CCDC 2 - 2008 Stipulated Price Contract PDF

Summary

This document is a stipulated price contract, outlining the terms and conditions for a construction project. It details aspects of payment, changes in work, and dispute resolution. The contract is copyrighted by the Canadian Construction Documents Committee (CCDC).

Full Transcript

TABLE OF CONTENTS AGREEMENT BETWEEN OWNER AND CONTRACTOR PART 5 PAYMENT A-1 The Work GC 5.1 Financing Information Required of the Owner A-2 Agreements and Amendments GC 5.2 Applications for...

TABLE OF CONTENTS AGREEMENT BETWEEN OWNER AND CONTRACTOR PART 5 PAYMENT A-1 The Work GC 5.1 Financing Information Required of the Owner A-2 Agreements and Amendments GC 5.2 Applications for Progress Payment A-3 Contract Documents GC 5.3 Progress Payment A-4 Contract Price GC 5.4 Substantial Performance of the Work A-5 Payment GC 5.5 Payment of Holdback upon Substantial Performance of the Work A-6 Receipt of and Addresses for Notices in Writing GC 5.6 Progressive Release of Holdback A-7 Language of the Contract GC 5.7 Final Payment A-8 Succession GC 5.8 Withholding of Payment GC 5.9 Non-conforming Work DEFINITIONS 1. Change Directive PART 6 CHANGES IN THE WORK 2. Change Order GC 6.1 Owner’s Right to Make Changes 3. Construction Equipment GC 6.2 Change Order 4. Consultant GC 6.3 Change Directive 5. Contract GC 6.4 Concealed or Unknown Conditions 6. Contract Documents GC 6.5 Delays 7. Contract Price GC 6.6 Claims for a Change in Contract Price 8. Contract Time 9. Contractor PART 7 DEFAULT NOTICE 10. Drawings GC 7.1 Owner's Right to Perform the Work, Terminate the Contractor’s Right to 11. Notice in Writing Continue with the Work or Terminate the Contract 12. Owner GC 7.2 Contractor's Right to Suspend the Work or Terminate the Contract 13. Place of the Work 14. Product PART 8 DISPUTE RESOLUTION 15. Project GC 8.1 Authority of the Consultant 16. Provide GC 8.2 Negotiation, Mediation and Arbitration 17. Shop Drawings GC 8.3 Retention of Rights 18. Specifications 19. Subcontractor PART 9 PROTECTION OF PERSONS AND PROPERTY 20. Substantial Performance of the Work GC 9.1 Protection of Work and Property 21. Supplemental Instruction GC 9.2 Toxic and Hazardous Substances 22. Supplier GC 9.3 Artifacts and Fossils 23. Temporary Work GC 9.4 Construction Safety 24. Value Added Taxes GC 9.5 Mould 25. Work 26. Working Day PART 10 GOVERNING REGULATIONS GC 10.1 Taxes and Duties GENERAL CONDITIONS OF THE STIPULATED PRICE CONTRACT GC 10.2 Laws, Notices, Permits, and Fees GC 10.3 Patent Fees PART 1 GENERAL PROVISIONS GC 10.4 Workers' Compensation GC 1.1 Contract Documents GC 1.2 Law of the Contract PART 11 INSURANCE AND CONTRACT SECURITY GC 1.3 Rights and Remedies GC 11.1 Insurance GC 1.4 Assignment GC 11.2 Contract Security PART 2 ADMINISTRATION OF THE CONTRACT PART 12 INDEMNIFICATION, WAIVER OF CLAIMS AND WARRANTY GC 2.1 Authority of the Consultant GC 12.1 Indemnification GC 2.2 Role of the Consultant GC 12.2 Waiver of Claims GC 2.3 Review and Inspection of the Work GC 12.3 Warranty GC 2.4 Defective Work The Canadian Construction Documents Committee (CCDC) is a national joint PART 3 EXECUTION OF THE WORK committee responsible for the development, production and review of standard GC 3.1 Control of the Work Canadian construction contracts, forms and guides. Formed in 1974 the CCDC is GC 3.2 Construction by Owner or Other Contractors made up of volunteer representatives from: GC 3.3 Temporary Work Public Sector Owners GC 3.4 Document Review Private Sector Owners GC 3.5 Construction Schedule Canadian Bar Association (Ex-Officio) GC 3.6 Supervision * The Association of Canadian Engineering Companies GC 3.7 Subcontractors and Suppliers * The Canadian Construction Association GC 3.8 Labour and Products * Construction Specifications Canada GC 3.9 Documents at the Site * The Royal Architectural Institute of Canada GC 3.10 Shop Drawings GC 3.11 Use of the Work *Committee policy and procedures are directed and approved by the four constituent GC 3.12 Cutting and Remedial Work national organizations. GC 3.13 Cleanup CCDC 2 is the product of a consensus-building process aimed at balancing the interests of all parties on the construction project. It reflects recommended industry PART 4 ALLOWANCES practices. CCDC 2 can have important consequences. The CCDC and its GC 4.1 Cash Allowances constituent member organizations do not accept any responsibility or liability for GC 4.2 Contingency Allowance loss or damage which may be suffered as a result of the use or interpretation of CCDC 2. CCDC Copyright 2008 Must not be copied in whole or in part without the written permission of the CCDC. Standard Construction Document CCDC 2 – 2008 DEFINITIONS The following Definitions shall apply to all Contract Documents. 1. Change Directive A Change Directive is a written instruction prepared by the Consultant and signed by the Owner directing the Contractor to proceed with a change in the Work within the general scope of the Contract Documents prior to the Owner and the Contractor agreeing upon adjustments in the Contract Price and the Contract Time. 2. Change Order A Change Order is a written amendment to the Contract prepared by the Consultant and signed by the Owner and the Contractor stating their agreement upon: - a change in the Work; - the method of adjustment or the amount of the adjustment in the Contract Price, if any; and - the extent of the adjustment in the Contract Time, if any. 3. Construction Equipment Construction Equipment means all machinery and equipment, either operated or not operated, that is required for preparing, fabricating, conveying, erecting, or otherwise performing the Work but is not incorporated into the Work. 4. Consultant The Consultant is the person or entity engaged by the Owner and identified as such in the Agreement. The Consultant is the Architect, the Engineer or entity licensed to practise in the province or territory of the Place of the Work. The term Consultant means the Consultant or the Consultant's authorized representative. 5. Contract The Contract is the undertaking by the parties to perform their respective duties, responsibilities and obligations as prescribed in the Contract Documents and represents the entire agreement between the parties. 6. Contract Documents The Contract Documents consist of those documents listed in Article A-3 of the Agreement - CONTRACT DOCUMENTS and amendments agreed upon between the parties. 7. Contract Price The Contract Price is the amount stipulated in Article A-4 of the Agreement - CONTRACT PRICE. 8. Contract Time The Contract Time is the time stipulated in paragraph 1.3 of Article A-1 of the Agreement - THE WORK from commencement of the Work to Substantial Performance of the Work. 9. Contractor The Contractor is the person or entity identified as such in the Agreement. The term Contractor means the Contractor or the Contractor's authorized representative as designated to the Owner in writing. 10. Drawings The Drawings are the graphic and pictorial portions of the Contract Documents, wherever located and whenever issued, showing the design, location and dimensions of the Work, generally including plans, elevations, sections, details, and diagrams. 11. Notice in Writing A Notice in Writing, where identified in the Contract Documents, is a written communication between the parties or between them and the Consultant that is transmitted in accordance with the provisions of Article A-6 of the Agreement – RECEIPT OF AND ADDRESSES FOR NOTICES IN WRITING. 12. Owner The Owner is the person or entity identified as such in the Agreement. The term Owner means the Owner or the Owner's authorized agent or representative as designated to the Contractor in writing, but does not include the Consultant. 13. Place of the Work The Place of the Work is the designated site or location of the Work identified in the Contract Documents. 14. Product Product or Products means material, machinery, equipment, and fixtures forming the Work, but does not include Construction Equipment. CCDC 2 - 2008 File 007100 6 Note: This contract is protected by copyright. Use of a CCDC 2 document not containing a CCDC 2 copyright seal constitutes an infringement of copyright. Only sign this contract if the document cover page bears a CCDC 2 copyright seal to demonstrate that it is intended by the parties to be an accurate and unamended version of CCDC 2 – 2008 except to the extent that any alterations, additions or modifications are set forth in supplementary conditions. 15. Project The Project means the total construction contemplated of which the Work may be the whole or a part. 16. Provide Provide means to supply and install. 17. Shop Drawings Shop Drawings are drawings, diagrams, illustrations, schedules, performance charts, brochures, Product data, and other data which the Contractor provides to illustrate details of portions of the Work. 18. Specifications The Specifications are that portion of the Contract Documents, wherever located and whenever issued, consisting of the written requirements and standards for Products, systems, workmanship, quality, and the services necessary for the performance of the Work. 19. Subcontractor A Subcontractor is a person or entity having a direct contract with the Contractor to perform a part or parts of the Work at the Place of the Work. 20. Substantial Performance of the Work Substantial Performance of the Work is as defined in the lien legislation applicable to the Place of the Work. If such legislation is not in force or does not contain such definition, or if the Work is governed by the Civil Code of Quebec, Substantial Performance of the Work shall have been reached when the Work is ready for use or is being used for the purpose intended and is so certified by the Consultant. 21. Supplemental Instruction A Supplemental Instruction is an instruction, not involving adjustment in the Contract Price or Contract Time, in the form of Specifications, Drawings, schedules, samples, models or written instructions, consistent with the intent of the Contract Documents. It is to be issued by the Consultant to supplement the Contract Documents as required for the performance of the Work. 22. Supplier A Supplier is a person or entity having a direct contract with the Contractor to supply Products. 23. Temporary Work Temporary Work means temporary supports, structures, facilities, services, and other temporary items, excluding Construction Equipment, required for the execution of the Work but not incorporated into the Work. 24. Value Added Taxes Value Added Taxes means such sum as shall be levied upon the Contract Price by the Federal or any Provincial or Territorial Government and is computed as a percentage of the Contract Price and includes the Goods and Services Tax, the Quebec Sales Tax, the Harmonized Sales Tax, and any similar tax, the collection and payment of which have been imposed on the Contractor by the tax legislation. 