Questions and Answers

All masonry work must cease when the temperature drops below ____________________°F.

30

Substitutes are not acceptable for the hood fire suppression system specified.

True (A)

A ___ is the formal, legal process authorizing any changes in location, layout, size, construction methods, or materials.

change order

Toilet and urinal partitions are manufactured by American Standard.

<p>False (B)</p> Signup and view all the answers

A minimum temperature of ___°F should be maintained during tile work and for seven days thereafter.

<p>50</p> Signup and view all the answers

Per ADA requirements, the clear and level landing area at each accessible entrance is ____________________' square.

<p>5</p> Signup and view all the answers

All ____________________ for footings must be unpainted and uncoated.

<p>reinforcing</p> Signup and view all the answers

The contractor shall provide certificates of insurance for Workers' Compensation and automobile liability coverage.

<p>False (B)</p> Signup and view all the answers

Information regarding plumbing, heating, and ventilation is included in ___.

<p>Division 15-Mechanical</p> Signup and view all the answers

Portable fire extinguishers are sized by the local fire control authority.

<p>True (A)</p> Signup and view all the answers

Information regarding insulation, flashing, and roofing is included in ___.

<p>Division 7-Thermal and Moisture Protection</p> Signup and view all the answers

The pick-up window unit has a ___ active light.

<p>24&quot; × 34&quot;</p> Signup and view all the answers

The owner can stop construction work at any time for testing and special inspections.

<p>True (A)</p> Signup and view all the answers

____________________ excavations must be on undisturbed earth.

<p>Footing</p> Signup and view all the answers

A minimum indoor temperature of ____________________°F must be maintained during painting.

<p>65</p> Signup and view all the answers

Flashing should be lapped a minimum of ___".

<p>6</p> Signup and view all the answers

Based on the Americans with Disabilities Act (ADA) New Construction Checklist, ____________________ accessible parking spaces are required if the parking lot contains 140 parking spaces.

<p>five</p> Signup and view all the answers

The contractor is responsible in the event of loss or damage to adjacent property during construction.

<p>True (A)</p> Signup and view all the answers

____________________ drawings are required for ordering, manufacturing, and final inspection of the roofing system.

<p>Shop</p> Signup and view all the answers

Information regarding floor tile and wall covering is included in ___.

<p>Division 9-Finishes</p> Signup and view all the answers

___ handicap-accessible parking spaces are required when 85 parking spaces are specified for the parking lot.

<p>Four</p> Signup and view all the answers

A formal list of construction deficiencies is referred to as a(n) ____________________ list.

<p>punch</p> Signup and view all the answers

The 2014 edition of the MasterFormat contains ___ divisions.

<p>50</p> Signup and view all the answers

Per ADA requirements, the maximum highest operable part of restroom accessories is ____________________".

<p>48</p> Signup and view all the answers

All storm and sanitary sewer work is the responsibility of the general contractor.

<p>True (A)</p> Signup and view all the answers

Flashcards

What is a Change Order?

A formal, legal process authorizing changes in construction.

What is the minimum temperature requirement for tile work?

A minimum of 50 degrees Fahrenheit must be maintained during tile installation and for 7 days after.

What is the required size of the landing area for accessible entrances?

The clear and level area at each accessible entrance must be 5' square.

What is the condition of reinforcing bars for footings?

All reinforcing for footings must be unpainted and uncoated.

Signup and view all the flashcards

Where must footing excavations be located?

Excavations for footings must be on undisturbed earth.

Signup and view all the flashcards

What is the minimum temperature for painting?

A minimum indoor temperature of 65 degrees Fahrenheit must be maintained during painting.

Signup and view all the flashcards

What is the minimum lap for flashing?

Flashing should lap a minimum of 6 inches.

Signup and view all the flashcards

How many accessible parking spaces are needed for a 140-space parking lot?

Five accessible parking spaces are required for a parking lot with 140 spaces.

Signup and view all the flashcards

What is a 'Punch List'?

A formal list of construction deficiencies is called a punch list.

Signup and view all the flashcards

How many divisions are in the 2014 MasterFormat?

