Questions and Answers
What is the primary purpose of performance reviews in project schedule control?
What is the primary purpose of performance reviews in project schedule control?
What is the result of a variance analysis in project schedule control?
What is the result of a variance analysis in project schedule control?
What is the output of the Schedule Control process that documents calculated Schedule Variance (SV) and Schedule Performance Index (SPI)?
What is the output of the Schedule Control process that documents calculated Schedule Variance (SV) and Schedule Performance Index (SPI)?
What is the formula to calculate Schedule Variance (SV) percentage?
What is the formula to calculate Schedule Variance (SV) percentage?
Signup and view all the answers
What does a negative Schedule Variance percentage indicate?
What does a negative Schedule Variance percentage indicate?
Signup and view all the answers
What is the purpose of change requests in the Schedule Control process?
What is the purpose of change requests in the Schedule Control process?
Signup and view all the answers
In the given example, what is the status of the project?
In the given example, what is the status of the project?
Signup and view all the answers
What is the calculation for Schedule Variance (SV)?
What is the calculation for Schedule Variance (SV)?
Signup and view all the answers
What is the primary purpose of the Schedule Development process?
What is the primary purpose of the Schedule Development process?
Signup and view all the answers
What do black diamonds represent in a Gantt chart?
What do black diamonds represent in a Gantt chart?
Signup and view all the answers
What is the purpose of adding milestones to a Gantt chart?
What is the purpose of adding milestones to a Gantt chart?
Signup and view all the answers
What is the primary concern of Schedule Control?
What is the primary concern of Schedule Control?
Signup and view all the answers
What is the purpose of a Project Schedule Network Diagram?
What is the purpose of a Project Schedule Network Diagram?
Signup and view all the answers
How can you create a milestone in a Gantt chart?
How can you create a milestone in a Gantt chart?
Signup and view all the answers
What is represented by lighter horizontal bars in a Gantt chart?
What is represented by lighter horizontal bars in a Gantt chart?
Signup and view all the answers
What is the benefit of getting stakeholders and functional managers to approve and sign off the project schedule?
What is the benefit of getting stakeholders and functional managers to approve and sign off the project schedule?
Signup and view all the answers
What is the primary advantage of analogous estimating over other techniques?
What is the primary advantage of analogous estimating over other techniques?
Signup and view all the answers
What is the purpose of three-point estimates in PERT?
What is the purpose of three-point estimates in PERT?
Signup and view all the answers
What is a characteristic of PERT that distinguishes it from CPM?
What is a characteristic of PERT that distinguishes it from CPM?
Signup and view all the answers
What is the formula used by PERT to calculate the mean duration?
What is the formula used by PERT to calculate the mean duration?
Signup and view all the answers
What is the primary purpose of schedule network analysis?
What is the primary purpose of schedule network analysis?
Signup and view all the answers
What is critical path method (CPM)?
What is critical path method (CPM)?
Signup and view all the answers
What is the primary output of the schedule development process?
What is the primary output of the schedule development process?
Signup and view all the answers
What is a diagram type that can be used to draw PERT charts?
What is a diagram type that can be used to draw PERT charts?
Signup and view all the answers
Study Notes
Estimating Techniques
- Analogous estimates are less time-consuming and costly but less accurate
- Parametric estimating uses a statistical relationship between historical data and other variables, making it more accurate than analogous estimates
- Three-point estimates use three estimates (most likely, optimistic, and pessimistic) to calculate a final estimate, which is used in PERT estimates
PERT (Program Evaluation and Review Technique)
- Uses three estimates per activity: optimistic, pessimistic, and most likely
- Can be drawn only using AOA diagrams and can have dummy events
- Calculates mean duration using the formula: (P + 4M + O)/6
Schedule Development
- Uses results from other time management processes to determine project start and end dates
- Output: project schedule network diagram, Gantt charts/bar charts, milestone charts
Schedule Network Analysis
- Generates the project schedule using a schedule model and analytical techniques
- Techniques used: critical path method, critical chain method, what-if analysis, and resource leveling
Critical Path Method (CPM)
- A schedule network analysis technique
- Part of the develop schedule process
Gantt Charts (Bar Charts)
- Display project schedule information in a calendar format
- Symbols: black diamonds (milestones), thick black bars (summary tasks), lighter horizontal bars (task durations), arrows (dependencies)
Schedule Control
- Concerned with determining the current status of the project schedule and managing changes
- Performance reviews measure schedule performance, and variance analysis identifies schedule variances
- Outputs: work performance measurements, organizational process asset updates, change requests, project management plan updates, and project document updates
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Description
Learn about different estimating techniques in project management, including analogous, parametric, and three-point estimates. Understand the advantages and limitations of each technique.