25. Work The Work means the total construction and related services required by the Contract Documents. 26. Working Day Working Day means a day other than a Saturday, Sunday, statutory holiday, or statutory vacation day that is observed by the construction industry in the area of the Place of the Work. CCDC 2 - 2008 File 007100 7 Note: This contract is protected by copyright. Use of a CCDC 2 document not containing a CCDC 2 copyright seal constitutes an infringement of copyright. Only sign this contract if the document cover page bears a CCDC 2 copyright seal to demonstrate that it is intended by the parties to be an accurate and unamended version of CCDC 2 – 2008 except to the extent that any alterations, additions or modifications are set forth in supplementary conditions. Standard Construction Document CCDC 2 – 2008 GENERAL CONDITIONS OF THE STIPULATED PRICE CONTRACT PART 1 GENERAL PROVISIONS GC 1.1 CONTRACT DOCUMENTS 1.1.1 The intent of the Contract Documents is to include the labour, Products and services necessary for the performance of the Work by the Contractor in accordance with these documents. It is not intended, however, that the Contractor shall supply products or perform work not consistent with, not covered by, or not properly inferable from the Contract Documents. 1.1.2 Nothing contained in the Contract Documents shall create any contractual relationship between:.1 the Owner and a Subcontractor, a Supplier, or their agent, employee, or other person performing any portion of the Work..2 the Consultant and the Contractor, a Subcontractor, a Supplier, or their agent, employee, or other person performing any portion of the Work. 1.1.3 The Contract Documents are complementary, and what is required by any one shall be as binding as if required by all. 1.1.4 Words and abbreviations which have well known technical or trade meanings are used in the Contract Documents in accordance with such recognized meanings. 1.1.5 References in the Contract Documents to the singular shall be considered to include the plural as the context requires. 1.1.6 Neither the organization of the Specifications nor the arrangement of Drawings shall control the Contractor in dividing the work among Subcontractors and Suppliers. 1.1.7 If there is a conflict within the Contract Documents:.1 the order of priority of documents, from highest to lowest, shall be − the Agreement between the Owner and the Contractor, − the Definitions, − Supplementary Conditions, − the General Conditions, − Division 1 of the Specifications, − technical Specifications, − material and finishing schedules, − the Drawings..2 Drawings of larger scale shall govern over those of smaller scale of the same date..3 dimensions shown on Drawings shall govern over dimensions scaled from Drawings..4 later dated documents shall govern over earlier documents of the same type. 1.1.8 The Owner shall provide the Contractor, without charge, sufficient copies of the Contract Documents to perform the Work. 1.1.9 Specifications, Drawings, models, and copies thereof furnished by the Consultant are and shall remain the Consultant's property, with the exception of the signed Contract sets, which shall belong to each party to the Contract. All Specifications, Drawings and models furnished by the Consultant are to be used only with respect to the Work and are not to be used on other work. These Specifications, Drawings and models are not to be copied or altered in any manner without the written authorization of the Consultant. 1.1.10 Models furnished by the Contractor at the Owner's expense are the property of the Owner. GC 1.2 LAW OF THE CONTRACT 1.2.1 The law of the Place of the Work shall govern the interpretation of the Contract. GC 1.3 RIGHTS AND REMEDIES 1.3.1 Except as expressly provided in the Contract Documents, the duties and obligations imposed by the Contract Documents and the rights and remedies available thereunder shall be in addition to and not a limitation of any duties, obligations, rights, and remedies otherwise imposed or available by law. 1.3.2 No action or failure to act by the Owner, Consultant or Contractor shall constitute a waiver of any right or duty afforded any of them under the Contract, nor shall any such action or failure to act constitute an approval of or acquiescence in any breach thereunder, except as may be specifically agreed in writing. CCDC 2 – 2008 File 007213 8 Note: This contract is protected by copyright. Use of a CCDC 2 document not containing a CCDC 2 copyright seal constitutes an infringement of copyright. Only sign this contract if the document cover page bears a CCDC 2 copyright seal to demonstrate that it is intended by the parties to be an accurate and unamended version of CCDC 2 – 2008 except to the extent that any alterations, additions or modifications are set forth in supplementary conditions. GC 1.4 ASSIGNMENT 1.4.1 Neither party to the Contract shall assign the Contract or a portion thereof without the written consent of the other, which consent shall not be unreasonably withheld. PART 2 ADMINISTRATION OF THE CONTRACT GC 2.1 AUTHORITY OF THE CONSULTANT 2.1.1 The Consultant will have authority to act on behalf of the Owner only to the extent provided in the Contract Documents, unless otherwise modified by written agreement as provided in paragraph 2.1.2. 2.1.2 The duties, responsibilities and limitations of authority of the Consultant as set forth in the Contract Documents shall be modified or extended only with the written consent of the Owner, the Contractor and the Consultant. 2.1.3 If the Consultant's employment is terminated, the Owner shall immediately appoint or reappoint a Consultant against whom the Contractor makes no reasonable objection and whose status under the Contract Documents shall be that of the former Consultant. GC 2.2 ROLE OF THE CONSULTANT 2.2.1 The Consultant will provide administration of the Contract as described in the Contract Documents. 2.2.2 The Consultant will visit the Place of the Work at intervals appropriate to the progress of construction to become familiar with the progress and quality of the work and to determine if the Work is proceeding in general conformity with the Contract Documents. 2.2.3 If the Owner and the Consultant agree, the Consultant will provide at the Place of the Work, one or more project representatives to assist in carrying out the Consultant's responsibilities. The duties, responsibilities and limitations of authority of such project representatives shall be as set forth in writing to the Contractor. 2.2.4 The Consultant will promptly inform the Owner of the date of receipt of the Contractor’s applications for payment as provided in paragraph 5.3.1.1 of GC 5.3 – PROGRESS PAYMENT. 2.2.5 Based on the Consultant's observations and evaluation of the Contractor's applications for payment, the Consultant will determine the amounts owing to the Contractor under the Contract and will issue certificates for payment as provided in Article A-5 of the Agreement - PAYMENT, GC 5.3 - PROGRESS PAYMENT and GC 5.7 - FINAL PAYMENT. 2.2.6 The Consultant will not be responsible for and will not have control, charge or supervision of construction means, methods, techniques, sequences, or procedures, or for safety precautions and programs required in connection with the Work in accordance with the applicable construction safety legislation, other regulations or general construction practice. The Consultant will not be responsible for the Contractor's failure to carry out the Work in accordance with the Contract Documents. The Consultant will not have control over, charge of or be responsible for the acts or omissions of the Contractor, Subcontractors, Suppliers, or their agents, employees, or any other persons performing portions of the Work. 2.2.7 Except with respect to GC 5.1 - FINANCING INFORMATION REQUIRED OF THE OWNER, the Consultant will be, in the first instance, the interpreter of the requirements of the Contract Documents. 2.2.8 Matters in question relating to the performance of the Work or the interpretation of the Contract Documents shall be initially referred in writing to the Consultant by the party raising the question for interpretations and findings and copied to the other party. 2.2.9 Interpretations and findings of the Consultant shall be consistent with the intent of the Contract Documents. In making such interpretations and findings the Consultant will not show partiality to either the Owner or the Contractor. 2.2.10 The Consultant’s interpretations and findings will be given in writing to the parties within a reasonable time. 2.2.11 With respect to claims for a change in Contract Price, the Consultant will make findings as set out in GC 6.6 – CLAIMS FOR A CHANGE IN CONTRACT PRICE. 2.2.12 The Consultant will have authority to reject work which in the Consultant's opinion does not conform to the requirements of the Contract Documents. Whenever the Consultant considers it necessary or advisable, the Consultant will have authority to require inspection or testing of work, whether or not such work is fabricated, installed or completed. However, neither the authority of the Consultant to act nor any decision either to exercise or not to exercise such authority shall give rise to any duty or responsibility of the Consultant to the Contractor, Subcontractors, Suppliers, or their agents, employees, or other persons performing any of the Work. CCDC 2 – 2008 File 007213 9 Note: This contract is protected by copyright. Use of a CCDC 2 document not containing a CCDC 2 copyright seal constitutes an infringement of copyright. Only sign this contract if the document cover page bears a CCDC 2 copyright seal to demonstrate that it is intended by the parties to be an accurate and unamended version of CCDC 2 – 2008 except to the extent that any alterations, additions or modifications are set forth in supplementary conditions. 2.2.13 During the progress of the Work the Consultant will furnish Supplemental Instructions to the Contractor with reasonable promptness or in accordance with a schedule for such instructions agreed to by the Consultant and the Contractor. 2.2.14 The Consultant will review and take appropriate action upon Shop Drawings, samples and other Contractor’s submittals, in accordance with the Contract Documents. 2.2.15 The Consultant will prepare Change Orders and Change Directives as provided in GC 6.2 - CHANGE ORDER and GC 6.3 - CHANGE DIRECTIVE. 2.2.16 The Consultant will conduct reviews of the Work to determine the date of Substantial Performance of the Work as provided in GC 5.4 - SUBSTANTIAL PERFORMANCE OF THE WORK. 2.2.17 All certificates issued by the Consultant will be to the best of the Consultant's knowledge, information and belief. By issuing any certificate, the Consultant does not guarantee the Work is correct or complete. 