The 2014 edition of the MasterFormat contains 50 divisions.

Signup and view all the flashcards

What is the maximum height for restroom accessories?

The maximum height for the highest operable part of restroom accessories should be 48 inches.

Signup and view all the flashcards

When must masonry work be stopped?

All masonry work must stop when the temperature falls below 30 degrees Fahrenheit.

Signup and view all the flashcards

Are substitutes allowed for the hood fire suppression system?

Substitutes are not allowed for the specified hood fire suppression system.

Signup and view all the flashcards

Who manufactures toilet and urinal partitions?

Toilet and urinal partitions are not manufactured by American Standard.

Signup and view all the flashcards

Where can information regarding plumbing, heating, and ventilation be found?

Information regarding plumbing, heating, and ventilation is found in Division 15-Mechanical of the MasterFormat.

Signup and view all the flashcards

Who determines the size of portable fire extinguishers?

Portable fire extinguishers are sized by the local fire control authority.

Signup and view all the flashcards

Where is information regarding insulation, flashing, and roofing found?

Information regarding insulation, flashing, and roofing is found in Division 7-Thermal and Moisture Protection of the MasterFormat.

Signup and view all the flashcards

What is the size of the active light for the pick-up window unit?

The pick-up window unit has a 24-inch by 34-inch active light.

Signup and view all the flashcards

Can the owner stop construction for inspections?

The owner can halt construction for testing and special inspections at any time.

Signup and view all the flashcards

What type of drawings are needed for the roofing system?

Shop drawings are required for ordering, manufacturing, and inspecting the roofing system.

Signup and view all the flashcards

Where is information regarding floor tile and wall covering found?

Information regarding floor tile and wall covering is found in Division 9-Finishes of the MasterFormat.

Signup and view all the flashcards

How many handicap-accessible parking spaces are needed for a parking lot with 85 spaces?

Four handicap-accessible parking spaces are required for a parking lot with 85 spaces.

Signup and view all the flashcards

Who is responsible for damage to surrounding property during construction?

The contractor is responsible for any damage to surrounding property during construction.

Signup and view all the flashcards

Study Notes

Masonry and Construction Conditions

  • Masonry work halts when temperatures fall below 32°F.
  • Minimum indoor temperature during painting must be 65°F.
  • Minimum temperature of 50°F is required during tile work and for seven days afterward.

Fire Protection Systems

  • Substitutes for the specified hood fire suppression system are not permitted.
  • Portable fire extinguishers must conform to local fire control authority sizing.

Change Management and Contractor Responsibilities

  • Change order is a formal process to authorize changes in design or construction.
  • Contractors must provide insurance certificates for Workers’ Compensation and automobile liability.
  • Contractors are liable for any loss or damage to adjacent properties during construction.

Design Specifications and Guidelines

  • Footing excavations should be conducted on undisturbed earth.
  • Insulation and roofing information is found in Division 7 (Thermal and Moisture Protection).
  • Shop drawings are mandatory for roofing system manufacturing and inspection.

Compliance with ADA Requirements

  • Clear landing area for accessible entrances must be at least 5' square per ADA.
  • Five accessible parking spaces are needed for lots with 140 parking spaces, while four are required for lots containing 85 spaces.
  • Highest operable part of restroom accessories must not exceed 48" according to ADA standards.

Miscellaneous Specifications

  • The pick-up window unit features a 24" × 34" active light.
  • Flashing must be lapped a minimum of 6".
  • A punch list details construction deficiencies and is used for final inspections.
  • The 2014 MasterFormat consists of 50 divisions.

Additional Information

  • The contractor may halt construction for necessary testing and special inspections.
  • Division 9 includes information on finishes, such as floor tiles and wall coverings.
  • Division 15 encompasses plumbing, heating, and ventilation specifications.

Studying That Suits You

Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

Quiz Team

Description

Test your knowledge on the specifications required for Wendy's Restaurant construction with these flashcards. This quiz covers essential terms and definitions that are critical for masonry work, fire suppression systems, and change orders. Perfect for anyone involved in restaurant construction projects.