Project Time Management Fundamentals

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to Lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

Which of the following is the primary purpose of the 'Define Activities' process in project management?

  • To sequence the project activities in the correct order.
  • To create a budget for each project activity.
  • To estimate the resources needed for each work package.
  • To identify and document the specific actions required to produce project deliverables. (correct)

Which of the following BEST describes a 'work package' in project management?

  • A document outlining the project's communication plan.
  • The smallest deliverable-oriented component of the work breakdown structure. (correct)
  • A collection of project activities assigned to a specific team member.
  • A risk mitigation strategy for a specific project threat.

According to the 8/80 rule, what is the recommended range for the effort required to complete a work package?

  • Between 40 and 100 hours.
  • Between 8 and 80 hours. (correct)
  • Less than 4 hours.
  • More than 80 hours.

What is the primary purpose of a schedule management plan in project management?

<p>To document the procedures for developing, maintaining, and managing the project schedule. (B)</p> Signup and view all the answers

Which of the following is LEAST likely to be included in a schedule management plan?

<p>Detailed budget information for each project activity. (B)</p> Signup and view all the answers

Which of the following is NOT an input to the 'Define Activities' process?

<p>Project charter. (D)</p> Signup and view all the answers

What is the purpose of decomposing work packages into activities when defining project activities?

<p>To break down the work into manageable tasks that can be estimated and scheduled. (C)</p> Signup and view all the answers

In the context of project activities, what is meant by naming activities in 'verb-noun' format?

<p>Activities should be named using action-oriented words followed by the deliverable. (A)</p> Signup and view all the answers

What is the primary goal of the 'Sequence Activities' process in project management?

<p>To identify and document the relationships between project activities. (C)</p> Signup and view all the answers

What is an 'activity dependency' in project management?

<p>The logical relationship that exists between two project activities. (A)</p> Signup and view all the answers

If a project activity must be completed before another activity can begin due to physical constraints, what type of dependency is this?

<p>Mandatory dependency. (A)</p> Signup and view all the answers

Which type of activity dependency is based on the project team's preferred sequence of activities?

<p>Discretionary dependency. (C)</p> Signup and view all the answers

What does a 'Finish-to-Start' (FS) relationship between two project activities mean?

<p>Activity A must finish before Activity B can start. (C)</p> Signup and view all the answers

Which precedence relationship type requires that Activity A must start before Activity B can finish?

<p>Start-to-Finish (SF). (A)</p> Signup and view all the answers

What is a 'lag' in project schedule management?

<p>A delay in the start of a successor activity. (C)</p> Signup and view all the answers

In project scheduling, what is the purpose of applying a 'lead'?

<p>To accelerate a successor activity. (A)</p> Signup and view all the answers

What is the primary purpose of a project schedule network diagram?

<p>To graphically represent the sequence of project activities and their dependencies. (C)</p> Signup and view all the answers

Which of the following statements is a key characteristic of the Precedence Diagramming Method (PDM)?

<p>It uses nodes to represent activities and arrows to represent precedence relationships. (B)</p> Signup and view all the answers

What is another term for 'summary activities' in project scheduling?

<p>Hammock activities. (B)</p> Signup and view all the answers

What is the key characteristic of conditional diagramming methods?

<p>They allow for nonsequential activities such as loops or conditional branches. (D)</p> Signup and view all the answers

When creating a project schedule network diagram using the Precedence Diagramming Method (PDM), what is the first step after gathering the activity list?

<p>Determine the dependencies among project activities. (C)</p> Signup and view all the answers

Which of the following is an example of a project resource?

<p>Labor, materials, and equipment. (B)</p> Signup and view all the answers

What is the main objective of the 'Estimate Activity Resources' process?

<p>To identify the specific resources needed to complete project activities. (A)</p> Signup and view all the answers

Which of the following is an input to the 'Estimate Activity Resources' process?

<p>Activity list. (C)</p> Signup and view all the answers

When estimating activity resources, what should a project manager do if certain resources are unavailable?

<p>Generate possible alternatives for unavailable resources. (A)</p> Signup and view all the answers

A project team is determining whether to purchase software licenses or hire a contractor with their own licenses. Which tool or technique for ‘Estimate Activity Resources’ is being applied?

<p>Alternatives analysis. (C)</p> Signup and view all the answers

What is the BEST description of the 'Estimate Activity Durations' process?

<p>The process of estimating the quantity of work required to complete project activities. (C)</p> Signup and view all the answers

Which of the following is a tool or technique used in the 'Estimate Activity Durations' process?

<p>Three-point estimates. (B)</p> Signup and view all the answers

A project manager asks the work package owners to estimate the time required for their respective tasks. Which guideline for estimating activity durations is being followed?

<p>Involve the work package owners. (A)</p> Signup and view all the answers

During the 'Estimate Activity Durations' process, a project manager reviews similar past projects to predict the duration of current activities. Which technique is being used?

