What is the primary purpose of the 'Receiving Process' described in the SOP?
What is the primary purpose of the 'Receiving Process' described in the SOP?
- To verify the accuracy and completeness of received items, including panels and accompanying documents. (correct)
- To inspect panels for defects and damages before they are used in a project.
- To allocate panels to specific jobs or projects based on their part numbers.
- To ensure that all panels are packaged properly and ready for shipment.
What does the acronym 'SOP' stand for in the document?
What does the acronym 'SOP' stand for in the document?
- Supply Order Program
- Safety Operational Process
- Standard Operating Procedure (correct)
- Sequential Operational Procedure
What specific document is referenced in the SOP, and what type of document is it?
What specific document is referenced in the SOP, and what type of document is it?
- CAP02-013, a forklift operations manual (correct)
- CAP02-013, a production schedule
- CAP02-013, a quality control inspection checklist
- CAP02-013, a safety precaution document for panel handling
What is the implication of the statement 'Ensure panels in good condition and used the dedicated regulator.'?
What is the implication of the statement 'Ensure panels in good condition and used the dedicated regulator.'?
What is the meaning of the phrase 'all panel and paperwork are matches'?
What is the meaning of the phrase 'all panel and paperwork are matches'?
Based on the information provided, what is the most likely type of industry this SOP is for?
Based on the information provided, what is the most likely type of industry this SOP is for?
What is the potential consequence of failing to follow the 'Receiving Process'?
What is the potential consequence of failing to follow the 'Receiving Process'?
What is the main purpose of the 'CAUTION/PERHATIAN' section in the SOP?
What is the main purpose of the 'CAUTION/PERHATIAN' section in the SOP?
Which team is responsible for completing "SECTION C" of the Shipment Checklist in the ZOHO system?
Which team is responsible for completing "SECTION C" of the Shipment Checklist in the ZOHO system?
When does the Transport Team complete "SECTION C" of the Shipment Checklist?
When does the Transport Team complete "SECTION C" of the Shipment Checklist?
What is the purpose of the note that states, "Please refer to SOP08-040 (Shipment Checklist Procedure)"?
What is the purpose of the note that states, "Please refer to SOP08-040 (Shipment Checklist Procedure)"?
Which team is responsible for completing "SECTION D" of the Shipment Checklist?
Which team is responsible for completing "SECTION D" of the Shipment Checklist?
What is the final step in the Shipment Checklist process, according to the content?
What is the final step in the Shipment Checklist process, according to the content?
What is the meaning of the abbreviation "CAP02-013" in the content?
What is the meaning of the abbreviation "CAP02-013" in the content?
What is the primary purpose of the Shipment Checklist, as described in the content?
What is the primary purpose of the Shipment Checklist, as described in the content?
What specific instructions are given to the Forwarder in the content related to the Shipment Checklist?
What specific instructions are given to the Forwarder in the content related to the Shipment Checklist?
What is the primary responsibility of the Team Leader in the selection process?
What is the primary responsibility of the Team Leader in the selection process?
Which basis must the Team Leader use when selecting panels for delivery?
Which basis must the Team Leader use when selecting panels for delivery?
What must the Team Leader ensure regarding the delivery of panels?
What must the Team Leader ensure regarding the delivery of panels?
Which of the following is NOT a responsibility of the Team Leader during the selection process?
Which of the following is NOT a responsibility of the Team Leader during the selection process?
What is implied about the sequence of selecting panels in the process described?
What is implied about the sequence of selecting panels in the process described?
What is the first step that an employee must take to begin the packaging process?
What is the first step that an employee must take to begin the packaging process?
Which of the following is NOT included in the visual check of the panel condition?
Which of the following is NOT included in the visual check of the panel condition?
What procedure should be followed for cleaning a normal/standard panel?
What procedure should be followed for cleaning a normal/standard panel?
What is the purpose of an Authorized Operator in the packaging process?
What is the purpose of an Authorized Operator in the packaging process?
Which document is NOT mentioned as necessary for the packaging process?
Which document is NOT mentioned as necessary for the packaging process?
What must be ensured about the panels before proceeding with packaging?
What must be ensured about the panels before proceeding with packaging?
What must an employee do if impurities are visible on a black panel?
What must an employee do if impurities are visible on a black panel?
Which step is NOT mentioned as part of the cleaning process for the bare panels?
Which step is NOT mentioned as part of the cleaning process for the bare panels?
