🎧 New: AI-Generated Podcasts Turn your study notes into engaging audio conversations. Learn more

Loading...
Loading...
Loading...
Loading...
Loading...
Loading...
Loading...

Full Transcript

1. What does Earned Value Management (EVM) integrate to assess project performance? - A) Scope, cost, and time data - B) Resource allocation and risk management - C) Communication and stakeholder management - D) Quality metrics and procurement data Correct Answer: A 2. Which key metric in EVM repr...

1. What does Earned Value Management (EVM) integrate to assess project performance? - A) Scope, cost, and time data - B) Resource allocation and risk management - C) Communication and stakeholder management - D) Quality metrics and procurement data Correct Answer: A 2. Which key metric in EVM represents the budgeted cost of work performed? - A) Planned Value (PV) - B) Earned Value (EV) - C) Actual Cost (AC) - D) Budget at Completion (BAC) Correct Answer: B 3. What is the Cost Baseline in EVM often represented by? - A) S-Curve - B) Histogram - C) Pie Chart - D) Scatter Plot Correct Answer: A 4. Which of the following describes Planned Value (PV) in EVM? - A) The value of the work actually performed - B) The budgeted cost of work scheduled - C) The actual costs incurred - D) The estimated completion cost Correct Answer: B 5. What is Schedule Variance (SV) in EVM? - A) SV = EV - PV - B) SV = PV - AC - C) SV = AC - EV - D) SV = PV - BAC Correct Answer: A 6. A positive Cost Variance (CV) in EVM indicates that: - A) The project is over budget - B) The project is under budget - C) The project is behind schedule - D) The project scope is increasing Correct Answer: B 7. What does a Schedule Performance Index (SPI) value greater than 1 indicate? - A) The project is behind schedule - B) The project is ahead of schedule - C) The project is over budget - D) The project is under budget Correct Answer: B 8. Which formula calculates Cost Performance Index (CPI)? - A) CPI = EV / AC - B) CPI = PV / EV - C) CPI = AC / PV - D) CPI = PV / AC Correct Answer: A 9. What does a CPI value less than 1.0 indicate? - A) The project is costing more than planned - B) The project is costing less than planned - C) The project is ahead of schedule - D) The project has no cost variance Correct Answer: A 10. In EVM, what is Estimate at Completion (EAC) used for? - A) To assess project quality - B) To forecast the expected total cost of the project - C) To determine the project team’s performance - D) To identify project risks Correct Answer: B 11. Which formula can be used for EAC when current cost performance is expected to continue? - A) EAC = BAC / CPI - B) EAC = BAC - EV - C) EAC = AC + ETC - D) EAC = EV / PV Correct Answer: A 12. What does a Burnup Chart represent in project metrics? - A) The amount of work left to do - B) Progress towards project completion - C) Project risks and mitigations - D) Cost over time Correct Answer: B 13. What does the vertical axis of a Burndown Chart typically represent? - A) Time - B) Effort remaining - C) Cost - D) Resources Correct Answer: B 14. In a Burndown Chart, if the actual work line is above the ideal line, what does it indicate? - A) The project is ahead of schedule - B) The project is behind schedule - C) The project is on budget - D) The project scope has decreased Correct Answer: B 15. What is the purpose of a change control process in project management? - A) To manage risks and identify opportunities - B) To monitor stakeholder communication - C) To identify, evaluate, and manage changes to project scope, cost, and schedule - D) To establish a project baseline Correct Answer: C 16. Who is typically responsible for approving project changes? - A) Project Team - B) Change Control Board (CCB) - C) Stakeholders - D) Functional Managers Correct Answer: B 17. What is scope creep? - A) The tendency for project costs to exceed the budget - B) Uncontrolled changes to the project scope - C) Changes made by the project sponsor - D) Scheduled project delays Correct Answer: B 18. In adaptive projects, how is change managed differently compared to predictive projects? - A) Changes are strictly limited - B) Changes are added to the Product Backlog and prioritized - C) Changes are rejected automatically - D) Changes are managed through fixed scope planning Correct Answer: B 19. What is a progress report used for in project management? - A) To describe what the team has accomplished in the last period - B) To determine the cost baseline - C) To allocate project resources - D) To finalize the project schedule Correct Answer: A 20. What does the Schedule Performance Index (SPI) measure? - A) Cost efficiency of budgeted resources - B) The variance between earned value and planned value - C) The project team's productivity - D) The accuracy of resource allocation Correct Answer: B 21. Which type of report forecasts project performance based on historical data? - A) Status report - B) Variance report - C) Forecast report - D) Progress report Correct Answer: C 22. Which document is used to track unresolved project issues? - A) Risk Register - B) Change Log - C) Issue Log - D) Stakeholder Register Correct Answer: C 23. What is the purpose of Key Performance Indicators (KPIs) in project reporting? - A) To assess project quality - B) To gauge the project’s performance quantitatively - C) To determine project risks - D) To identify stakeholders Correct Answer: B 24. Which KPI category measures how well resources are being utilized? - A) Time - B) Cost - C) Resource usage - D) Quality Correct Answer: C 25. What does the Cost Performance Index (CPI) value indicate if it is greater than 1.0? - A) The project is over budget - B) The project is under budget - C) The project is ahead of schedule - D) The project is behind schedule