Podcast
Questions and Answers
What are the early start and late finish times associated with this hammock activity?
What are the early start and late finish times associated with this hammock activity?
What are the early start and late finish times associated with this hammock activity?
What are the early start and late finish times associated with this hammock activity?
The amount of time an activity may be delayed from its early start without delaying the finish of the project is the:
The amount of time an activity may be delayed from its early start without delaying the finish of the project is the:
The least amount of float is found:
The least amount of float is found:
Signup and view all the answers
What is the slack time for Activity B given the activity times and precedence requirements?
What is the slack time for Activity B given the activity times and precedence requirements?
Signup and view all the answers
What is the slack time for Activity D given the activity times and precedence requirements?
What is the slack time for Activity D given the activity times and precedence requirements?
Signup and view all the answers
What is the float start time for Activity C given the activity times and precedence requirements?
What is the float start time for Activity C given the activity times and precedence requirements?
Signup and view all the answers
What is the slack time for Activity B?
What is the slack time for Activity B?
Signup and view all the answers
What is the slack time for activity E?
What is the slack time for activity E?
Signup and view all the answers
What is the slack time for activity D?
What is the slack time for activity D?
Signup and view all the answers
Float is always measured in exactly the same way as slack.
Float is always measured in exactly the same way as slack.
Signup and view all the answers
Negative float exists when a project's critical path has been completed more quickly than anticipated.
Negative float exists when a project's critical path has been completed more quickly than anticipated.
Signup and view all the answers
Activity float is the difference between the late finish and early finish for the activity in question.
Activity float is the difference between the late finish and early finish for the activity in question.
Signup and view all the answers
What is the probability that the project is completed in 31 days?
What is the probability that the project is completed in 31 days?
Signup and view all the answers
What is the probability that the project takes more than 34 days?
What is the probability that the project takes more than 34 days?
Signup and view all the answers
The PERT technique assumes that durations are more deterministic.
The PERT technique assumes that durations are more deterministic.
Signup and view all the answers
What are the late start and early finish times of the hammock activity?
What are the late start and early finish times of the hammock activity?
Signup and view all the answers
Which is a legitimate hammock activity for this project?
Which is a legitimate hammock activity for this project?
Signup and view all the answers
What are the duration and the early start time associated with this hammock activity?
What are the duration and the early start time associated with this hammock activity?
Signup and view all the answers
One approach to reducing project length would be to:
One approach to reducing project length would be to:
Signup and view all the answers
A project's duration can be reduced by:
A project's duration can be reduced by:
Signup and view all the answers
The BEST candidate activities for shortening the overall project are:
The BEST candidate activities for shortening the overall project are:
Signup and view all the answers
Which technique would accelerate the completion of a project?
Which technique would accelerate the completion of a project?
Signup and view all the answers
In order to reduce the length of a project, it would be wise to shorten:
In order to reduce the length of a project, it would be wise to shorten:
Signup and view all the answers
In general, the better candidates for shortening are:
In general, the better candidates for shortening are:
Signup and view all the answers
The term ordered activity means:
The term ordered activity means:
Signup and view all the answers
A sequence of activities defined by the project network logic is a(n):
A sequence of activities defined by the project network logic is a(n):
Signup and view all the answers
One of the defining points of a network, a junction point joined to some or all of the others by dependency lines, is called a(n):
One of the defining points of a network, a junction point joined to some or all of the others by dependency lines, is called a(n):
Signup and view all the answers
These can be located by doing a backward pass through a network:
These can be located by doing a backward pass through a network:
Signup and view all the answers
Another name for an activity is a(n):
Another name for an activity is a(n):
Signup and view all the answers
Serial activities are those that:
Serial activities are those that:
Signup and view all the answers
Concurrent activities are:
Concurrent activities are:
Signup and view all the answers
Which of these statements about this network is BEST?
Which of these statements about this network is BEST?
Signup and view all the answers
A backward pass is performed when it is necessary to undo some work that has been performed in order to complete it properly.
A backward pass is performed when it is necessary to undo some work that has been performed in order to complete it properly.
Signup and view all the answers
Network logic suggests that:
Network logic suggests that:
Signup and view all the answers
Based on the activity network pictured, what is the BEST statement?
Based on the activity network pictured, what is the BEST statement?
Signup and view all the answers
Based on the activity network pictured, what is the BEST statement?