2.2.18 The Consultant will receive and review written warranties and related documents required by the Contract and provided by the Contractor and will forward such warranties and documents to the Owner for the Owner's acceptance. GC 2.3 REVIEW AND INSPECTION OF THE WORK 2.3.1 The Owner and the Consultant shall have access to the Work at all times. The Contractor shall provide sufficient, safe and proper facilities at all times for the review of the Work by the Consultant and the inspection of the Work by authorized agencies. If parts of the Work are in preparation at locations other than the Place of the Work, the Owner and the Consultant shall be given access to such work whenever it is in progress. 2.3.2 If work is designated for tests, inspections or approvals in the Contract Documents, or by the Consultant's instructions, or by the laws or ordinances of the Place of the Work, the Contractor shall give the Consultant reasonable notification of when the work will be ready for review and inspection. The Contractor shall arrange for and shall give the Consultant reasonable notification of the date and time of inspections by other authorities. 2.3.3 The Contractor shall furnish promptly to the Consultant two copies of certificates and inspection reports relating to the Work. 2.3.4 If the Contractor covers, or permits to be covered, work that has been designated for special tests, inspections or approvals before such special tests, inspections or approvals are made, given or completed, the Contractor shall, if so directed, uncover such work, have the inspections or tests satisfactorily completed, and make good covering work at the Contractor's expense. 2.3.5 The Consultant may order any portion or portions of the Work to be examined to confirm that such work is in accordance with the requirements of the Contract Documents. If the work is not in accordance with the requirements of the Contract Documents, the Contractor shall correct the work and pay the cost of examination and correction. If the work is in accordance with the requirements of the Contract Documents, the Owner shall pay the cost of examination and restoration. 2.3.6 The Contractor shall pay the cost of making any test or inspection, including the cost of samples required for such test or inspection, if such test or inspection is designated in the Contract Documents to be performed by the Contractor or is designated by the laws or ordinances applicable to the Place of the Work. 2.3.7 The Contractor shall pay the cost of samples required for any test or inspection to be performed by the Consultant or the Owner if such test or inspection is designated in the Contract Documents. GC 2.4 DEFECTIVE WORK 2.4.1 The Contractor shall promptly correct defective work that has been rejected by the Consultant as failing to conform to the Contract Documents whether or not the defective work has been incorporated in the Work and whether or not the defect is the result of poor workmanship, use of defective products or damage through carelessness or other act or omission of the Contractor. 2.4.2 The Contractor shall make good promptly other contractors' work destroyed or damaged by such corrections at the Contractor's expense. 2.4.3 If in the opinion of the Consultant it is not expedient to correct defective work or work not performed as provided in the Contract Documents, the Owner may deduct from the amount otherwise due to the Contractor the difference in value between the work as performed and that called for by the Contract Documents. If the Owner and the Contractor do not agree on the difference in value, they shall refer the matter to the Consultant for a determination. CCDC 2 – 2008 File 007213 10 Note: This contract is protected by copyright. Use of a CCDC 2 document not containing a CCDC 2 copyright seal constitutes an infringement of copyright. Only sign this contract if the document cover page bears a CCDC 2 copyright seal to demonstrate that it is intended by the parties to be an accurate and unamended version of CCDC 2 – 2008 except to the extent that any alterations, additions or modifications are set forth in supplementary conditions. PART 3 EXECUTION OF THE WORK GC 3.1 CONTROL OF THE WORK 3.1.1 The Contractor shall have total control of the Work and shall effectively direct and supervise the Work so as to ensure conformity with the Contract Documents. 3.1.2 The Contractor shall be solely responsible for construction means, methods, techniques, sequences, and procedures and for co-ordinating the various parts of the Work under the Contract. GC 3.2 CONSTRUCTION BY OWNER OR OTHER CONTRACTORS 3.2.1 The Owner reserves the right to award separate contracts in connection with other parts of the Project to other contractors and to perform work with own forces. 3.2.2 When separate contracts are awarded for other parts of the Project, or when work is performed by the Owner's own forces, the Owner shall:.1 provide for the co-ordination of the activities and work of other contractors and Owner's own forces with the Work of the Contract;.2 assume overall responsibility for compliance with the applicable health and construction safety legislation at the Place of the Work;.3 enter into separate contracts with other contractors under conditions of contract which are compatible with the conditions of the Contract;.4 ensure that insurance coverage is provided to the same requirements as are called for in GC 11.1 - INSURANCE and co- ordinate such insurance with the insurance coverage of the Contractor as it affects the Work; and.5 take all reasonable precautions to avoid labour disputes or other disputes on the Project arising from the work of other contractors or the Owner's own forces. 3.2.3 When separate contracts are awarded for other parts of the Project, or when work is performed by the Owner's own forces, the Contractor shall:.1 afford the Owner and other contractors reasonable opportunity to store their products and execute their work;.2 cooperate with other contractors and the Owner in reviewing their construction schedules; and.3 promptly report to the Consultant in writing any apparent deficiencies in the work of other contractors or of the Owner's own forces, where such work affects the proper execution of any portion of the Work, prior to proceeding with that portion of the Work. 3.2.4 Where the Contract Documents identify work to be performed by other contractors or the Owner’s own forces, the Contractor shall co-ordinate and schedule the Work with the work of other contractors and the Owner’s own forces as specified in the Contract Documents. 3.2.5 Where a change in the Work is required as a result of the co-ordination and integration of the work of other contractors or Owner's own forces with the Work, the changes shall be authorized and valued as provided in GC 6.1 – OWNER’S RIGHT TO MAKE CHANGES, GC 6.2 - CHANGE ORDER and GC 6.3 - CHANGE DIRECTIVE. 3.2.6 Disputes and other matters in question between the Contractor and other contractors shall be dealt with as provided in Part 8 of the General Conditions - DISPUTE RESOLUTION provided the other contractors have reciprocal obligations. The Contractor shall be deemed to have consented to arbitration of any dispute with any other contractor whose contract with the Owner contains a similar agreement to arbitrate. GC 3.3 TEMPORARY WORK 3.3.1 The Contractor shall have the sole responsibility for the design, erection, operation, maintenance, and removal of Temporary Work. 3.3.2 The Contractor shall engage and pay for registered professional engineering personnel skilled in the appropriate disciplines to perform those functions referred to in paragraph 3.3.1 where required by law or by the Contract Documents and in all cases where such Temporary Work is of such a nature that professional engineering skill is required to produce safe and satisfactory results. CCDC 2 – 2008 File 007213 11 Note: This contract is protected by copyright. Use of a CCDC 2 document not containing a CCDC 2 copyright seal constitutes an infringement of copyright. Only sign this contract if the document cover page bears a CCDC 2 copyright seal to demonstrate that it is intended by the parties to be an accurate and unamended version of CCDC 2 – 2008 except to the extent that any alterations, additions or modifications are set forth in supplementary conditions. 3.3.3 Notwithstanding the provisions of GC 3.1 - CONTROL OF THE WORK, paragraphs 3.3.1 and 3.3.2 or provisions to the contrary elsewhere in the Contract Documents where such Contract Documents include designs for Temporary Work or specify a method of construction in whole or in part, such designs or methods of construction shall be considered to be part of the design of the Work and the Contractor shall not be held responsible for that part of the design or the specified method of construction. The Contractor shall, however, be responsible for the execution of such design or specified method of construction in the same manner as for the execution of the Work. GC 3.4 DOCUMENT REVIEW 3.4.1 The Contractor shall review the Contract Documents and shall report promptly to the Consultant any error, inconsistency or omission the Contractor may discover. Such review by the Contractor shall be to the best of the Contractor's knowledge, information and belief and in making such review the Contractor does not assume any responsibility to the Owner or the Consultant for the accuracy of the review. The Contractor shall not be liable for damage or costs resulting from such errors, inconsistencies or omissions in the Contract Documents, which the Contractor did not discover. If the Contractor does discover any error, inconsistency or omission in the Contract Documents, the Contractor shall not proceed with the work affected until the Contractor has received corrected or missing information from the Consultant. GC 3.5 CONSTRUCTION SCHEDULE 3.5.1 The Contractor shall:.1 prepare and submit to the Owner and the Consultant prior to the first application for payment, a construction schedule that indicates the timing of the major activities of the Work and provides sufficient detail of the critical events and their inter-relationship to demonstrate the Work will be performed in conformity with the Contract Time;.2 monitor the progress of the Work relative to the construction schedule and update the schedule on a monthly basis or as stipulated by the Contract Documents; and.3 advise the Consultant of any revisions required to the schedule as the result of extensions of the Contract Time as provided in Part 6 of the General Conditions - CHANGES IN THE WORK. GC 3.6 SUPERVISION 3.6.1 The Contractor shall provide all necessary supervision and appoint a competent representative who shall be in attendance at the Place of the Work while work is being performed. The appointed representative shall not be changed except for valid reason. 