Week 8 Project Time Management Part 1 PDF

Summary

This document provides an overview of project time management concepts. It describes the process of managing schedules, estimating resources, and calculating critical paths in projects. The document is relevant for understanding and applying principles of IT project management.

Full Transcript

Information Technology Project Management, Seventh Edition Note: See the text itself for full citations.  Understand the importance of project schedules and good project time management  Discuss the process of planning schedule management  Define activi...

Information Technology Project Management, Seventh Edition Note: See the text itself for full citations.  Understand the importance of project schedules and good project time management  Discuss the process of planning schedule management  Define activities as the basis for developing project schedules  Describe how project managers use network diagrams and dependencies to assist in activity sequencing  Understand the relationship between estimating resources and project schedules  Explain how various tools and techniques help project managers perform activity duration estimates Information Technology Project Management, Seventh Edition Copyright 2014 2  Use a Gantt chart for planning and tracking schedule information, find the critical path for a project, and describe how critical chain scheduling and the Program Evaluation and Review Technique (PERT) affect schedule development  Discuss how reality checks and discipline are involved in controlling and managing changes to the project schedule  Describe how project management software can assist in project time management and review words of caution before using this software Information Technology Project Management, Seventh Edition Copyright 2014 3  Managers often cite delivering projects on time as one of their biggest challenges  Time has the least amount of flexibility; it passes no matter what happens on a project  Schedule issues are the main reason for conflicts on projects, especially during the second half of projects Information Technology Project Management, Seventh Edition Copyright 2014 4  One dimension of the Meyers-Briggs Type Indicator focuses on peoples’ attitudes toward structure and deadline  Some people prefer to follow schedules and meet deadlines while others do not (J vs. P)  Difference cultures and even entire countries have different attitudes about schedules Information Technology Project Management, Seventh Edition Copyright 2014 5  Planning schedule management: determining the policies, procedures, and documentation that will be used for planning, executing, and controlling the project schedule  Defining activities: identifying the specific activities that the project team members and stakeholders must perform to produce the project deliverables  Sequencing activities: identifying and documenting the relationships between project activities  Estimating activity resources: estimating how many resources a project team should use to perform project activities  Estimating activity durations: estimating the number of work periods that are needed to complete individual activities  Developing the schedule: analyzing activity sequences, activity resource estimates, and activity duration estimates to create the project schedule  Controlling the schedule: controlling and managing changes to the project schedule Information Technology Project Management, Seventh Edition Copyright 2014 6 Information Technology Project Management, Seventh Edition Copyright 2014 7  The project team uses expert judgment, analytical techniques, and meetings to develop the schedule management plan  A schedule management plan includes: ◦ Project schedule model development – includes estimated durations, dependencies etc. ◦ The scheduling methodology and tools – CPM, Network diagrams, etc. ◦ Level of accuracy and units of measure - hours, days, or another unit ◦ Control thresholds - ±10% ◦ Rules of performance measurement ◦ Reporting formats - the format and frequency of schedule reports required ◦ Process descriptions Information Technology Project Management, Seventh Edition Copyright 2014 8  An activity or task is an element of work normally found on the work breakdown structure (WBS) that has an expected duration, a cost, and resource requirements  Activity definition involves developing a more detailed WBS and supporting explanations to understand all the work to be done so you can develop realistic cost and duration estimates Information Technology Project Management, Seventh Edition Copyright 2014 9  An activity list is a tabulation of activities to be included on a project schedule that includes ◦ the activity name ◦ an activity identifier or number ◦ a brief description of the activity  Activity attributes provide more information such as predecessors, successors, logical relationships, leads and lags, resource requirements, constraints, imposed dates, and assumptions related to the activity Information Technology Project Management, Seventh Edition Copyright 2014 10  A milestone is a significant event that normally has no duration  It often takes several activities and a lot of work to complete a milestone  They’re useful tools for setting schedule goals and monitoring progress  Examples include obtaining customer sign-off on key documents or completion of specific products Information Technology Project Management, Seventh Edition Copyright 2014 11  Involves reviewing activities and determining dependencies  A dependency or relationship is the sequencing of project activities or tasks  You must determine dependencies in order to use critical path analysis Information Technology Project Management, Seventh Edition Copyright 2014 12  Mandatory dependencies: inherent in the nature of the work being performed on a project, sometimes referred to as hard logic. For example, you cannot test code until after the code is written.  