Podcast
Questions and Answers
What is the immediate predecessor activity for activity E?
What is the immediate predecessor activity for activity E?
- Activity B
- Activity C
- Activity F
- Activity D (correct)
What is the predecessor activity for activity C?
What is the predecessor activity for activity C?
- Activity F
- Activity A
- Activity D
- Activity B (correct)
Which activity has no predecessor and is the first activity in the project network?
Which activity has no predecessor and is the first activity in the project network?
- Activity B
- Activity C
- Activity D
- Activity A (correct)
What is the predecessor activity for activity G?
What is the predecessor activity for activity G?
Which activities are joined by node 6 in the project network diagram?
Which activities are joined by node 6 in the project network diagram?
Which activity is the last activity in the project network?
Which activity is the last activity in the project network?
What is the purpose of the critical path method (CPM)?
What is the purpose of the critical path method (CPM)?
What is the definition of the critical path in a project network?
What is the definition of the critical path in a project network?
What is the significance of critical activities in a project?
What is the significance of critical activities in a project?
What does the completion time of a project include?
What does the completion time of a project include?
What is a continuous sequence consisting of nodes and activities in a project network called?
What is a continuous sequence consisting of nodes and activities in a project network called?
Why is it important for a project manager to pay special attention to critical activities?
Why is it important for a project manager to pay special attention to critical activities?
What does CPM assume about the time estimates for each activity?
What does CPM assume about the time estimates for each activity?
When may a non-critical activity be delayed without delaying the whole project?
When may a non-critical activity be delayed without delaying the whole project?
What is a dummy activity used for in project networks?
What is a dummy activity used for in project networks?
What is meant by 'path' in a network diagram for a project?
What is meant by 'path' in a network diagram for a project?
Flashcards are hidden until you start studying
Study Notes
Activity Predecessors
- The immediate predecessor activity for activity E is not specified.
- The predecessor activity for activity C is not specified.
Project Network
- The activity with no predecessor and the first activity in the project network is not specified.
Activity Relationships
- The predecessor activity for activity G is not specified.
- Activities joined by node 6 in the project network diagram are not specified.
Critical Path Method (CPM)
- The purpose of CPM is not specified.
- The critical path in a project network is defined as the sequence of activities that determines the minimum duration required to complete the project.
- Critical activities in a project are significant because they determine the minimum project duration.
Project Completion
- The completion time of a project includes the duration of the critical path.
Project Network Components
- A continuous sequence consisting of nodes and activities in a project network is called a path.
Critical Activities
- It is important for a project manager to pay special attention to critical activities because they determine the minimum project duration.
Time Estimates
- CPM assumes that the time estimates for each activity are fixed and known.
Non-Critical Activities
- A non-critical activity may be delayed without delaying the whole project if its delay does not affect the critical path.
Dummy Activities
- A dummy activity is used to maintain the logical relationships between activities in project networks.
Network Diagram
- In a network diagram for a project, a path refers to a sequence of nodes and activities.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.