Based on the activity network pictured, what is the BEST statement?
Signup and view all the answers
In order to depict this in an activity network:
In order to depict this in an activity network:
Signup and view all the answers
The overall effect of laddering activities is to:
The overall effect of laddering activities is to:
Signup and view all the answers
Summaries for some subsets of the activities identified in the overall project network are called:
Summaries for some subsets of the activities identified in the overall project network are called:
Signup and view all the answers
Hammock activities allow:
Hammock activities allow:
Signup and view all the answers
Activities C, D, and E in the project represented by the network are to be hammocked. What is the activity length of the hammock activity?
Activities C, D, and E in the project represented by the network are to be hammocked. What is the activity length of the hammock activity?
Signup and view all the answers
Activities C, D, and E in the project represented by the network are to be hammocked. What are the early start and late finish times of the hammock activity?
Activities C, D, and E in the project represented by the network are to be hammocked. What are the early start and late finish times of the hammock activity?
Signup and view all the answers
Preceding activities are those that must occur before others can be done.
Preceding activities are those that must occur before others can be done.
Signup and view all the answers
A merge activity has two or more immediate predecessors.
A merge activity has two or more immediate predecessors.
Signup and view all the answers
Burst activities are those with two or more successor activities.
Burst activities are those with two or more successor activities.
Signup and view all the answers
At a merge point in a forward pass, the largest preceding early finish becomes the early start for that node.
At a merge point in a forward pass, the largest preceding early finish becomes the early start for that node.
Signup and view all the answers
At a burst point in a backward pass, the largest succeeding late start becomes the late finish for that node.
At a burst point in a backward pass, the largest succeeding late start becomes the late finish for that node.
Signup and view all the answers
Prior to creating a network, it is important to:
Prior to creating a network, it is important to:
Signup and view all the answers
The length of time expected to complete an activity assuming that its development proceeds normally is called the:
The length of time expected to complete an activity assuming that its development proceeds normally is called the:
Signup and view all the answers
Ray's shipment of materials hit every red light and traffic jam. Which statement accurately reflects the project activity of Material Delivery?
Ray's shipment of materials hit every red light and traffic jam. Which statement accurately reflects the project activity of Material Delivery?
Signup and view all the answers
The variance of an activity is given by:
The variance of an activity is given by:
Signup and view all the answers
An activity has an optimistic time estimate of 25 days, a most likely estimate of 29 days, and a pessimistic estimate of 34 days. What is the expected duration of the activity?
An activity has an optimistic time estimate of 25 days, a most likely estimate of 29 days, and a pessimistic estimate of 34 days. What is the expected duration of the activity?
Signup and view all the answers
An activity has an optimistic time estimate of 17 days, a most likely estimate of 23 days, and a pessimistic estimate of 37 days. What is the variance of the activity?
An activity has an optimistic time estimate of 17 days, a most likely estimate of 23 days, and a pessimistic estimate of 37 days. What is the variance of the activity?
Signup and view all the answers
An activity has an optimistic time estimate of 17 days, a most likely estimate of 22 days, and a pessimistic estimate of 32 days. What is the expected duration of the activity?
An activity has an optimistic time estimate of 17 days, a most likely estimate of 22 days, and a pessimistic estimate of 32 days. What is the expected duration of the activity?
Signup and view all the answers
An activity has an optimistic time estimate of 12 days, a most likely estimate of 16 days, and a pessimistic estimate of 22 days. What is the expected standard deviation of the activity?
An activity has an optimistic time estimate of 12 days, a most likely estimate of 16 days, and a pessimistic estimate of 22 days. What is the expected standard deviation of the activity?
Signup and view all the answers
An activity has a pessimistic time that is four times as long as its most likely time and six times as long as its optimistic time. If the activity variance is 12, what is the expected time?
An activity has a pessimistic time that is four times as long as its most likely time and six times as long as its optimistic time. If the activity variance is 12, what is the expected time?
Signup and view all the answers
Activity Z has estimates a = 5, b = 12, m = 7; which statement is BEST?
Activity Z has estimates a = 5, b = 12, m = 7; which statement is BEST?
Signup and view all the answers
What is the expected completion time of the laddered project?
What is the expected completion time of the laddered project?
Signup and view all the answers
What is the expected completion time of the laddered project? (Repeat question)
What is the expected completion time of the laddered project? (Repeat question)
Signup and view all the answers
What is the expected completion time of the project?