Discretionary dependencies: defined by the project team. sometimes referred to as soft logic and should be used with care since they may limit later scheduling options. Example: Do not start the detailed design of a new information system until the users sign off on all of the analysis works.  External dependencies: involve relationships between project and non-project activities. For example, the installation of a new operating system and other software may depend on delivery of new hardware from an external supplier. Information Technology Project Management, Seventh Edition Copyright 2014 13  Network diagrams are the preferred technique for showing activity sequencing  A network diagram is a schematic display of the logical relationships among, or sequencing of, project activities  Two main formats are the arrow and precedence diagramming methods Information Technology Project Management, Seventh Edition Copyright 2014 14 Information Technology Project Management, Seventh Edition Copyright 2014 15  Also called activity-on-arrow (AOA) network diagrams  Activities are represented by arrows  Nodes or circles are the starting and ending points of activities  Can only show finish-to-start dependencies Information Technology Project Management, Seventh Edition Copyright 2014 16 1. Find all of the activities that start at node 1. Draw their finish nodes and draw arrows between node 1 and those finish nodes. Put the activity letter or name and duration estimate on the associated arrow 2. Continuing drawing the network diagram, working from left to right. Look for bursts and merges. Bursts occur when a single node is followed by two or more activities. A merge occurs when two or more nodes precede a single node 3. Continue drawing the project network diagram until all activities are included on the diagram that have dependencies 4. As a rule of thumb, all arrowheads should face toward the right, and no arrows should cross on an AOA network diagram Information Technology Project Management, Seventh Edition Copyright 2014 17  Activities are represented by boxes  Arrows show relationships between activities  More popular than ADM method and used by project management software  Better at showing different types of dependencies Information Technology Project Management, Seventh Edition Copyright 2014 18 Examples : Finish-to-start dependency: you cannot provide user training until a new system has been installed. Start-to-start dependency: On IT projects, a group of activities might start simultaneously, such as the many tasks that occur when a new system goes live. Finish-to-finish dependency: quality control efforts cannot finish before production finishes Start-to-finish dependency: raw materials should be ready for the manufacturing process to begin Information Technology Project Management, Seventh Edition Copyright 2014 19 Information Technology Project Management, Seventh Edition Copyright 2014 20  Before estimating activity durations, you must have a good idea of the quantity and type of resources that will be assigned to each activity; resources are people, equipment, and materials  Consider important issues in estimating resources ◦ How difficult will it be to do specific activities on this project? ◦ What is the organization’s history in doing similar activities? ◦ Are the required resources available?  A resource breakdown structure is a hierarchical structure that identifies the project’s resources by category and type Information Technology Project Management, Seventh Edition Copyright 2014 21  Duration includes the actual amount of time worked on an activity plus elapsed time  Effort is the number of workdays or work hours required to complete a task  Effort does not normally equal duration  People doing the work should help create estimates, and an expert should review them Information Technology Project Management, Seventh Edition Copyright 2014 22  Instead of providing activity estimates as a discrete number, such as four weeks, it’s often helpful to create a three-point estimate ◦ an estimate that includes an optimistic, most likely, and pessimistic estimate, such as three weeks for the optimistic, four weeks for the most likely, and five weeks for the pessimistic estimate  Three-point estimates are needed for PERT and Monte Carlo simulations Information Technology Project Management, Seventh Edition Copyright 2014 23  Uses results of the other time management processes to determine the start and end date of the project  Ultimate goal is to create a realistic project schedule that provides a basis for monitoring project progress for the time dimension of the project  Important tools and techniques include Gantt charts, critical path analysis, and critical chain scheduling, and PERT analysis Information Technology Project Management, Seventh Edition Copyright 2014 24  Gantt charts provide