3.6.2 The appointed representative shall represent the Contractor at the Place of the Work. Information and instructions provided by the Consultant to the Contractor’s appointed representative shall be deemed to have been received by the Contractor, except with respect to Article A-6 of the Agreement – RECEIPT OF AND ADDRESSES FOR NOTICES IN WRITING. GC 3.7 SUBCONTRACTORS AND SUPPLIERS 3.7.1 The Contractor shall preserve and protect the rights of the parties under the Contract with respect to work to be performed under subcontract, and shall:.1 enter into contracts or written agreements with Subcontractors and Suppliers to require them to perform their work as provided in the Contract Documents;.2 incorporate the terms and conditions of the Contract Documents into all contracts or written agreements with Subcontractors and Suppliers; and.3 be as fully responsible to the Owner for acts and omissions of Subcontractors, Suppliers and of persons directly or indirectly employed by them as for acts and omissions of persons directly employed by the Contractor. 3.7.2 The Contractor shall indicate in writing, if requested by the Owner, those Subcontractors or Suppliers whose bids have been received by the Contractor which the Contractor would be prepared to accept for the performance of a portion of the Work. Should the Owner not object before signing the Contract, the Contractor shall employ those Subcontractors or Suppliers so identified by the Contractor in writing for the performance of that portion of the Work to which their bid applies. 3.7.3 The Owner may, for reasonable cause, at any time before the Owner has signed the Contract, object to the use of a proposed Subcontractor or Supplier and require the Contractor to employ one of the other subcontract bidders. 3.7.4 If the Owner requires the Contractor to change a proposed Subcontractor or Supplier, the Contract Price and Contract Time shall be adjusted by the differences occasioned by such required change. CCDC 2 – 2008 File 007213 12 Note: This contract is protected by copyright. Use of a CCDC 2 document not containing a CCDC 2 copyright seal constitutes an infringement of copyright. Only sign this contract if the document cover page bears a CCDC 2 copyright seal to demonstrate that it is intended by the parties to be an accurate and unamended version of CCDC 2 – 2008 except to the extent that any alterations, additions or modifications are set forth in supplementary conditions. 3.7.5 The Contractor shall not be required to employ as a Subcontractor or Supplier, a person or firm to which the Contractor may reasonably object. 3.7.6 The Owner, through the Consultant, may provide to a Subcontractor or Supplier information as to the percentage of the Subcontractor's or Supplier's work which has been certified for payment. GC 3.8 LABOUR AND PRODUCTS 3.8.1 The Contractor shall provide and pay for labour, Products, tools, Construction Equipment, water, heat, light, power, transportation, and other facilities and services necessary for the performance of the Work in accordance with the Contract. 3.8.2 Unless otherwise specified in the Contract Documents, Products provided shall be new. Products which are not specified shall be of a quality consistent with those specified and their use acceptable to the Consultant. 3.8.3 The Contractor shall maintain good order and discipline among the Contractor's employees engaged on the Work and shall not employ on the Work anyone not skilled in the tasks assigned. GC 3.9 DOCUMENTS AT THE SITE 3.9.1 The Contractor shall keep one copy of current Contract Documents, submittals, reports, and records of meetings at the Place of the Work, in good order and available to the Owner and the Consultant. GC 3.10 SHOP DRAWINGS 3.10.1 The Contractor shall provide Shop Drawings as required in the Contract Documents. 3.10.2 The Contractor shall provide Shop Drawings to the Consultant to review in orderly sequence and sufficiently in advance so as to cause no delay in the Work or in the work of other contractors. 3.10.3 Upon request of the Contractor or the Consultant, they shall jointly prepare a schedule of the dates for provision, review and return of Shop Drawings. 3.10.4 The Contractor shall provide Shop Drawings in the form specified, or if not specified, as directed by the Consultant. 3.10.5 Shop Drawings provided by the Contractor to the Consultant shall indicate by stamp, date and signature of the person responsible for the review that the Contractor has reviewed each one of them. 3.10.6 The Consultant's review is for conformity to the design concept and for general arrangement only. 3.10.7 Shop Drawings which require approval of any legally constituted authority having jurisdiction shall be provided to such authority by the Contractor for approval. 3.10.8 The Contractor shall review all Shop Drawings before providing them to the Consultant. The Contractor represents by this review that:.1 the Contractor has determined and verified all applicable field measurements, field construction conditions, Product requirements, catalogue numbers and similar data, or will do so, and.2 the Contractor has checked and co-ordinated each Shop Drawing with the requirements of the Work and of the Contract Documents. 3.10.9 At the time of providing Shop Drawings, the Contractor shall expressly advise the Consultant in writing of any deviations in a Shop Drawing from the requirements of the Contract Documents. The Consultant shall indicate the acceptance or rejection of such deviation expressly in writing. 3.10.10 The Consultant's review shall not relieve the Contractor of responsibility for errors or omissions in the Shop Drawings or for meeting all requirements of the Contract Documents. 3.10.11 The Contractor shall provide revised Shop Drawings to correct those which the Consultant rejects as inconsistent with the Contract Documents, unless otherwise directed by the Consultant. The Contractor shall notify the Consultant in writing of any revisions to the Shop Drawings other than those requested by the Consultant. 3.10.12 The Consultant will review and return Shop Drawings in accordance with the schedule agreed upon, or, in the absence of such schedule, with reasonable promptness so as to cause no delay in the performance of the Work. CCDC 2 – 2008 File 007213 13 Note: This contract is protected by copyright. Use of a CCDC 2 document not containing a CCDC 2 copyright seal constitutes an infringement of copyright. Only sign this contract if the document cover page bears a CCDC 2 copyright seal to demonstrate that it is intended by the parties to be an accurate and unamended version of CCDC 2 – 2008 except to the extent that any alterations, additions or modifications are set forth in supplementary conditions. GC 3.11 USE OF THE WORK 3.11.1 The Contractor shall confine Construction Equipment, Temporary Work, storage of Products, waste products and debris, and operations of employees and Subcontractors to limits indicated by laws, ordinances, permits, or the Contract Documents and shall not unreasonably encumber the Place of the Work. 3.11.2 The Contractor shall not load or permit to be loaded any part of the Work with a weight or force that will endanger the safety of the Work. GC 3.12 CUTTING AND REMEDIAL WORK 3.12.1 The Contractor shall perform the cutting and remedial work required to make the affected parts of the Work come together properly. 3.12.2 The Contractor shall co-ordinate the Work to ensure that the cutting and remedial work is kept to a minimum. 3.12.3 Should the Owner, the Consultant, other contractors or anyone employed by them be responsible for ill-timed work necessitating cutting or remedial work to be performed, the cost of such cutting or remedial work shall be valued as provided in GC 6.1 – OWNER’S RIGHT TO MAKE CHANGES, GC 6.2 - CHANGE ORDER and GC 6.3 - CHANGE DIRECTIVE. 3.12.4 Cutting and remedial work shall be performed by specialists familiar with the Products affected and shall be performed in a manner to neither damage nor endanger the Work. GC 3.13 CLEANUP 3.13.1 The Contractor shall maintain the Work in a safe and tidy condition and free from the accumulation of waste products and debris, other than that caused by the Owner, other contractors or their employees. 3.13.2 Before applying for Substantial Performance of the Work as provided in GC 5.4 – SUBSTANTIAL PERFORMANCE OF THE WORK, the Contractor shall remove waste products and debris, other than that resulting from the work of the Owner, other contractors or their employees, and shall leave the Place of the Work clean and suitable for use or occupancy by the Owner. The Contractor shall remove products, tools, Construction Equipment, and Temporary Work not required for the performance of the remaining work. 3.13.3 Prior to application for the final payment, the Contractor shall remove any remaining products, tools, Construction Equipment, Temporary Work, and waste products and debris, other than those resulting from the work of the Owner, other contractors or their employees. PART 4 ALLOWANCES GC 4.1 CASH ALLOWANCES 4.1.1 The Contract Price includes the cash allowances, if any, stated in the Contract Documents. The scope of work or costs included in such cash allowances shall be as described in the Contract Documents. 4.1.2 The Contract Price, and not the cash allowances, includes the Contractor's overhead and profit in connection with such cash allowances. 4.1.3 Expenditures under cash allowances shall be authorized by the Owner through the Consultant. 4.1.4 Where the actual cost of the Work under any cash allowance exceeds the amount of the allowance, the Contractor shall be compensated for the excess incurred and substantiated plus an amount for overhead and profit on the excess as set out in the Contract Documents. Where the actual cost of the Work under any cash allowance is less than the amount of the allowance, the Owner shall be credited for the unexpended portion of the cash allowance, but not for the Contractor’s overhead and profit on such amount. Multiple cash allowances shall not be combined for the purpose of calculating the foregoing. 4.1.5 The Contract Price shall be adjusted by Change Order to provide for any difference between the amount of each cash allowance and the actual cost of the work under that cash allowance. 4.1.6 The value of the work performed under a cash allowance is eligible to be included in progress payments. 4.1.7 The Contractor and the Consultant shall jointly prepare a schedule that shows when the Consultant and Owner must authorize ordering of items called for under cash allowances to avoid delaying the progress of the Work. CCDC 2 – 2008 File 007213 14 Note: This contract is protected by copyright. Use of a CCDC 2 document not containing a CCDC 2 copyright seal constitutes an infringement of copyright. Only sign this contract if the document cover page bears a CCDC 2 copyright seal to demonstrate that it is intended by the parties to be an accurate and unamended version of CCDC 2 – 2008 except to the extent that any alterations, additions or modifications are set forth in supplementary conditions. GC 4.2 CONTINGENCY ALLOWANCE 4.2.1 The Contract Price includes the contingency allowance, if any, stated in the Contract Documents. 