Which of the following would be considered a unique risk factor in the requirements prioritization process? A) Stakeholder availability B) Changes in project scope C) Conflicting r... Which of the following would be considered a unique risk factor in the requirements prioritization process? A) Stakeholder availability B) Changes in project scope C) Conflicting requirements D) Time constraints
Understand the Problem
The question is asking for identification of a unique risk factor specifically in the context of requirements prioritization within a project management scenario. This involves analyzing the options provided to determine which one stands out as distinct compared to the others.
Answer
Conflicting requirements.
Conflicting requirements would be considered a unique risk factor in the requirements prioritization process.
Answer for screen readers
Conflicting requirements would be considered a unique risk factor in the requirements prioritization process.
More Information
In the requirements prioritization process, conflicting requirements are unique risks because they can lead to delays, scope changes, and dissatisfaction among stakeholders if not properly addressed.
Tips
Confusing constraints with risk factors. Constraints are limitations that can lead to risks when they impact project goals.