a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a calendar format  Symbols include: ◦ A black diamond: a milestones ◦ Thick black bars: summary tasks ◦ Lighter horizontal bars: durations of tasks ◦ Arrows: dependencies between tasks Information Technology Project Management, Seventh Edition Copyright 2014 25 Task Sheet View Information Technology Project Management, Seventh Edition Copyright 2014 26 Information Technology Project Management, Seventh Edition Copyright 2014 27  Many people like to focus on meeting milestones, especially for large projects  Milestones emphasize important events or accomplishments on projects  Normally create milestone by entering tasks with a zero duration, or you can mark any task as a milestone Information Technology Project Management, Seventh Edition Copyright 2014 28  Milestones should be ◦ Specific ◦ Measurable ◦ Assignable ◦ Realistic ◦ Time-framed Information Technology Project Management, Seventh Edition Copyright 2014 29  Schedule risk is inherent in the development of complex systems. Luc Richard, the founder of www.projectmangler.com, suggests that project managers can reduce schedule risk through project milestones, a best practice that involves identifying and tracking significant points or achievements in the project. The five key points of using project milestones include the following: 1. Define milestones early in the project and include them in the Gantt chart to provide a visual guide 2. Keep milestones small and frequent 3. The set of milestones must be all-encompassing 4. Each milestone must be binary, meaning it is either complete or incomplete. 5. Carefully monitor the critical path Information Technology Project Management, Seventh Edition Copyright 2014 30 Information Technology Project Management, Seventh Edition Copyright 2014 31  CPM is a network diagramming technique used to predict total project duration  A critical path for a project is the series of activities that determines the earliest time by which the project can be completed  The critical path is the longest path through the network diagram and has the least amount of slack or float  Slack or float is the amount of time an activity may be delayed without delaying a succeeding activity or the project finish date Information Technology Project Management, Seventh Edition Copyright 2014 32  First develop a good network diagram  Add the duration estimates for all activities on each path through the network diagram  The longest path is the critical path  If one or more of the activities on the critical path takes longer than planned, the whole project schedule will slip unless the project manager takes corrective action Information Technology Project Management, Seventh Edition Copyright 2014 33 Information Technology Project Management, Seventh Edition Copyright 2014 34  A project team at Apple computer put a stuffed gorilla on the top of the cubicle of the person currently managing critical task  The critical path is not the one with all the critical activities; it only accounts for time ◦ Remember the example of growing grass being on the critical path for Disney’s Animal Kingdom  There can be more than one critical path if the lengths of two or more paths are the same  The critical path can change as the Informationproject progresses Technology Project Management, Seventh Edition Copyright 2014 35  Free slack or free float is the amount of time an activity can be delayed without delaying the early start of any immediately following activities  Total slack or total float is the amount of time an activity may be delayed from its early start without delaying the planned project finish date  A forward pass through the network diagram determines the early start and finish dates  A backward pass determines the late start and finish dates Information Technology Project Management, Seventh Edition Copyright 2014 36 Information Technology Project Management, Seventh Edition Copyright 2014 37 Calculating Early and Late Start and Finish Dates Information Technology Project Management, Seventh Edition Copyright 2014 Information Technology Project Management, Seventh Edition Copyright 2014 39  Three main techniques for shortening schedules ◦ Shortening durations of critical activities/tasks by adding more resources or changing their scope ◦ Crashing activities by obtaining the greatest amount of schedule compression for the least incremental cost ◦ Fast tracking activities by doing them in parallel or overlapping them Information Technology Project Management, Seventh Edition Copyright 2014 40  It is important to update project schedule information to meet time goals for a project  The critical path may change as you enter actual start and finish dates  If you know the project completion date will slip, negotiate with the project sponsor Information Technology Project Management, Seventh Edition Copyright 2014 41  Critical chain scheduling ◦ a method of scheduling that considers limited resources when creating a project schedule and includes buffers to protect the project completion date  Uses the Theory of Constraints (TOC) ◦ a management philosophy developed by Eliyahu M. Goldratt and introduced in his book The Goal.  