4.2.2 The contingency allowance includes the Contractor's overhead and profit in connection with such contingency allowance. 4.2.3 Expenditures under the contingency allowance shall be authorized and valued as provided in GC 6.1 – OWNER’S RIGHT TO MAKE CHANGES, GC 6.2 - CHANGE ORDER and GC 6.3 - CHANGE DIRECTIVE. 4.2.4 The Contract Price shall be adjusted by Change Order to provide for any difference between the expenditures authorized under paragraph 4.2.3 and the contingency allowance. PART 5 PAYMENT GC 5.1 FINANCING INFORMATION REQUIRED OF THE OWNER 5.1.1 The Owner shall, at the request of the Contractor, before signing the Contract, and promptly from time to time thereafter, furnish to the Contractor reasonable evidence that financial arrangements have been made to fulfill the Owner's obligations under the Contract. 5.1.2 The Owner shall give the Contractor Notice in Writing of any material change in the Owner's financial arrangements to fulfill the Owner's obligations under the Contract during the performance of the Contract. GC 5.2 APPLICATIONS FOR PROGRESS PAYMENT 5.2.1 Applications for payment on account as provided in Article A-5 of the Agreement - PAYMENT may be made monthly as the Work progresses. 5.2.2 Applications for payment shall be dated the last day of each payment period, which is the last day of the month or an alternative day of the month agreed in writing by the parties. 5.2.3 The amount claimed shall be for the value, proportionate to the amount of the Contract, of Work performed and Products delivered to the Place of the Work as of the last day of the payment period. 5.2.4 The Contractor shall submit to the Consultant, at least 15 calendar days before the first application for payment, a schedule of values for the parts of the Work, aggregating the total amount of the Contract Price, so as to facilitate evaluation of applications for payment. 5.2.5 The schedule of values shall be made out in such form and supported by such evidence as the Consultant may reasonably direct and when accepted by the Consultant, shall be used as the basis for applications for payment, unless it is found to be in error. 5.2.6 The Contractor shall include a statement based on the schedule of values with each application for payment. 5.2.7 Applications for payment for Products delivered to the Place of the Work but not yet incorporated into the Work shall be supported by such evidence as the Consultant may reasonably require to establish the value and delivery of the Products. GC 5.3 PROGRESS PAYMENT 5.3.1 After receipt by the Consultant of an application for payment submitted by the Contractor in accordance with GC 5.2 - APPLICATIONS FOR PROGRESS PAYMENT:.1 the Consultant will promptly inform the Owner of the date of receipt of the Contractor’s application for payment,.2 the Consultant will issue to the Owner and copy to the Contractor, no later than 10 calendar days after the receipt of the application for payment, a certificate for payment in the amount applied for, or in such other amount as the Consultant determines to be properly due. If the Consultant amends the application, the Consultant will promptly advise the Contractor in writing giving reasons for the amendment,.3 the Owner shall make payment to the Contractor on account as provided in Article A-5 of the Agreement - PAYMENT on or before 20 calendar days after the later of: - receipt by the Consultant of the application for payment, or - the last day of the monthly payment period for which the application for payment is made. CCDC 2 – 2008 File 007213 15 Note: This contract is protected by copyright. Use of a CCDC 2 document not containing a CCDC 2 copyright seal constitutes an infringement of copyright. Only sign this contract if the document cover page bears a CCDC 2 copyright seal to demonstrate that it is intended by the parties to be an accurate and unamended version of CCDC 2 – 2008 except to the extent that any alterations, additions or modifications are set forth in supplementary conditions. GC 5.4 SUBSTANTIAL PERFORMANCE OF THE WORK 5.4.1 When the Contractor considers that the Work is substantially performed, or if permitted by the lien legislation applicable to the Place of the Work a designated portion thereof which the Owner agrees to accept separately is substantially performed, the Contractor shall, within one Working Day, deliver to the Consultant and to the Owner a comprehensive list of items to be completed or corrected, together with a written application for a review by the Consultant to establish Substantial Performance of the Work or substantial performance of the designated portion of the Work. Failure to include an item on the list does not alter the responsibility of the Contractor to complete the Contract. 5.4.2 The Consultant will review the Work to verify the validity of the application and shall promptly, and in any event, no later than 20 calendar days after receipt of the Contractor's list and application:.1 advise the Contractor in writing that the Work or the designated portion of the Work is not substantially performed and give reasons why, or.2 state the date of Substantial Performance of the Work or a designated portion of the Work in a certificate and issue a copy of that certificate to each of the Owner and the Contractor. 5.4.3 Immediately following the issuance of the certificate of Substantial Performance of the Work, the Contractor, in consultation with the Consultant, shall establish a reasonable date for finishing the Work. GC 5.5 PAYMENT OF HOLDBACK UPON SUBSTANTIAL PERFORMANCE OF THE WORK 5.5.1 After the issuance of the certificate of Substantial Performance of the Work, the Contractor shall:.1 submit an application for payment of the holdback amount,.2 submit CCDC 9A ‘Statutory Declaration’ to state that all accounts for labour, subcontracts, Products, Construction Equipment, and other indebtedness which may have been incurred by the Contractor in the Substantial Performance of the Work and for which the Owner might in any way be held responsible have been paid in full, except for amounts properly retained as a holdback or as an identified amount in dispute. 5.5.2 After the receipt of an application for payment from the Contractor and the statement as provided in paragraph 5.5.1, the Consultant will issue a certificate for payment of the holdback amount. 5.5.3 Where the holdback amount required by the applicable lien legislation has not been placed in a separate holdback account, the Owner shall, 10 calendar days prior to the expiry of the holdback period stipulated in the lien legislation applicable to the Place of the Work, place the holdback amount in a bank account in the joint names of the Owner and the Contractor. 5.5.4 In the common law jurisdictions, the holdback amount authorized by the certificate for payment of the holdback amount is due and payable on the first calendar day following the expiration of the holdback period stipulated in the lien legislation applicable to the Place of the Work. Where lien legislation does not exist or apply, the holdback amount shall be due and payable in accordance with other legislation, industry practice or provisions which may be agreed to between the parties. The Owner may retain out of the holdback amount any sums required by law to satisfy any liens against the Work or, if permitted by the lien legislation applicable to the Place of the Work, other third party monetary claims against the Contractor which are enforceable against the Owner. 5.5.5 In the Province of Quebec, the holdback amount authorized by the certificate for payment of the holdback amount is due and payable 30 calendar days after the issuance of the certificate. The Owner may retain out of the holdback amount any sums required to satisfy any legal hypothecs that have been taken, or could be taken, against the Work or other third party monetary claims against the Contractor which are enforceable against the Owner. GC 5.6 PROGRESSIVE RELEASE OF HOLDBACK 5.6.1 In the common law jurisdictions, where legislation permits and where, upon application by the Contractor, the Consultant has certified that the work of a Subcontractor or Supplier has been performed prior to Substantial Performance of the Work, the Owner shall pay the Contractor the holdback amount retained for such subcontract work, or the Products supplied by such Supplier, on the first calendar day following the expiration of the holdback period for such work stipulated in the lien legislation applicable to the Place of the Work. The Owner may retain out of the holdback amount any sums required by law to satisfy any liens against the Work or, if permitted by the lien legislation applicable to the Place of the Work, other third party monetary claims against the Contractor which are enforceable against the Owner. CCDC 2 – 2008 File 007213 16 Note: This contract is protected by copyright. Use of a CCDC 2 document not containing a CCDC 2 copyright seal constitutes an infringement of copyright. Only sign this contract if the document cover page bears a CCDC 2 copyright seal to demonstrate that it is intended by the parties to be an accurate and unamended version of CCDC 2 – 2008 except to the extent that any alterations, additions or modifications are set forth in supplementary conditions. 5.6.2 In the Province of Quebec, where, upon application by the Contractor, the Consultant has certified that the work of a Subcontractor or Supplier has been performed prior to Substantial Performance of the Work, the Owner shall pay the Contractor the holdback amount retained for such subcontract work, or the Products supplied by such Supplier, no later than 30 calendar days after such certification by the Consultant. The Owner may retain out of the holdback amount any sums required to satisfy any legal hypothecs that have been taken, or could be taken, against the Work or other third party monetary claims against the Contractor which are enforceable against the Owner. 5.6.3 Notwithstanding the provisions of the preceding paragraphs, and notwithstanding the wording of such certificates, the Contractor shall ensure that such subcontract work or Products are protected pending the issuance of a final certificate for payment and be responsible for the correction of defects or work not performed regardless of whether or not such was apparent when such certificates were issued. GC 5.7 FINAL PAYMENT 5.7.1 When the Contractor considers that the Work is completed, the Contractor shall submit an application for final payment. 