Network Diagram Guidelines Quiz

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to Lesson

Podcast

Play an AI-generated podcast conversation about this lesson
Download our mobile app to listen on the go
Get App

Questions and Answers

Match the guideline number with its description:

Guideline 1 = Networks typically flow from left to right, or top to bottom Guideline 4 = Splitting of activities is not allowed Guideline 6 = Each activity should be uniquely identified in ascending order Guideline 8 = A network should ideally begin and end with common nodes

Match the guideline with its relevant concept:

Guideline 2 = Activities represented by boxes and relationships by arrows Guideline 3 = Left-hand side of the node represents activity start Guideline 5 = An activity cannot begin until all preceding activities are finished Guideline 7 = Looping and conditional statements are not allowed

Match the guideline with its forbidden practice:

Guideline 4 = Activities must carry on continuously without interruption Guideline 5 = Activities cannot start until all prior ones are completed Guideline 6 = Unique identification of activities is mandatory Guideline 7 = Flow from one activity back to an earlier one is disallowed

Match the guideline with its function in a network diagram:

<p>Guideline 1 = Determines the direction of flow in the network Guideline 2 = Clarifies the connection between activities Guideline 8 = Facilitates the creation of common start and finish nodes Guideline 3 = Indicates the start and end of an activity within a node</p> Signup and view all the answers

Match the guideline with its correct application:

<p>Guideline 2 = Uses arrows to indicate precedence flow Guideline 4 = Ensures no interruptions in processes Guideline 7 = Prevents looping of activities in a network Guideline 8 = Utilizes dummy activities for multiple connections</p> Signup and view all the answers

Match the guideline to its relevant project management principle:

<p>Guideline 1 = Establishes overall network layout Guideline 5 = Prioritizes task completion before starting new ones Guideline 6 = Aids in clarity and tracking of activities Guideline 3 = Provides visual representation of activity duration</p> Signup and view all the answers

Match the guidelines with their strategic importance:

<p>Guideline 4 = Maintains activity integrity Guideline 5 = Ensures logical flow of project activities Guideline 7 = Avoids confusion in network paths Guideline 2 = Systematizes the visual representation of dependencies</p> Signup and view all the answers

Match the guideline with its restriction on networks:

<p>Guideline 6 = Allows only ascending order for activity identification Guideline 4 = Prohibits interruptions during activities Guideline 2 = Prohibits the use of lines without clear representation Guideline 7 = Prohibits conditional paths in activity flow</p> Signup and view all the answers

Match the guidelines with their descriptions of project visualization:

<p>Guideline 1 = Describes the flow directionality of networks Guideline 8 = Incorporates dummy nodes for clarity Guideline 5 = Ensures completion before starting new tasks Guideline 3 = Clarifies node representation for activities</p> Signup and view all the answers

Match each guideline with its corresponding principle:

<p>Guideline 1 = Direction of flow in a network Guideline 3 = Start and finish representation in nodes Guideline 5 = Dependency between activities Guideline 8 = Use of dummy activities for multiple nodes</p> Signup and view all the answers

Match the guideline with its characteristic restriction:

<p>Guideline 2 = Activities represented by arrows Guideline 4 = Disallowance of activity splitting Guideline 6 = Unique identification of activities Guideline 7 = Prohibition of looping or conditional statements</p> Signup and view all the answers

Match each guideline with the appropriate network feature:

<p>Guideline 1 = Flow direction in diagrams Guideline 3 = Node construction and flow Guideline 5 = Completion requirement of predecessors Guideline 7 = Clear-cut procedural pathways</p> Signup and view all the answers

Match the guideline to its underlying rationale:

<p>Guideline 4 = Continuous process representation Guideline 6 = Clarity and order in project activities Guideline 2 = Visual representation of workflow Guideline 8 = Commonality in project start and finish</p> Signup and view all the answers

Match the guideline with its operational rule:

<p>Guideline 1 = Arrangement of activities Guideline 5 = Practical dependency management Guideline 7 = Structural integrity of pathways Guideline 3 = Visual symmetry of nodes</p> Signup and view all the answers

Match the guideline with its purpose in network diagrams:

<p>Guideline 2 = Definition of activity relationships Guideline 4 = Maintenance of process integrity Guideline 6 = Order in project execution Guideline 8 = Management of complexity via dummies</p> Signup and view all the answers

Match the guideline with its implication for management:

<p>Guideline 5 = Ensuring sequential progress Guideline 6 = Facilitating tracking and reporting Guideline 7 = Avoiding project reiteration Guideline 1 = Establishing clear movement direction</p> Signup and view all the answers

Match each guideline with its function in network flow:

<p>Guideline 2 = Signal flow relationships Guideline 3 = Clarification of activity start/end Guideline 4 = Prohibition of interruptions Guideline 8 = Integration of multiple endpoints</p> Signup and view all the answers

Match the guideline with its critical project management aspect:

<p>Guideline 1 = Streamlining visualization Guideline 5 = Coordination of dependencies Guideline 7 = Defining a clear linear process Guideline 8 = Managing multiple paths effectively</p> Signup and view all the answers