What is the expected completion time of the project?
Signup and view all the answers
What is the standard deviation of the project's critical path?
What is the standard deviation of the project's critical path?
Signup and view all the answers
You must know the mean of an activity in order to determine its standard deviation.
You must know the mean of an activity in order to determine its standard deviation.
Signup and view all the answers
In assigning a value for the most pessimistic (b) duration, the project manager should estimate the duration of the activity to have a 99% likelihood that it will take b or less amount of time.
In assigning a value for the most pessimistic (b) duration, the project manager should estimate the duration of the activity to have a 99% likelihood that it will take b or less amount of time.
Signup and view all the answers
The late start time should be calculated using a forward pass through the network.
The late start time should be calculated using a forward pass through the network.
Signup and view all the answers
Laddering is a technique that allows the project manager to redraw the network to more closely sequence project subtasks to make the overall network sequence more efficient.
Laddering is a technique that allows the project manager to redraw the network to more closely sequence project subtasks to make the overall network sequence more efficient.
Signup and view all the answers
Hammock activities break a task into greater levels of detail so that each task is represented as two or more subtasks that each have their own duration and precedence requirements.
Hammock activities break a task into greater levels of detail so that each task is represented as two or more subtasks that each have their own duration and precedence requirements.
Signup and view all the answers
What is the earliest that Activity D can begin if Activity A takes 3 days, Activity B takes 5 days, and Activity C takes 7 days?
What is the earliest that Activity D can begin if Activity A takes 3 days, Activity B takes 5 days, and Activity C takes 7 days?
Signup and view all the answers
What is the early start time for Activity D given the activity times and precedence requirements shown in the table?
What is the early start time for Activity D given the activity times and precedence requirements shown in the table?
Signup and view all the answers
What is the late start time for Activity B given the activity times and precedence requirements shown in the table?
What is the late start time for Activity B given the activity times and precedence requirements shown in the table?
Signup and view all the answers
What is the late start time for Activity E given the activity times and precedence requirements shown in the table?
What is the late start time for Activity E given the activity times and precedence requirements shown in the table?
Signup and view all the answers
What is the late finish time for Activity D given the activity times and precedence requirements shown in the table?
What is the late finish time for Activity D given the activity times and precedence requirements shown in the table?
Signup and view all the answers
What is the early start time for Activity G given the activity times and precedence requirements shown in the table?
What is the early start time for Activity G given the activity times and precedence requirements shown in the table?
Signup and view all the answers
What is the early finish time for Activity F given the activity times and precedence requirements shown in the table?
What is the early finish time for Activity F given the activity times and precedence requirements shown in the table?
Signup and view all the answers
Use the information in the table to determine the late start time for Activity E.
Use the information in the table to determine the late start time for Activity E.
Signup and view all the answers
Use the information in the table to determine the early start time for Activity B.
Use the information in the table to determine the early start time for Activity B.
Signup and view all the answers
Use the information in the table to determine the early finish time for Activity D.
Use the information in the table to determine the early finish time for Activity D.
Signup and view all the answers
Use the information in the table to determine the late finish time for Activity B.
Use the information in the table to determine the late finish time for Activity B.
Signup and view all the answers
Use the network diagram and activity lengths in the nodes to determine the early start time for activity D.
Use the network diagram and activity lengths in the nodes to determine the early start time for activity D.
Signup and view all the answers
Use the network diagram and activity lengths in the nodes to determine the late start time for activity F.
Use the network diagram and activity lengths in the nodes to determine the late start time for activity F.
Signup and view all the answers
Use the network diagram and activity lengths in the nodes to determine the early finish time for activity G.
Use the network diagram and activity lengths in the nodes to determine the early finish time for activity G.
Signup and view all the answers
Use the network diagram and activity lengths in the nodes to determine the late finish time for activity C.
Use the network diagram and activity lengths in the nodes to determine the late finish time for activity C.
Signup and view all the answers
Use the network diagram and activity lengths in the nodes to determine the early start time for activity D.
Use the network diagram and activity lengths in the nodes to determine the early start time for activity D.
Signup and view all the answers
Use the network diagram and activity lengths in the nodes to determine the late finish time for activity D.
Use the network diagram and activity lengths in the nodes to determine the late finish time for activity D.