<p>Analogous estimating. (D)</p> Signup and view all the answers

What should a project manager consider when determining how to quantify the work for activity duration estimates?

<p>The units of measure for the work and the level of precision needed. (B)</p> Signup and view all the answers

After estimating individual activity durations, what is an important step to ensure accuracy?

<p>Verifying the accuracy of your estimates. (B)</p> Signup and view all the answers

Why is it important to consider the need for reserve time when estimating activity durations?

<p>To account for potential delays and unexpected issues. (D)</p> Signup and view all the answers

Flashcards

What is an activity?

A basic unit of project work needing an action to create a deliverable.

What is a work package?

Planned work or deliverables; the lowest WBS component where cost/schedule is easily estimated.

What is the 8/80 rule?

Guideline: Work packages need more than 8, but less than 80 hours of effort.

What is a schedule management plan?

A document describing the approach to develop, maintain and manage the project schedule.

Signup and view all the flashcards

What is the Define Activities process?

Identifying and documenting actions to create project deliverables.

Signup and view all the flashcards

What is Sequence Activities?

Planning process to identify and document dependencies among activities.

Signup and view all the flashcards

What are Activity Dependencies?

A logical connection between two project activities.

Signup and view all the flashcards

What is a mandatory dependency?

Inherent to the work with physical constraints. Activity dependency type.

Signup and view all the flashcards

What is a discretionary dependency?

Defined by the team's discretion. Activity dependency type.

Signup and view all the flashcards

What is an external dependency?

Contingent on external factors. Activity dependency type.

Signup and view all the flashcards

What are precedence relationships?

Logical link between two activities describing the order to carry things out.

Signup and view all the flashcards

What is Finish-to-Start (FS)?

Activity A must finish before activity B can START.

Signup and view all the flashcards

What is Finish-to-Finish (FF)?

Activity A must finish before activity B can FINISH.

Signup and view all the flashcards

What is Start-to-Start (SS)?

Activity A must start before activity B can START.

Signup and view all the flashcards

What is Start-to-Finish (SF)?

Activity A must start before activity B can FINISH.

Signup and view all the flashcards

What is a lag?

A delay in starting a successor activity.

Signup and view all the flashcards

What is a lead?

Successor activity starts before the predecessor ends in a FS relationship.

Signup and view all the flashcards

What is a Project Schedule Network Diagram?

Visual depiction of project activities and their dependencies.

Signup and view all the flashcards

What is the Precedence Diagramming Method (PDM)?

Project schedule network diagram with boxes/nodes for activities and arrows showing relationships.

Signup and view all the flashcards

What are summary activities?

A group of related schedule activities shown as a single aggregate activity.

Signup and view all the flashcards

What are conditional diagramming methods?

A diagramming method enabling non-sequential activities, loops, or conditional branches.

Signup and view all the flashcards

What are project resources?

Any useful material object or person needed for project completion.

Signup and view all the flashcards

What is Estimate Activity Resources?

Determining specific resources to complete the activities of the project.

Signup and view all the flashcards

What is The Estimate Activity Durations Process?

Calculating the amount of work to complete project activities using available resources.

Signup and view all the flashcards

Study Notes

  • Estimating project time involves creating an activity list, creating a Project Schedule Network Diagram, estimating activity resources, and estimating duration for project activities.
  • Project Time Management belongs to the Planning Process Group.

Activities

  • Activities represent an element of project work requiring an action to produce a deliverable.
  • Activities should have an expected duration, consume budget or human resources, and be named in verb-noun format.
  • An example of activities in a company project are to revise user manual, make a sales presentation and to reserve conference room.

Work Package

  • Work packages are planned work or deliverables and are the lowest-level component of the work breakdown structure (WBS).
  • Cost and schedule can be easily estimated for work packages.

The 8/80 Rule

  • The 8/80 rule is a guideline for work packages, suggesting they require more than 8 but fewer than 80 hours of effort to complete.
  • It aids project managers in creating work package lists.

Schedule Management Plans

  • Schedule management plans involve an approach to developing, maintaining, and managing the project schedule.
  • These plans describe the purpose, approved tools and techniques, number/types/purposes of project schedules, how changes to the schedule baseline are managed, responsibilities for developing and maintaining project schedules, and schedule performance reporting.

Define Activities Process

  • This is the process of identifying and documenting specific activities that must be performed to produce the project's deliverables.
  • Inputs include scope baseline, enterprise environmental factors and organizational process assets.
  • Tools and techniques include decomposition, rolling wave planning, templates, and expert judgment.
  • Outputs include an activity list, activity attributes, and a milestone list.

How to Define Activities

  • Guidelines include gathering inputs and materials, analyzing and decomposing each work package of the WBS (Work Breakdown Structure) into activities required to produce the deliverable.
  • Other guidelines include consulting records of similar projects/subject matter experts/all constraints and assumptions.
  • As well as evaluating the activity list once each work package is decomposed into activities.