Match the guideline number with its specific restriction:

<p>Guideline 4 = Activity splitting is not allowed Guideline 5 = No activity can start before its predecessors are complete Guideline 7 = No looping or conditional statements allowed Guideline 6 = Each activity must have a unique ascending identifier</p> Signup and view all the answers

Match the guideline with its corresponding visualization requirement:

<p>Guideline 1 = Direction flow from left to right or top to bottom Guideline 2 = Representation of activities with boxes and relationships with arrows Guideline 8 = Use of a common start and finish node Guideline 3 = Left side represents the start; right side represents the finish</p> Signup and view all the answers

Match the guideline with its function in project management:

<p>Guideline 2 = Indicates precedence among activities Guideline 6 = Ensures uniqueness of activities for clarity Guideline 8 = Facilitates linking multiple start and finish points Guideline 4 = Maintains continuity of processes</p> Signup and view all the answers

Match the guideline with its implication for network design:

<p>Guideline 1 = Establishes overall flow of the network Guideline 3 = Clarifies activity progress Guideline 5 = Defines strict sequencing of activities Guideline 7 = Prohibits inefficiencies caused by loops</p> Signup and view all the answers

Match the guideline with its specific characteristic:

<p>Guideline 4 = Each activity must proceed without interruption Guideline 2 = Activities are visualized as nodes Guideline 5 = Failure to complete preceding activities halts a new start Guideline 1 = Describes the typical layout of activities</p> Signup and view all the answers

Match the guideline with its relevant project flow aspect:

<p>Guideline 3 = Distinguishes start and finish of activities Guideline 6 = Enforces clarity in activity representation Guideline 7 = Ensures smooth transitions between activities Guideline 8 = Simplifies complex networks with dummy activities</p> Signup and view all the answers

Match the guideline with its necessary condition:

<p>Guideline 5 = Completion of predecessors is required Guideline 1 = Flow direction is standardized Guideline 8 = Dummy activities can bridge gaps in starts and finishes Guideline 4 = No fragmentation of activities is permitted</p> Signup and view all the answers

Match the guideline with its specific enforcement:

<p>Guideline 2 = Activities must be clearly delineated Guideline 7 = Prevents redundant loops in work Guideline 1 = Ensures clarity in presentation Guideline 6 = Promotes order and sequence in activity listing</p> Signup and view all the answers

Match the guideline with its focus on continuity:

<p>Guideline 4 = Continuity of processes without interruption Guideline 2 = Flow is depicted through arrows Guideline 5 = New activities start only after previous ones finish Guideline 1 = Directionality in flow is emphasized</p> Signup and view all the answers

Match the guideline number with its relevant restriction on activity representation:

<p>1 = Networks typically flow from left to right, or top to bottom 4 = Splitting of activities is not allowed 5 = An activity cannot begin until all its preceding activities have been completed 7 = Looping or conditional statements are not allowed</p> Signup and view all the answers

Match the guideline number with its description of flow direction:

<p>2 = Activities are represented by boxes (nodes) 6 = Each activity should be uniquely identified in ascending order 3 = Left-hand side indicates the start of the activity 8 = A network should ideally begin with a common start node</p> Signup and view all the answers

Match the guideline number with its characterization of a network node:

<p>2 = Relationships between activities are represented by arrows 3 = The right-hand side represents the finish of the activity 4 = An activity represents an individual process 8 = Dummy activities are used to link multiple start and finish nodes</p> Signup and view all the answers

Match the guideline number with its implication on activity sequence:

<p>5 = An activity cannot start until its predecessors are complete 7 = Looping signifies a flow back to earlier activities 1 = Network flows are typically directed left to right or top to bottom 4 = Activities must carry on continuously without interruption</p> Signup and view all the answers

Match the guideline number with its applicable condition for network activities:

<p>7 = Conditional statements are not allowed 8 = Multiple start or finish activities may use dummy nodes 6 = Activities must be identified in an ordered manner 3 = Node sides indicate activity status</p> Signup and view all the answers

Match the guideline number with its definition of a network flow:

<p>2 = Arrows indicate precedence and flow 1 = Direction generally flows from left to right 5 = Completion of preceding activities is mandatory 4 = Continuity without splitting is emphasized</p> Signup and view all the answers

Match the guideline number with its restriction on project management:

<p>6 = Unique activity identification in ascending order 7 = Prohibition of looping and conditional flows 5 = Predecessors must be completed before starting 8 = Utilization of dummy nodes for multiple connections</p> Signup and view all the answers

Match the guideline number with its illustration of node usage:

<p>4 = Activities should not be interrupted 2 = Nodes represent boxes for activities 3 = Node sides indicate start and finish 8 = Start and Finish nodes simplify connections</p> Signup and view all the answers

Match the guideline number with its restriction against certain programming practices:

<p>7 = Disallowance of looping back to earlier activities 1 = Network flow direction rules 5 = Sequence completion of activities 6 = Requirement for unique activity identification</p> Signup and view all the answers

