Which statement about the Design-Bid-Build contract structure is true? A) The project owner retains full responsibility for project delays. B) The contractor must adhere to predefi... Which statement about the Design-Bid-Build contract structure is true? A) The project owner retains full responsibility for project delays. B) The contractor must adhere to predefined scope from the beginning. C) The contractor assumes all financial risks for project overruns. D) The contractor has little understanding of project scope prior to bidding.

Understand the Problem

The question is asking which statement among the provided options accurately describes the Design-Bid-Build contract structure, a common method used in project management and construction.

Answer

The contractor must adhere to predefined scope from the beginning.

The contractor must adhere to predefined scope from the beginning.

Answer for screen readers

The contractor must adhere to predefined scope from the beginning.

More Information

In the Design-Bid-Build contract structure, the contractor is provided with detailed designs and specifications at the outset. The contractor is expected to adhere to the predefined scope as per the contract.

Tips

A common mistake is assuming the contractor has flexibility in the scope similar to Design-Build methods, which they do not in this contract form.

AI-generated content may contain errors. Please verify critical information

Thank you for voting!