Why is it important to use a QR code in the packaging process?
Why is it important to use a QR code in the packaging process?
Which of the following conditions must a panel be checked for?
Which of the following conditions must a panel be checked for?
What is the purpose of the SOP08-017 document?
What is the purpose of the SOP08-017 document?
Which of the following is true regarding the categorization of the panels?
Which of the following is true regarding the categorization of the panels?
What action should be taken when a document is controlled by the CTRM AC Quality Assurance Department?
What action should be taken when a document is controlled by the CTRM AC Quality Assurance Department?
What is indicated by the term 'Uncontrolled Copy When Printed'?
What is indicated by the term 'Uncontrolled Copy When Printed'?
When organizing panels into boxes, what is the primary factor to consider?
When organizing panels into boxes, what is the primary factor to consider?
Which operational procedure must be referenced for the packaging checklist?
Which operational procedure must be referenced for the packaging checklist?
What does the reference to 'Page 7 of 13' imply about the document structure?
What does the reference to 'Page 7 of 13' imply about the document structure?
What is the significance of referencing figures or diagrams in the SOP?
What is the significance of referencing figures or diagrams in the SOP?
What is the first step in the paperwork process according to the outlined procedure?
What is the first step in the paperwork process according to the outlined procedure?
Where should all paperwork be sent after being organized by SSN?
Where should all paperwork be sent after being organized by SSN?
In the CofC process, what is required of employees after receiving the CofC email?
In the CofC process, what is required of employees after receiving the CofC email?
What is indicated to be done with the CofC in relation to the delivery boxes?
What is indicated to be done with the CofC in relation to the delivery boxes?
What is the outcome if any paperwork is incorrectly organized by SSN?
What is the outcome if any paperwork is incorrectly organized by SSN?
What form of communication is used to send CofC to the employees?
What form of communication is used to send CofC to the employees?
Which of the following is NOT a step mentioned in the CofC process?
Which of the following is NOT a step mentioned in the CofC process?
Which document must be printed and placed in the delivery boxes according to the project package?
Which document must be printed and placed in the delivery boxes according to the project package?
Flashcards
Selecting Process
Selecting Process
The method of choosing items for packaging operations.
Team Leader's Role
Team Leader's Role
The responsibility of overseeing the selection of panels in the process.
FIFO
FIFO
First In First Out; an inventory method where the oldest items are used first.
Panel Selection
Panel Selection
Signup and view all the flashcards
Packaging Process
Packaging Process
Signup and view all the flashcards
Receiving Process
Receiving Process
Signup and view all the flashcards
Panel and Paperwork Matching
Panel and Paperwork Matching
Signup and view all the flashcards
Part Number
Part Number
Signup and view all the flashcards
Staging
Staging
Signup and view all the flashcards
Forklift Operation Procedure
Forklift Operation Procedure
Signup and view all the flashcards
Condition Check
Condition Check
Signup and view all the flashcards
Dedicated Regulator
Dedicated Regulator
Signup and view all the flashcards
Balut and Wrap Method
Balut and Wrap Method
Signup and view all the flashcards
Packaging Project Package
Packaging Project Package
Signup and view all the flashcards
SOP08-017
SOP08-017
Signup and view all the flashcards
Controlled Document
Controlled Document
Signup and view all the flashcards
Slot Panel Positioning
Slot Panel Positioning
Signup and view all the flashcards
Packaging Checklist Procedure
Packaging Checklist Procedure
Signup and view all the flashcards
Quality Assurance Department
Quality Assurance Department
Signup and view all the flashcards
Uncontrolled Copy
Uncontrolled Copy
Signup and view all the flashcards
Packaging Checklist
Packaging Checklist
Signup and view all the flashcards
QR Code
QR Code
Signup and view all the flashcards
Panel Verification
Panel Verification
Signup and view all the flashcards
Visual Panel Check
Visual Panel Check
Signup and view all the flashcards
Panel Cleaning Procedure
Panel Cleaning Procedure
Signup and view all the flashcards
Authorized Operator
Authorized Operator
Signup and view all the flashcards
Panel Condition Checks
Panel Condition Checks
Signup and view all the flashcards
Damp and Dry Cloth Cleaning
Damp and Dry Cloth Cleaning
Signup and view all the flashcards
Cleaning Tools
Cleaning Tools
Signup and view all the flashcards
Documentation Matching
Documentation Matching
Signup and view all the flashcards
Paperwork Collection
Paperwork Collection
Signup and view all the flashcards
Send to DDC
Send to DDC
Signup and view all the flashcards
CofC Process
CofC Process
Signup and view all the flashcards
Print the CofC
Print the CofC
Signup and view all the flashcards
Insert CofC into Boxes
Insert CofC into Boxes
Signup and view all the flashcards
Email from Quality Department
Email from Quality Department
Signup and view all the flashcards
Project Package Delivery
Project Package Delivery
Signup and view all the flashcards
Dedicated Boxes for CofC
Dedicated Boxes for CofC
Signup and view all the flashcards
Shipment Checklist
Shipment Checklist
Signup and view all the flashcards
Transport Team
Transport Team
Signup and view all the flashcards
Forwarder
Forwarder
Signup and view all the flashcards
ZOHO System
ZOHO System
Signup and view all the flashcards
SECTION C
SECTION C
Signup and view all the flashcards
SECTION D
SECTION D
Signup and view all the flashcards
Submission of Checklist
Submission of Checklist
Signup and view all the flashcards
Study Notes
Standard Operating Procedure (SOP) for Staging Process
- The SOP outlines procedures for receiving, staging, and preparing panels for the logistic department.