Flashcards are hidden until you start studying

Study Notes

Network Diagram Guidelines

  • Network diagrams typically flow from left to right or top to bottom.
  • Activities are represented by boxes (nodes), while arrows represent relationships between activities.
  • Arrows indicate precedence and flow.
  • The left side of a node represents the start of an activity, while the right side represents the finish.
  • Activities cannot be split, meaning they represent continuous processes.
  • An activity cannot begin until all preceding activities are complete.
  • Activities should be uniquely identified in ascending order from left to right or top to bottom.
  • Looping and conditional statements are not allowed in network diagrams.
  • Ideally, networks should begin with a common start node and end with a common end node.
  • Dummy activities can be used to create common nodes for projects with multiple start or finish activities.
  • Dummy activities are represented by boxes labeled "Start" or "Finish" and do not represent actual work.

Network Diagram Guidelines

  • Networks typically flow from left to right or top to bottom.
  • Activities are represented by boxes (nodes), and relationships between activities are represented by arrows. Arrows indicate precedence and flow. 
  • The left side of a node represents the start of an activity and the right side represents the finish.
  • Activities cannot be split and must be carried out continuously without interruption.
  • An activity cannot begin until all preceding activities have been completed.
  • Activities should be uniquely identified in ascending order from left to right or top to bottom.
  • Looping and conditional statements are not allowed.
  • A network should ideally begin with a common start node and finish with a common end node.
  • Dummy activities can be used to create common nodes for projects with multiple start or finish activities.

Network Flow & Structure

  • Networks typically flow from left to right or top to bottom.
  • Activities are represented by boxes (nodes), while relationships between activities are represented by arrows.
  • Arrows indicate precedence and flow.
  • The left side of an activity node represents the start of the activity, while the right side represents the finish.
  • Activities cannot be split and must be carried out continuously without interruption.
  • An activity can only begin once all preceding activities have been completed.
  • Each activity should have a unique identification number, assigned in ascending order from left to right or top to bottom.
  • Looping and conditional statements are not allowed in network diagrams.
  • Networks ideally begin with a common start node and end with a common end node.
  • Dummy activities are used to create common nodes when a project has multiple start or finish activities. These dummy activities represent 'Start' and 'Finish' and do not represent actual work.

Network Flow Direction

  • Networks flow from left to right or top to bottom.

Activity Representation

  • Activities are represented by boxes (nodes).
  • Arrows indicate relationships between activities.
  • Arrows show precedence and flow.

Activity Node Representation

  • The left side of a node represents the activity's start.
  • The right side of a node represents the activity's finish.

Activity Splitting

  • Activity splitting is not allowed.
  • Activities must be continuous and uninterrupted.

Activity Precedence

  • An activity cannot start until all preceding activities are finished.

Activity Identification

  • Each activity is uniquely identified in ascending order.
  • Identification proceeds from left to right or top to bottom.

Network Looping and Conditional Statements

  • Looping and conditional statements are not permitted.
  • Looping involves network flow to an earlier activity, repeating work.
  • Conditional statements involve alternative paths based on earlier activity outcomes.

Network Start and Finish Nodes

  • Networks should ideally start with a common start node and end with a common end node.
  • For multiple start or finish activities, dummy activities can be used to create common nodes.
  • Dummy activities do not represent actual activities (e.g., 'Start', 'Finish').

Network Flow Direction

  • Networks typically flow from left to right, or top to bottom.

Activity Representation

  • Activities are represented by boxes, also known as nodes.
  • Relationships between activities are represented by arrows.
  • Arrows indicate precedence and flow.

Activity Node Representation

  • The left-hand side of an activity node represents the start of the activity.
  • The right-hand side of an activity node represents the finish of the activity.

Activity Splitting

  • Splitting activities is not allowed.
  • An activity represents an individual process that must continue without interruption.

Activity Precedence

  • An activity cannot begin until all its preceding activities have been completed.

Activity Identification

  • Each activity should be uniquely identified in ascending order from left to right or top to bottom, depending on the network's direction.

Looping and Conditional Statements

  • Looping and conditional statements are not allowed in networks.
  • Looping involves the network flowing back to an earlier activity to repeat a task.
  • Conditional statements involve alternative paths based on the outcome of an earlier activity.

Common Start and End Nodes

  • Networks should ideally begin with a common start node and finish with a common end node.
  • Dummy activities, like "Start" and "Finish" boxes, can be used to create common nodes for projects with multiple start or finish activities.
  • Dummy activities represent non-actual activities.

Studying That Suits You

Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

Quiz Team

More Like This

Project Network Diagrams Quiz
6 questions

Project Network Diagrams Quiz

AdventurousRockCrystal6744 avatar
AdventurousRockCrystal6744
Project Scheduling and Network Diagram
5 questions
Project Network Diagram Overview
5 questions

Project Network Diagram Overview

IntriguingConnemara9819 avatar
IntriguingConnemara9819
Use Quizgecko on...
Browser
Browser