Correct Answer: B 26. What type of variance analysis is used to determine if the project is on schedule? - A) Cost Variance (CV) - B) Schedule Variance (SV) - C) Earned Value (EV) - D) Budget at Completion (BAC) Correct Answer: B 27. In EVM, what is Actual Cost (AC)? - A) The cost that should have been incurred by a given date - B) The cost incurred for the work completed to date - C) The total estimated cost of the project - D) The forecasted cost at completion Correct Answer: B 28. What is the purpose of a variance report? - A) To track changes to the project scope - B) To compare actual performance to planned performance - C) To allocate project resources - D) To determine stakeholder needs Correct Answer: B 29. What does Estimate to Complete (ETC) represent in project forecasting? - A) The total cost at project completion - B) The cost required to complete the remaining project work - C) The actual cost of completed work - D) The baseline project budget Correct Answer: B 30. Which report type is used to communicate project progress to a broad audience? - A) Status report - B) Burnup chart - C) Dashboard - D) Risk register Correct Answer: C 31. Which of the following is an example of a positive risk response strategy? - A) Mitigate - B) Avoid - C) Exploit - D) Transfer Correct Answer: C 32. What does a burnup chart typically include to indicate progress? - A) Ideal trajectory, completed line, and total scope - B) Work left to complete, time remaining, and cost to complete - C) Team performance, resource allocation, and risks - D) Project quality, schedule changes, and scope increases Correct Answer: A 33. Which change request status indicates that a change will be implemented at a later time? - A) Approve - B) Reject - C) Defer - D) Escalate Correct Answer: C 34. What does the term "information radiator" refer to in project reporting? - A) Reports provided during project meetings - B) Big visual boards displayed in high-traffic areas to show project progress - C) Stake holder satisfaction surveys - D) Project management software Correct Answer: B 35. Which document lists all changes made to the project, including their status? - A) Issue Log - B) Change Log - C) Stakeholder Register - D) Risk Register Correct Answer: B 36. What is a key benefit of variance analysis in project reporting? - A) It helps project managers understand differences between planned and actual performance - B) It allocates resources for future activities - C) It determines stakeholder satisfaction - D) It identifies new project risks Correct Answer: A 37. In project metrics, what is a velocity chart used for? - A) To measure how much work the team can complete in each iteration - B) To assess the overall project cost - C) To determine resource requirements - D) To track procurement activities Correct Answer: A 38. What is the significance of a Schedule Performance Index (SPI) value of 1.0? - A) The project is ahead of schedule - B) The project is behind schedule - C) The project is exactly on schedule - D) The project is under budget Correct Answer: C 39. What is the purpose of a cost variance analysis? - A) To determine if the project is meeting scope requirements - B) To ensure costs do not exceed authorized funding - C) To prioritize stakeholder needs - D) To identify project risks Correct Answer: B 40. Which project metric helps determine the remaining amount of work versus available time? - A) Cost Performance Index (CPI) - B) Burnup Chart - C) Burndown Chart - D) Variance Report Correct Answer: C 41. What does the Estimate at Completion (EAC) formula AC + (BAC - EV) assume about cost variances? - A) They are likely to continue in the future - B) They are considered atypical - C) They have no impact on project completion - D) They are external influences only Correct Answer: B 42. What does a negative Schedule Variance (SV) indicate? - A) The project is behind schedule - B) The project is under budget - C) The project is ahead of schedule - D) The project is over budget Correct Answer: A 43. Which of the following can be used as an input for project reporting? - A) Earned Value - B) Lessons Learned - C) Work Breakdown Structure - D) Critical Path Analysis Correct Answer: B 44. What is the Cost Variance (CV) if EV = $149,100 and AC = $139,100? - A) $10,000 - B) -$10,000 - C) $20,000 - D) -$20,000 Correct Answer: A 45. What is an important step in the change control process after a change is approved? - A) Documenting the change in the communication plan - B) Adjusting project baselines as per the approved change - C) Eliminating any remaining project risks - D) Creating a new work breakdown structure Correct Answer: B 46. What does a positive CPI value indicate about project cost? - A) Costs are higher than planned - B) Costs are on target - C) Costs are lower than planned - D) Costs are not yet known Correct Answer: C 47. In EVM, which value is calculated as EV - PV? - A) Cost Variance (CV) - B) Schedule Variance (SV) - C) Planned Value (PV) - D) Estimate at Completion (EAC) Correct Answer: B 48. What is the significance of BAC in EVM? - A) It represents the current cost of the project - B) It is the original total budget for the project - C) It measures the earned value of completed work - D) It predicts future project costs Correct Answer: B 49. In reporting, what does "forecasting" focus on? - A) Historical performance - B) Future performance based on current trends - C) Current issues and challenges - D) Stakeholder involvement Correct Answer: B 50. What does SPI = EV / PV help determine? - A) If the project is within budget - B) If the project is meeting its schedule goals - C) If the project needs a new risk assessment - D) If the project team is properly allocated Correct Answer: B

Use Quizgecko on...
Browser
Browser