- Panels are received only if serviceable with relevant paperwork.
- Daily panel deliveries, except for urgent/critical cases, occur twice (morning and evening) during working hours.
- Staging personnel ensure sufficient space before receiving panels from Final Inspection.
Staging Process Procedure
- Staging receives serviceable panels with paperwork from Final Inspection, stored in a regulator.
- Final Inspection delivers panels twice daily (morning and evening), before and after work ends, excluding urgent critical cases.
- Ensure sufficient space at the Staging area before final inspection hand over the panels.
Working Tools and PPE
- Working Tools: Glue heat gun, strapping machine, etc.
- PPE: Gloves, safety shoes, safety belt, safety goggles, safety helmet.
- The document lists various tools and personal protective equipment (PPE) necessary for the staging process.
Packaging Process
- Verify panel and paperwork consistency (part number, description, CSN).
- Visually inspect panel condition on and the condition of the regulator.
- Arrange the regulator according to project packaging or in designated spots (pigeonholes) ensuring safe panel storage.
- Employees are prohibited from accepting potentially faulty panels.
- Received panels should be stored in a closed area.
Selecting Process
- Team Leaders determine panels for packaging, prioritising First-In, First-Out (FIFO).
- Daily panel data is sourced from the QAD system for packaging/delivery selection, based on FIFO.
- Panels selected might be from incomplete buffers, existing pigeonholes, or new arrivals from Final Inspection.
- Panels stored over 6 months need inspection for conditions like dirt, dust, fungus, damage, or foreign object debris (FOD).
- Issues reported to engineers for resolution.
Packaging Checklist
- QR codes initiate electronic packaging checklists.
- The checklist verifies panel data (part number, description, CSN number).
- Visual checks ensure no dirt, dust, fungus, damage, or foreign objects.
- Panels are cleaned according to standards (normal/black panels).
- The authorised operator approves the cleaned panels.
- Panels are wrapped/packed as per project package specifications (per SOP08-017).
Packaging and Buffer Process
- Employees use QR codes to generate digital packaging checklists.
- The checklist verifies pre-defined criteria (part numbers, conditions).
- Employees clean panels, following procedures for standard/black panels.
- Authorized operators verify the cleanliness.
- Panels are wrapped/packed per project package SOPs.
Paperwork Process and CofC (Certificate of Conformance)
- Paperwork, identified by SSN number, is collected and processed by the relevant documentation team.
- CofC (Certificates of Conformance) are obtained electronically from the Quality Department and printed.
- CofCs are inserted inside each delivery box per project specifications.
Strapping Boxes and Shipment Checklist
- Boxes are strapped using company-provided equipment (strapping machine, tape).
- Employee checks for external box condition (no visible dirt, damage, or foreign objects).
- Employees use the digital shipment checklist to complete documentation, conforming to SOP08-040.
e-MTR Booking System
- Employees book forklift services for loading/unloading goods via the e-MTR system.
- Details like pick-up date/time, collection/unloading point, and item descriptions are necessary inputs for booking.
- Forklift operators load/unload boxes following e-MTR instructions.
Shipment Checklist
- Transport staff completes the online Shipment Checklist, transferring data from Staging and passing to Forwarders.
- Forwarders provide details of the shipment and submit through the system.