The Milestone Decision Authority (MDA) approves each phase of the program, and is accountable for cost, schedule and performance reporting. True or False?

Question image

Understand the Problem

The question is asking whether the statement about the Milestone Decision Authority (MDA) approving each phase of a program and being accountable for cost, schedule, and performance reporting is true or false. This type of question requires understanding the role of the MDA in project management.

Answer

False

The statement is False. The Milestone Decision Authority (MDA) is responsible for approving each phase of a program, but accountability for cost, schedule, and performance reporting lies with the Program Manager (PM) and the Acquisition Program Baseline (APB).

Answer for screen readers

The statement is False. The Milestone Decision Authority (MDA) is responsible for approving each phase of a program, but accountability for cost, schedule, and performance reporting lies with the Program Manager (PM) and the Acquisition Program Baseline (APB).

More Information

The Milestone Decision Authority (MDA) focuses on program approval, while the Program Manager (PM) and the Acquisition Program Baseline (APB) handle reporting responsibilities.

Tips

Common mistake: Assuming MDA is responsible for all aspects of program management. Clarify the distinction between approval and reporting duties.