Attempts to minimize multitasking ◦ when a resource works on more than one task at a time Information Technology Project Management, Seventh Edition Copyright 2014 42 Information Technology Project Management, Seventh Edition Copyright 2014 43  A buffer is additional time to complete a task  Murphy’s Law states that if something can go wrong, it will  Parkinson’s Law states that work expands to fill the time allowed  In traditional estimates, people often add a buffer to each task and use it if it’s needed or not  Critical chain scheduling removes buffers from individual tasks and instead creates ◦ a project buffer or additional time added before the project’s due date ◦ feeding buffers or additional time added before tasks on the critical path Information Technology Project Management, Seventh Edition Copyright 2014 44 Information Technology Project Management, Seventh Edition Copyright 2014 45  PERT is a network analysis technique used to estimate project duration when there is a high degree of uncertainty about the individual activity duration estimates  PERT uses probabilistic time estimates ◦ duration estimates based on using optimistic, most likely, and pessimistic estimates of activity durations, or a three- point estimate Information Technology Project Management, Seventh Edition Copyright 2014 46  PERT weighted average = optimistic time + 4X most likely time + pessimistic time 6 Example: PERT weighted average = 8 workdays + 4 X 10 workdays + 24 workdays = 12 days 6 where optimistic time= 8 days most likely time = 10 days, and pessimistic time = 24 days Therefore, you’d use 12 days on the network diagram instead of 10 when using PERT for the above example Information Technology Project Management, Seventh Edition Copyright 2014 47  Perform reality checks on schedules  Allow for contingencies  Don’t plan for everyone to work at 100% capacity all the time  Hold progress meetings with stakeholders and be clear and honest in communicating schedule issues Information Technology Project Management, Seventh Edition Copyright 2014 48  Goals are to know the status of the schedule, influence factors that cause schedule changes, determine that the schedule has changed, and manage changes when they occur  Tools and techniques include ◦ Progress reports ◦ A schedule change control system ◦ Project management software, including schedule comparison charts like the tracking Gantt chart ◦ Variance analysis, such as analyzing float or slack ◦ Performance management, such as earned value (chapter 7) Information Technology Project Management, Seventh Edition Copyright 2014 49  First review the draft schedule or estimated completion date in the project charter  Prepare a more detailed schedule with the project team  Make sure the schedule is realistic and followed  Example: no single resource is utilized more than 75 percent. The actual inefficiency estimate should be assessed for each individual organization, but typically it will vary between 70 and 80 percent.  Alert top management well in advance if there are schedule problems Information Technology Project Management, Seventh Edition Copyright 2014 50  Strong leadership helps projects succeed more than good PERT charts  Project managers should use ◦ empowerment ◦ incentives ◦ discipline ◦ negotiation Information Technology Project Management, Seventh Edition Copyright 2014 51  Mittal Steel Poland earned Poland’s Project Excellence Award in 2007 for implementing a SAP system  Derek Prior, research director at AMR Research, identified three things the most successful SAP implementation projects do to deliver business benefits: ◦ Form a global competence centre ◦ Identify super-users for each location ◦ Provide ongoing involvement of managers in business processes so they feel they own these processes Information Technology Project Management, Seventh Edition Copyright 2014 52  Software for facilitating communications helps people exchange schedule-related information  Decision support models help analyze trade-offs that can be made  Project management software can help in various time management areas Information Technology Project Management, Seventh Edition Copyright 2014 53  Microsoft lists dozens of examples of how customers benefit from using Project 2010. One such customer, Amdocs, a global provider of customer experience systems (CES) software, wanted to help its IT project teams work more efficiently  Employees now have Web-based access from any location, managers have better project visibility, and the company can extend the centralized solution to include more users and applications. Amdocs can now deploy Project Server 2010 in less than a day, or 50 percent faster. Only one person is needed to manage the shared infrastructure. Information Technology Project Management, Seventh Edition Copyright 2014 54  Many people misuse project management software because they don’t understand important concepts and have not had training  You must enter dependencies to have dates adjust automatically and to determine the critical path  You must enter actual schedule information to compare planned and actual progress Information Technology Project Management, Seventh Edition Copyright 2014 55  Project time management is often cited as the main source of conflict on projects, and most IT projects exceed time estimates  Main processes include ◦ Plan schedule management ◦ Define activities ◦ Sequence activities ◦ Estimate activity resources ◦ Estimate activity durations ◦ Develop schedule ◦ Control schedule Information Technology Project Management, Seventh Edition Copyright 2014 56

Use Quizgecko on...
Browser
Browser