Completed WBS Table Example

  • WBS: TRN0002.0 to student to assess needs.
  • Training activity examples: training needs review with key resources; review with BT Strategic Planning group, identify high-level BT PM Needs, PMO Steering Committee, new PM processes; training content review, training material and results.

The Sequence Activities Process

  • The sequence activities process is a planning process that involves identifying and documenting interactivity dependencies among project activities for the purpose of creating the project schedule.
  • Inputs include activity list, activity attributes, milestone list, project scope statement, and organizational process assets.
  • Tools & Techniques include precedence diagramming method (PDM), dependency determination, applying leads and lags, along with schedule network templates.
  • Outputs include project schedule network diagrams and project document updates.

Activity Dependencies

  • Activity dependencies represent a logical relationship that exists between two project activities.
  • Design functionality depends on the framed structure, walls, windows, and roof.
  • The structure in place depends on reassessing the plans and determining modifications.

Types of Activity Dependencies

  • Mandatory dependencies are inherent to the work itself and affected by physical constraints.
  • Discretionary dependencies are defined by the project and project management team at their discretion.
  • External dependencies are contingent on inputs from outside the project activities.

Precedence Relationships

  • Precedence relationships are the logical relationships between two activities that describes the sequence in which they should be carried out.
  • For example, drywall installation must finish before painting can begin.

Precedence Relationship Types

  • Finish-to-Start (FS): Activity A must finish before activity B can start.
  • Finish-to-Finish (FF): Activity A must finish before activity B can finish.
  • Start-to-Start (SS): Activity A must start before activity B can start.
  • Start-to-Finish (SF): Activity A must start before activity B can finish.

Lag and Lead

  • Lag represents a delay in the start of a successor activity.
  • Lead represents a change in a logical relationship and allows the successor activity to start before the predecessor activity ends in a finish-to-start (FS) relationship.
  • Lead is implemented when a successor activity needs to be accelerated to shorten the project schedule.

Project Schedule Network Diagrams

  • These diagrams are a graphical representation of the sequence of project activities and their dependencies.
  • They are read from left to right or top to bottom.

The Precedence Diagramming Method (PDM)

  • PDM produces a project schedule network diagram that uses rectangular boxes (nodes) to represent activities and arrows to represent precedence relationships between activities.
  • PDM characteristics: Reads from left to right, shows duration in nodes, can be created manually or with software, reports related activities as an aggregate, and uses all precedence relationship types.

Summary Activities

  • Summary Activities are a group of related schedule activities shown as a single aggregate activity in a bar chart or graph for reporting purposes.
  • Summary activities are also called "hammock activities."

Conditional Diagramming Methods

  • Conditional Diagramming Methods are a network diagramming method that allows for nonsequential activities, such as loops or conditional branches.

How to Create a Project Schedule Network Diagram

  • Steps to create a PDM project schedule network diagram: Determine dependencies, identify predecessor and successor activities, create nodes, draw arrows and include lags/leads.
  • The final step is to verify diagram accuracy.

Project Resources

  • Project resources are useful material objects or people needed for project completion.
  • These include labor, materials, facilities, equipment, consultants, services, supplies, and utilities.
  • For example, resources for a health & wellness seminar project could be a conference room, brochures/pamphlets, visiting consultants and vendors.

Estimate Activity Resources Process

  • It involves determining specific resources necessary for completing project activities.
  • Inputs include activity list, activity attributes, resource calendars, enterprise environmental factors and organizational process assets.
  • Methods and techniques include expert judgment, alternatives analysis, published estimating data, bottom-up estimating, and project management software.
  • Resulting in activity resource requirements, resource breakdown structure, and project document updates .

How to Estimate Activity Resources

  • Guidelines include determining what resources and quantity are necessary, generate alternatives for unavailable resources.
  • Other guidelines include analyzing the scope statement, organizational policies, if needed identify expert judgement, and analyze the resources already available.
  • For example, determining resources for a website design project include hiring a contractor, computer/printer/workstation, software, and commercial printing capabilities.

Estimate Activity Durations Process

  • The activity involves estimating the quantity of work required to complete individual project activities using available resources.
  • Inputs include activity list, activity attributes, resource requirements, resource calendars, project scope statement, enterprise environmental factors, and organizational process assets.
  • Tools and Techniques include expert judgment, analogous estimating, parametric estimating, three-point estimates, and reserve analysis.
  • Outputs include activity duration estimates and project document updates.

How to Estimate Duration for Project Activities

  • Guidelines include involving work package owners, and consulting historical information.
  • Other guidelines: Determine how to quantify work, consider resource requirements/capabilities, determine the appropriate estimation method, modify planning process constraints/assumptions, verify accuracy, and consider the need for reserve time.
  • Including activity estimates such as resources, website design work , and units.

Studying That Suits You

Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

Quiz Team

Related Documents

More Like This

Use Quizgecko on...
Browser
Browser