Network Diagram Development Problem
16 Questions
3 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

What is the immediate predecessor activity for activity E?

  • Activity B
  • Activity C
  • Activity F
  • Activity D (correct)
  • What is the predecessor activity for activity C?

  • Activity F
  • Activity A
  • Activity D
  • Activity B (correct)
  • Which activity has no predecessor and is the first activity in the project network?

  • Activity B
  • Activity C
  • Activity D
  • Activity A (correct)
  • What is the predecessor activity for activity G?

    <p>Activity F</p> Signup and view all the answers

    Which activities are joined by node 6 in the project network diagram?

    <p>Activity D and Activity F</p> Signup and view all the answers

    Which activity is the last activity in the project network?

    <p>Activity G</p> Signup and view all the answers

    What is the purpose of the critical path method (CPM)?

    <p>To determine the time to complete a project and identify important activities</p> Signup and view all the answers

    What is the definition of the critical path in a project network?

    <p>The path with the largest time of execution</p> Signup and view all the answers

    What is the significance of critical activities in a project?

    <p>They are activities that cannot be delayed without delaying the whole project</p> Signup and view all the answers

    What does the completion time of a project include?

    <p>The time required to complete all activities of the project in the specified sequence</p> Signup and view all the answers

    What is a continuous sequence consisting of nodes and activities in a project network called?

    <p>A path in the network</p> Signup and view all the answers

    Why is it important for a project manager to pay special attention to critical activities?

    <p>Because any delay in them will delay the completion of the whole project</p> Signup and view all the answers

    What does CPM assume about the time estimates for each activity?

    <p>Precise time estimate is available for each activity</p> Signup and view all the answers

    When may a non-critical activity be delayed without delaying the whole project?

    <p>When its delay does not exceed a certain limit</p> Signup and view all the answers

    What is a dummy activity used for in project networks?

    <p>To connect two nodes without any actual work being done</p> Signup and view all the answers

    What is meant by 'path' in a network diagram for a project?

    <p>A continuous sequence, consisting of nodes and activities alternatively, beginning with the start event and stopping at the end event of a network</p> Signup and view all the answers

    Study Notes

    Activity Predecessors

    • The immediate predecessor activity for activity E is not specified.
    • The predecessor activity for activity C is not specified.

    Project Network

    • The activity with no predecessor and the first activity in the project network is not specified.

    Activity Relationships

    • The predecessor activity for activity G is not specified.
    • Activities joined by node 6 in the project network diagram are not specified.

    Critical Path Method (CPM)

    • The purpose of CPM is not specified.
    • The critical path in a project network is defined as the sequence of activities that determines the minimum duration required to complete the project.
    • Critical activities in a project are significant because they determine the minimum project duration.

    Project Completion

    • The completion time of a project includes the duration of the critical path.

    Project Network Components

    • A continuous sequence consisting of nodes and activities in a project network is called a path.

    Critical Activities

    • It is important for a project manager to pay special attention to critical activities because they determine the minimum project duration.

    Time Estimates

    • CPM assumes that the time estimates for each activity are fixed and known.

    Non-Critical Activities

    • A non-critical activity may be delayed without delaying the whole project if its delay does not affect the critical path.

    Dummy Activities

    • A dummy activity is used to maintain the logical relationships between activities in project networks.

    Network Diagram

    • In a network diagram for a project, a path refers to a sequence of nodes and activities.

    Studying That Suits You

    Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

    Quiz Team

    Description

    This quiz presents a problem statement related to developing a network diagram for a project, with specified activities and their immediate predecessors. It provides a scenario and asks for the development of the network diagram based on the given information.

    More Like This

    Project Scheduling and Network Diagram
    5 questions
    Activity Network Diagram
    10 questions
    PMGT3623 Scheduling - Week 3 Quiz
    54 questions

    PMGT3623 Scheduling - Week 3 Quiz

    SweetheartMandelbrot1035 avatar
    SweetheartMandelbrot1035
    Use Quizgecko on...
    Browser
    Browser