5.7.2 The Consultant will, no later than 10 calendar days after the receipt of an application from the Contractor for final payment, review the Work to verify the validity of the application and advise the Contractor in writing that the application is valid or give reasons why it is not valid. 5.7.3 When the Consultant finds the Contractor's application for final payment valid, the Consultant will promptly issue a final certificate for payment. 5.7.4 Subject to the provision of paragraph 10.4.1 of GC 10.4 - WORKERS' COMPENSATION, and any lien legislation applicable to the Place of the Work, the Owner shall, no later than 5 calendar days after the issuance of a final certificate for payment, pay the Contractor as provided in Article A-5 of the Agreement - PAYMENT. GC 5.8 WITHHOLDING OF PAYMENT 5.8.1 If because of climatic or other conditions reasonably beyond the control of the Contractor, there are items of work that cannot be performed, payment in full for that portion of the Work which has been performed as certified by the Consultant shall not be withheld or delayed by the Owner on account thereof, but the Owner may withhold, until the remaining portion of the Work is finished, only such an amount that the Consultant determines is sufficient and reasonable to cover the cost of performing such remaining work. GC 5.9 NON-CONFORMING WORK 5.9.1 No payment by the Owner under the Contract nor partial or entire use or occupancy of the Work by the Owner shall constitute an acceptance of any portion of the Work or Products which are not in accordance with the requirements of the Contract Documents. PART 6 CHANGES IN THE WORK GC 6.1 OWNER’S RIGHT TO MAKE CHANGES 6.1.1 The Owner, through the Consultant, without invalidating the Contract, may make:.1 changes in the Work consisting of additions, deletions or other revisions to the Work by Change Order or Change Directive, and.2 changes to the Contract Time for the Work, or any part thereof, by Change Order. 6.1.2 The Contractor shall not perform a change in the Work without a Change Order or a Change Directive. GC 6.2 CHANGE ORDER 6.2.1 When a change in the Work is proposed or required, the Consultant will provide the Contractor with a written description of the proposed change in the Work. The Contractor shall promptly present, in a form acceptable to the Consultant, a method of adjustment or an amount of adjustment for the Contract Price, if any, and the adjustment in the Contract Time, if any, for the proposed change in the Work. 6.2.2 When the Owner and Contractor agree to the adjustments in the Contract Price and Contract Time or to the method to be used to determine the adjustments, such agreement shall be effective immediately and shall be recorded in a Change Order. The value of the work performed as the result of a Change Order shall be included in the application for progress payment. CCDC 2 – 2008 File 007213 17 Note: This contract is protected by copyright. Use of a CCDC 2 document not containing a CCDC 2 copyright seal constitutes an infringement of copyright. Only sign this contract if the document cover page bears a CCDC 2 copyright seal to demonstrate that it is intended by the parties to be an accurate and unamended version of CCDC 2 – 2008 except to the extent that any alterations, additions or modifications are set forth in supplementary conditions. GC 6.3 CHANGE DIRECTIVE 6.3.1 If the Owner requires the Contractor to proceed with a change in the Work prior to the Owner and the Contractor agreeing upon the corresponding adjustment in Contract Price and Contract Time, the Owner, through the Consultant, shall issue a Change Directive. 6.3.2 A Change Directive shall only be used to direct a change in the Work which is within the general scope of the Contract Documents. 6.3.3 A Change Directive shall not be used to direct a change in the Contract Time only. 6.3.4 Upon receipt of a Change Directive, the Contractor shall proceed promptly with the change in the Work. 6.3.5 For the purpose of valuing Change Directives, changes in the Work that are not substitutions or otherwise related to each other shall not be grouped together in the same Change Directive. 6.3.6 The adjustment in the Contract Price for a change carried out by way of a Change Directive shall be determined on the basis of the cost of the Contractor’s actual expenditures and savings attributable to the Change Directive, valued in accordance with paragraph 6.3.7 and as follows:.1 If the change results in a net increase in the Contractor’s cost, the Contract Price shall be increased by the amount of the net increase in the Contractor’s cost, plus the Contractor’s percentage fee on such net increase..2 If the change results in a net decrease in the Contractor’s cost, the Contract Price shall be decreased by the amount of the net decrease in the Contractor’s cost, without adjustment for the Contractor’s percentage fee..3 The Contractor’s fee shall be as specified in the Contract Documents or as otherwise agreed by the parties. 6.3.7 The cost of performing the work attributable to the Change Directive shall be limited to the actual cost of the following:.1 salaries, wages and benefits paid to personnel in the direct employ of the Contractor under a salary or wage schedule agreed upon by the Owner and the Contractor, or in the absence of such a schedule, actual salaries, wages and benefits paid under applicable bargaining agreement, and in the absence of a salary or wage schedule and bargaining agreement, actual salaries, wages and benefits paid by the Contractor, for personnel (1) stationed at the Contractor’s field office, in whatever capacity employed; (2) engaged in expediting the production or transportation of material or equipment, at shops or on the road; (3) engaged in the preparation or review of Shop Drawings, fabrication drawings, and coordination drawings; or (4) engaged in the processing of changes in the Work..2 contributions, assessments or taxes incurred for such items as employment insurance, provincial or territorial health insurance, workers' compensation, and Canada or Quebec Pension Plan, insofar as such cost is based on wages, salaries or other remuneration paid to employees of the Contractor and included in the cost of the Work as provided in paragraph 6.3.7.1;.3 travel and subsistence expenses of the Contractor's personnel described in paragraph 6.3.7.1;.4 all Products including cost of transportation thereof;.5 materials, supplies, Construction Equipment, Temporary Work, and hand tools not owned by the workers, including transportation and maintenance thereof, which are consumed in the performance of the Work; and cost less salvage value on such items used but not consumed, which remain the property of the Contractor;.6 all tools and Construction Equipment, exclusive of hand tools used in the performance of the Work, whether rented from or provided by the Contractor or others, including installation, minor repairs and replacements, dismantling, removal, transportation, and delivery cost thereof;.7 all equipment and services required for the Contractor’s field office;.8 deposits lost;.9 the amounts of all subcontracts;.10 quality assurance such as independent inspection and testing services;.11 charges levied by authorities having jurisdiction at the Place of the Work;.12 royalties, patent licence fees and damages for infringement of patents and cost of defending suits therefor subject always to the Contractor's obligations to indemnify the Owner as provided in paragraph 10.3.1 of GC 10.3 - PATENT FEES;.13 any adjustment in premiums for all bonds and insurance which the Contractor is required, by the Contract Documents, to purchase and maintain;.14 any adjustment in taxes, other than Value Added Taxes, and duties for which the Contractor is liable;.15 charges for long distance telephone and facsimile communications, courier services, expressage, and petty cash items incurred in relation to the performance of the Work;.16 removal and disposal of waste products and debris; and.17 safety measures and requirements. CCDC 2 – 2008 File 007213 18 Note: This contract is protected by copyright. Use of a CCDC 2 document not containing a CCDC 2 copyright seal constitutes an infringement of copyright. Only sign this contract if the document cover page bears a CCDC 2 copyright seal to demonstrate that it is intended by the parties to be an accurate and unamended version of CCDC 2 – 2008 except to the extent that any alterations, additions or modifications are set forth in supplementary conditions. 6.3.8 Notwithstanding any other provisions contained in the General Conditions of the Contract, it is the intention of the parties that the cost of any item under any cost element referred to in paragraph 6.3.7 shall cover and include any and all costs or liabilities attributable to the Change Directive other than those which are the result of or occasioned by any failure on the part of the Contractor to exercise reasonable care and diligence in the Contractor’s attention to the Work. Any cost due to failure on the part of the Contractor to exercise reasonable care and diligence in the Contractor’s attention to the Work shall be borne by the Contractor. 6.3.9 The Contractor shall keep full and detailed accounts and records necessary for the documentation of the cost of performing the Work attributable to the Change Directive and shall provide the Consultant with copies thereof when requested. 6.3.10 For the purpose of valuing Change Directives, the Owner shall be afforded reasonable access to all of the Contractor’s pertinent documents related to the cost of performing the Work attributable to the Change Directive. 6.3.11 Pending determination of the final amount of a Change Directive, the undisputed value of the Work performed as the result of a Change Directive is eligible to be included in progress payments. 6.3.12 If the Owner and the Contractor do not agree on the proposed adjustment in the Contract Time attributable to the change in the Work, or the method of determining it, the adjustment shall be referred to the Consultant for determination. 6.3.13 When the Owner and the Contractor reach agreement on the adjustment to the Contract Price and to the Contract Time, this agreement shall be recorded in a Change Order. GC 6.4 CONCEALED OR UNKNOWN CONDITIONS 6.4.1 If the Owner or the Contractor discover conditions at the Place of the Work which are:.1 subsurface or otherwise concealed physical conditions which existed before the commencement of the Work which differ materially from those indicated in the Contract Documents; or.2 physical conditions, other than conditions due to weather, that are of a nature which differ materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the Contract Documents, then the observing party shall give Notice in Writing to the other party of such conditions before they are disturbed and in no event later than 5 Working Days after first observance of the conditions. 