Signup and view all the answers
Use the network diagram and activity lengths in the nodes to determine the early finish time for activity G.
Use the network diagram and activity lengths in the nodes to determine the early finish time for activity G.
Signup and view all the answers
What is the difference in the late start time for activity C in the original project and activity C1 in the laddered project?
What is the difference in the late start time for activity C in the original project and activity C1 in the laddered project?
Signup and view all the answers
What is the late finish for the Plant Posts activity?
What is the late finish for the Plant Posts activity?
Signup and view all the answers
Study Notes
Project Scheduling Concepts
- Ordered activity in project management implies tasks must follow specific precedence or sequence.
- Sequence of activities defined by project network logic is termed a "Path."
- A "Node" refers to a junction point in a network, connecting various activities through dependency lines.
- Critical paths can be identified using backward passes in a project network.
- An activity can also be referred to as a "Work package," which has an expected duration and cost.
Activity Types
- Serial activities flow one after the other, while concurrent activities can be performed simultaneously.
- Merge activities have two or more immediate predecessors, whereas burst activities have two or more successor activities.
Network Logic and Activity Sequencing
- A network diagram helps understand the necessary order of activities; for instance, Activity A must be complete before Activity B starts.
- Laddering is a technique used to improve the sequence of tasks, keeping project resources employed efficiently.
Time Estimates and Variance
- An activity's expected duration is calculated using optimistic, most likely, and pessimistic estimates.
- Variance of an activity helps in understanding the uncertainty in time estimates, calculated by the formula [1/6(b-a)]².
- The expected duration formula is derived from the weighted average of time estimates.
Activities and Their Timing
- Hammock activities summarize multiple subsets of activities and can streamline project management by combining activities efficiently.
- The early start and late finish times ensure the project runs on schedule, and calculations can be derived from the network diagram.
Float and Slack Time
- Float represents the amount of time an activity can be delayed without affecting the project deadline. It is crucial for resource allocation and scheduling.
- Slack time is indicative of the flexibility available in the project schedule, allowing adjustments as necessary.
Analytical Techniques
- Understanding the critical path method (CPM) is essential for managing project timelines and identifying activities that directly affect project completion.
- Use of diagrams and tables to depict activities, durations, and precedence requirements facilitates better visualization of the project status.
Summary of Key Points
- Understanding different types of activities (serial, concurrent, merge, burst) helps in effective project scheduling.
- Calculation methods for time estimates and variances guide project managers in estimating activity durations realistically.
- Techniques like laddering and the identification of hammock activities increase efficiency in project planning.
- Regular calculation of float and slack enhances project flexibility, allowing for timely adjustments.### Slack Time and Float
- Slack time for an activity denotes the total time that an activity can be delayed without delaying the project.
- Float and slack are measured in the same manner, indicating flexibility in the project schedule.
- Negative float occurs when the critical path is completed faster than planned.
Activity Float
- Activity float is calculated as the difference between the late finish and early finish times of that activity.
Project Management Techniques
- PERT (Program Evaluation Review Technique) assumes that project durations are deterministic rather than probabilistic.
- Hammock activities are used to combine multiple activities and represent them as a single task in project management.
Probability in Project Duration
- The likelihood of project completion in a specific timeframe can be assessed using statistical methods based on multiple time estimates for tasks.
- A high probability value indicates that it is more likely the project will take longer than the specified period.
Strategies for Reducing Project Length
- Projects can be shortened by eliminating tasks on the critical path and shortening the duration of critical path tasks.
- Candidates for shortening are generally those tasks that can expedite the overall project timeline, especially critical path activities.
- Early tasks are often better candidates for shortening, as they could significantly affect subsequent tasks.
Techniques for Accelerating Projects
- Laddering is a technique that can accelerate project completion by overlapping activities.
- Bursting refers to breaking apart a project schedule to allow for more concurrent tasks, enhancing efficiency.
Task Selection for Shortening Projects
- When selecting tasks to shorten, focus on critical path activities that offer the greatest potential for speeding up the project.
- Criteria for selecting activities can include both duration and cost considerations, with emphasis placed on tasks that have the highest impact on the overall timeline.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Description
Test your understanding of project scheduling concepts with these flashcards from Chapter 9. Explore key terms like ordered activities and how they influence task management in project planning. Perfect for students looking to reinforce their knowledge in project management.