate the Early Start Time (EST) and Late Start Time (LST) for each activity.
- Calculate the Early Finish Time (EFT) and Late Finish Time (LFT) for each activity.
- Determine the total float for each activity.
- Identify the critical path and its duration.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Description
This quiz deals with calculating project schedules and network diagrams, including activity durations and dependency relationships. It requires understanding of project management concepts and techniques.