6.4.2 The Consultant will promptly investigate such conditions and make a finding. If the finding is that the conditions differ materially and this would cause an increase or decrease in the Contractor's cost or time to perform the Work, the Consultant, with the Owner's approval, will issue appropriate instructions for a change in the Work as provided in GC 6.2 - CHANGE ORDER or GC 6.3 - CHANGE DIRECTIVE. 6.4.3 If the Consultant finds that the conditions at the Place of the Work are not materially different or that no change in the Contract Price or the Contract Time is justified, the Consultant will report the reasons for this finding to the Owner and the Contractor in writing. 6.4.4 If such concealed or unknown conditions relate to toxic and hazardous substances and materials, artifacts and fossils, or mould, the parties will be governed by the provisions of GC 9.2 - TOXIC AND HAZARDOUS SUBSTANCES, GC 9.3 - ARTIFACTS AND FOSSILS and GC 9.5 – MOULD. GC 6.5 DELAYS 6.5.1 If the Contractor is delayed in the performance of the Work by an action or omission of the Owner, Consultant or anyone employed or engaged by them directly or indirectly, contrary to the provisions of the Contract Documents, then the Contract Time shall be extended for such reasonable time as the Consultant may recommend in consultation with the Contractor. The Contractor shall be reimbursed by the Owner for reasonable costs incurred by the Contractor as the result of such delay. 6.5.2 If the Contractor is delayed in the performance of the Work by a stop work order issued by a court or other public authority and providing that such order was not issued as the result of an act or fault of the Contractor or any person employed or engaged by the Contractor directly or indirectly, then the Contract Time shall be extended for such reasonable time as the Consultant may recommend in consultation with the Contractor. The Contractor shall be reimbursed by the Owner for reasonable costs incurred by the Contractor as the result of such delay. CCDC 2 – 2008 File 007213 19 Note: This contract is protected by copyright. Use of a CCDC 2 document not containing a CCDC 2 copyright seal constitutes an infringement of copyright. Only sign this contract if the document cover page bears a CCDC 2 copyright seal to demonstrate that it is intended by the parties to be an accurate and unamended version of CCDC 2 – 2008 except to the extent that any alterations, additions or modifications are set forth in supplementary conditions. 6.5.3 If the Contractor is delayed in the performance of the Work by:.1 labour disputes, strikes, lock-outs (including lock-outs decreed or recommended for its members by a recognized contractors' association, of which the Contractor is a member or to which the Contractor is otherwise bound),.2 fire, unusual delay by common carriers or unavoidable casualties,.3 abnormally adverse weather conditions, or.4 any cause beyond the Contractor's control other than one resulting from a default or breach of Contract by the Contractor, then the Contract Time shall be extended for such reasonable time as the Consultant may recommend in consultation with the Contractor. The extension of time shall not be less than the time lost as the result of the event causing the delay, unless the Contractor agrees to a shorter extension. The Contractor shall not be entitled to payment for costs incurred by such delays unless such delays result from actions by the Owner, Consultant or anyone employed or engaged by them directly or indirectly. 6.5.4 No extension shall be made for delay unless Notice in Writing of the cause of delay is given to the Consultant not later than 10 Working Days after the commencement of the delay. In the case of a continuing cause of delay only one Notice in Writing shall be necessary. 6.5.5 If no schedule is made under paragraph 2.2.13 of GC 2.2 - ROLE OF THE CONSULTANT, then no request for extension shall be made because of failure of the Consultant to furnish instructions until 10 Working Days after demand for such instructions has been made. GC 6.6 CLAIMS FOR A CHANGE IN CONTRACT PRICE 6.6.1 If the Contractor intends to make a claim for an increase to the Contract Price, or if the Owner intends to make a claim against the Contractor for a credit to the Contract Price, the party that intends to make the claim shall give timely Notice in Writing of intent to claim to the other party and to the Consultant. 6.6.2 Upon commencement of the event or series of events giving rise to a claim, the party intending to make the claim shall:.1 take all reasonable measures to mitigate any loss or expense which may be incurred as a result of such event or series of events, and.2 keep such records as may be necessary to support the claim. 6.6.3 The party making the claim shall submit within a reasonable time to the Consultant a detailed account of the amount claimed and the grounds upon which the claim is based. 6.6.4 Where the event or series of events giving rise to the claim has a continuing effect, the detailed account submitted under paragraph 6.6.3 shall be considered to be an interim account and the party making the claim shall, at such intervals as the Consultant may reasonably require, submit further interim accounts giving the accumulated amount of the claim and any further grounds upon which it is based. The party making the claim shall submit a final account after the end of the effects resulting from the event or series of events. 6.6.5 The Consultant’s findings, with respect to a claim made by either party, will be given by Notice in Writing to both parties within 30 Working Days after receipt of the claim by the Consultant, or within such other time period as may be agreed by the parties. 6.6.6 If such finding is not acceptable to either party, the claim shall be settled in accordance with Part 8 of the General Conditions - DISPUTE RESOLUTION. PART 7 DEFAULT NOTICE GC 7.1 OWNER'S RIGHT TO PERFORM THE WORK, TERMINATE THE CONTRACTOR’S RIGHT TO CONTINUE WITH THE WORK OR TERMINATE THE CONTRACT 7.1.1 If the Contractor is adjudged bankrupt, or makes a general assignment for the benefit of creditors because of the Contractor's insolvency, or if a receiver is appointed because of the Contractor's insolvency, the Owner may, without prejudice to any other right or remedy the Owner may have, terminate the Contractor’s right to continue with the Work, by giving the Contractor or receiver or trustee in bankruptcy Notice in Writing to that effect. 7.1.2 If the Contractor neglects to prosecute the Work properly or otherwise fails to comply with the requirements of the Contract to a substantial degree and if the Consultant has given a written statement to the Owner and Contractor that sufficient cause exists to justify such action, the Owner may, without prejudice to any other right or remedy the Owner may have, give the Contractor Notice in Writing that the Contractor is in default of the Contractor's contractual obligations and instruct the Contractor to correct the default in the 5 Working Days immediately following the receipt of such Notice in Writing. CCDC 2 – 2008 File 007213 20 Note: This contract is protected by copyright. Use of a CCDC 2 document not containing a CCDC 2 copyright seal constitutes an infringement of copyright. Only sign this contract if the document cover page bears a CCDC 2 copyright seal to demonstrate that it is intended by the parties to be an accurate and unamended version of CCDC 2 – 2008 except to the extent that any alterations, additions or modifications are set forth in supplementary conditions. 7.1.3 If the default cannot be corrected in the 5 Working Days specified or in such other time period as may be subsequently agreed in writing by the parties, the Contractor shall be in compliance with the Owner's instructions if the Contractor:.1 commences the correction of the default within the specified time, and.2 provides the Owner with an acceptable schedule for such correction, and.3 corrects the default in accordance with the Contract terms and with such schedule. 7.1.4 If the Contractor fails to correct the default in the time specified or in such other time period as may be subsequently agreed in writing by the parties, without prejudice to any other right or remedy the Owner may have, the Owner may:.1 correct such default and deduct the cost thereof from any payment then or thereafter due the Contractor provided the Consultant has certified such cost to the Owner and the Contractor, or.2 terminate the Contractor's right to continue with the Work in whole or in part or terminate the Contract. 7.1.5 If the Owner terminates the Contractor's right to continue with the Work as provided in paragraphs 7.1.1 and 7.1.4, the Owner shall be entitled to:.1 take possession of the Work and Products at the Place of the Work; subject to the rights of third parties, utilize the Construction Equipment at the Place of the Work; finish the Work by whatever method the Owner may consider expedient, but without undue delay or expense, and.2 withhold further payment to the Contractor until a final certificate for payment is issued, and.3 charge the Contractor the amount by which the full cost of finishing the Work as certified by the Consultant, including compensation to the Consultant for the Consultant's additional services and a reasonable allowance as determined by the Consultant to cover the cost of corrections to work performed by the Contractor that may be required under GC 12.3 - WARRANTY, exceeds the unpaid balance of the Contract Price; however, if such cost of finishing the Work is less than the unpaid balance of the Contract Price, the Owner shall pay the Contractor the difference, and.4 on expiry of the warranty period, charge the Contractor the amount by which the cost of corrections to the Contractor's work under GC 12.3 - WARRANTY exceeds the allowance provided for such corrections, or if the cost of such corrections is less than the allowance, pay the Contractor the difference. 7.1.6 The Contractor's obligation under the Contract as to quality, correction and warranty of the work performed by the Contractor up to the time of termination shall continue after such termination of the Contract. GC 7.2 CONTRACTOR'S RIGHT TO SUSPEND THE WORK OR TERMINATE THE CONTRACT 7.2.1 If the Owner is adjudged bankrupt, or makes a general assignment for the benefit of creditors because of the Owner's insolvency, or if a receiver is appointed because of the Owner's insolvency, the Contractor may, without prejudice to any other right or remedy the Contractor may have, terminate the Contract by giving the Owner or receiver or trustee in bankruptcy Notice in Writing to that effect. 7.2.2 If the Work is suspended or otherwise delayed for a period of 20 Working Days or more under an order of a court or other public authority and providing that such order was not issued as the result of an act or fault of the Contractor or of anyone directly or indirectly employed or engaged by the Contractor, the Contractor may, without prejudice to any other right or remedy the Contractor may have, terminate the Contract by giving the Owner Notice in Writing to that effect. 7.2.3 The Contractor may give Notice in Writing to the Owner, with a copy to the Consultant, that the Owner is in default of the Owner's contractual obligations if:.1 the Owner fails to furnish, when so requested by the Contractor, reasonable evidence that financial arrangements have been made to fulfill the Owner's obligations under the Contract, or.2 the Consultant fails to issue a certificate as provided in GC 5.3 - PROGRESS PAYMENT, or.3 the Owner fails to pay the Contractor when due the amounts certified by the Consultant or awarded by arbitration or court, or.4 the Owner violates the requirements of the Contract to a substantial degree and the Consultant, except for GC 5.1 - FINANCING INFORMATION REQUIRED OF THE OWNER, confirms by written statement to the Contractor that sufficient cause exists. 7.2.4 The Contractor's Notice in Writing to the Owner provided under paragraph 7.2.3 shall advise that if the default is not corrected within 5 Working Days following the receipt of the Notice in Writing, the Contractor may, without prejudice to any other right or remedy the Contractor may have, suspend the Work or terminate the Contract. 7.2.5 If the Contractor terminates the Contract under the conditions set out above, the Contractor shall be entitled to be paid for all work performed including reasonable profit, for loss sustained upon Products and Construction Equipment, and such other damages as the Contractor may have sustained as a result of the termination of the Contract. CCDC 2 – 2008 File 007213 21 Note: This contract is protected by copyright. Use of a CCDC 2 document not containing a CCDC 2 copyright seal constitutes an infringement of copyright. Only sign this contract if the document cover page bears a CCDC 2 copyright seal to demonstrate that it is intended by the parties to be an accurate and unamended version of CCDC 2 – 2008 except to the extent that any alterations, additions or modifications are set forth in supplementary conditions. PART 8 DISPUTE RESOLUTION GC 8.1 AUTHORITY OF THE CONSULTANT 8.1.1 Differences between the parties to the Contract as to the interpretation, application or administration of the Contract or any failure to agree where agreement between the parties is called for, herein collectively called disputes, which are not resolved in the first instance by findings of the Consultant as provided in GC 2.2 - ROLE OF THE CONSULTANT, shall be settled in accordance with the requirements of Part 8 of the General Conditions - DISPUTE RESOLUTION. 8.1.2 If a dispute arises under the Contract in respect of a matter in which the Consultant has no authority under the Contract to make a finding, the procedures set out in paragraph 8.1.3 and paragraphs 8.2.3 to 8.2.8 of GC 8.2 - NEGOTIATION, MEDIATION AND ARBITRATION, and in GC 8.3 - RETENTION OF RIGHTS apply to that dispute with the necessary changes to detail as may be required. 8.1.3 If a dispute is not resolved promptly, the Consultant will give such instructions as in the Consultant's opinion are necessary for the proper performance of the Work and to prevent delays pending settlement of the dispute. The parties shall act immediately according to such instructions, it being understood that by so doing neither party will jeopardize any claim the party may have. If it is subsequently determined that such instructions were in error or at variance with the Contract Documents, the Owner shall pay the Contractor costs incurred by the Contractor in carrying out such instructions which the Contractor was required to do beyond what the Contract Documents correctly understood and interpreted would have required, including costs resulting from interruption of the Work. GC 8.2 NEGOTIATION, MEDIATION AND ARBITRATION 8.2.1 In accordance with the Rules for Mediation of Construction Disputes as provided in CCDC 40 in effect at the time of bid closing, the parties shall appoint a Project Mediator.1 within 20 Working Days after the Contract was awarded, or.2 if the parties neglected to make an appointment within the 20 Working Days, within 10 Working Days after either party by Notice in Writing requests that the Project Mediator be appointed. 8.2.2 A party shall be conclusively deemed to have accepted a finding of the Consultant under GC 2.2 - ROLE OF THE CONSULTANT and to have expressly waived and released the other party from any claims in respect of the particular matter dealt with in that finding unless, within 15 Working Days after receipt of that finding, the party sends a Notice in Writing of dispute to the other party and to the Consultant, which contains the particulars of the matter in dispute and the relevant provisions of the Contract Documents. The responding party shall send a Notice in Writing of reply to the dispute within 10 Working Days after receipt of such Notice in Writing setting out particulars of this response and any relevant provisions of the Contract Documents. 8.2.3 The parties shall make all reasonable efforts to resolve their dispute by amicable negotiations and agree to provide, without prejudice, frank, candid and timely disclosure of relevant facts, information and documents to facilitate these negotiations. 8.2.4 After a period of 10 Working Days following receipt of a responding party's Notice in Writing of reply under paragraph 8.2.2, the parties shall request the Project Mediator to assist the parties to reach agreement on any unresolved dispute. The mediated negotiations shall be conducted in accordance with the Rules for Mediation of Construction Disputes as provided in CCDC 40 in effect at the time of bid closing. 8.2.5 If the dispute has not been resolved within 10 Working Days after the Project Mediator was requested under paragraph 8.2.4 or within such further period agreed by the parties, the Project Mediator shall terminate the mediated negotiations by giving Notice in Writing to the Owner, the Contractor and the Consultant. 8.2.6 By giving a Notice in Writing to the other party and the Consultant, not later than 10 Working Days after the date of termination of the mediated negotiations under paragraph 8.2.5, either party may refer the dispute to be finally resolved by arbitration under the Rules for Arbitration of Construction Disputes as provided in CCDC 40 in effect at the time of bid closing. The arbitration shall be conducted in the jurisdiction of the Place of the Work. 8.2.7 On expiration of the 10 Working Days, the arbitration agreement under paragraph 8.2.6 is not binding on the parties and, if a Notice in Writing is not given under paragraph 8.2.6 within the required time, the parties may refer the unresolved dispute to the courts or to any other form of dispute resolution, including arbitration, which they have agreed to use. CCDC 2 – 2008 File 007213 22 Note: This contract is protected by copyright. Use of a CCDC 2 document not containing a CCDC 2 copyright seal constitutes an infringement of copyright. Only sign this contract if the document cover page bears a CCDC 2 copyright seal to demonstrate that it is intended by the parties to be an accurate and unamended version of CCDC 2 – 2008 except to the extent that any alterations, additions or modifications are set forth in supplementary conditions. 8.2.8 If neither party, by Notice in Writing, given within 10 Working Days of the date of Notice in Writing requesting arbitration in paragraph 8.2.6, requires that a dispute be arbitrated immediately, all disputes referred to arbitration as provided in paragraph 8.2.6 shall be.1 held in abeyance until (1) Substantial Performance of the Work, (2) the Contract has been terminated, or (3) the Contractor has abandoned the Work, whichever is earlier; and.2 consolidated into a single arbitration under the rules governing the arbitration under paragraph 8.2.6. GC 8.3 RETENTION OF RIGHTS 8.3.1 It is agreed that no act by either party shall be construed as a renunciation or waiver of any rights or recourses, provided the party has given the Notice in Writing required under Part 8 of the General Conditions - DISPUTE RESOLUTION and has carried out the instructions as provided in paragraph 8.1.3 of GC 8.1 – AUTHORITY OF THE CONSULTANT. 8.3.2 Nothing in Part 8 of the General Conditions - DISPUTE RESOLUTION shall be construed in any way to limit a party from asserting any statutory right to a lien under applicable lien legislation of the jurisdiction of the Place of the Work and the assertion of such right by initiating judicial proceedings is not to be construed as a waiver of any right that party may have under paragraph 8.2.6 of GC 8.2 – NEGOTIATION, MEDIATION AND ARBITRATION to proceed by way of arbitration to adjudicate the merits of the claim upon which such a lien is based. PART 9 PROTECTION OF PERSONS AND PROPERTY GC 9.1 PROTECTION OF WORK AND PROPERTY 9.1.1 The Contractor shall protect the Work and the Owner's property and property adjacent to the Place of the Work from damage which may arise as the result of the Contractor's operations under the Contract, and shall be responsible for such damage, except damage which occurs as the result of:.1 errors in the Contract Documents;.2 acts or omissions by the Owner, the Consultant, other contractors, their agents and employees. 9.1.2 Before commencing any work, the Contractor shall determine the location of all underground utilities and structures indicated in the Contract Documents or that are reasonably apparent in an inspection of the Place of the Work. 9.1.3 Should the Contractor in the performance of the Contract damage the Work, the Owner's property or property adjacent to the Place of the Work, the Contractor shall be responsible for making good such damage at the Contractor's expense. 9.1.4 Should damage occur to the Work or Owner's property for which the Contractor is not responsible, as provided in paragraph 9.1.1, the Contractor shall make good such damage to the Work and, if the Owner so directs, to the Owner's property. The Contract Price and Contract Time shall be adjusted as provided in GC 6.1 – OWNER’S RIGHT TO MAKE CHANGES, GC 6.2 - CHANGE ORDER and GC 6.3 - CHANGE DIRECTIVE. GC 9.2 TOXIC AND HAZARDOUS SUBSTANCES 9.2.1 For the purposes of applicable legislation related to toxic and hazardous substances, the Owner shall be deemed to have control and management of the Place of the Work with respect to existing conditions. 9.2.2 Prior to the Contractor commencing the Work, the Owner shall,.1 take all reasonable steps to determine whether any toxic or hazardous substances are present at the Place of the Work, and.2 provide the Consultant and the Contractor with a written list of any such substances that are known to exist and their locations. 9.2.3 The Owner shall take

Use Quizgecko on...
Browser
Browser