What is the total number of work hours allocated for each day from Sunday to Saturday according to the Global Calendar?
What is the total number of work hours allocated for each day from Sunday to Saturday according to the Global Calendar?
- 30 hours
- 21 hours (correct)
- 24 hours
- 16 hours
Which Organizational Breakdown Structure (OBS) role is listed without any responsibilities specified?
Which Organizational Breakdown Structure (OBS) role is listed without any responsibilities specified?
- CIVIL HEAD
- SENIOR MANAGER
- CEO
- CHAIRMAN (correct)
Which EPS ID is responsible to the CEO according to the Enterprise Project Structure?
Which EPS ID is responsible to the CEO according to the Enterprise Project Structure?
- NEWEPS
- TATA CONSTRUCTION
- TCS
- TATA (correct)
What is the starting date for the activity 'Dismantling Structures' in the PUNE ROAD PROJECT?
What is the starting date for the activity 'Dismantling Structures' in the PUNE ROAD PROJECT?
What is the planned date for providing and laying Tack Co?
What is the planned date for providing and laying Tack Co?
Which of the following units of measure is NOT listed in the Units Of Measure table?
Which of the following units of measure is NOT listed in the Units Of Measure table?
Which activity is scheduled to be completed first in January 2025?
Which activity is scheduled to be completed first in January 2025?
According to the Calendar Weekly Hours, which day has the highest work hours assigned?
According to the Calendar Weekly Hours, which day has the highest work hours assigned?
What is the primary role of the resource labeled 'SITE ENGINEER'?
What is the primary role of the resource labeled 'SITE ENGINEER'?
Which abbreviation corresponds to 'Each' in the Units Of Measure?
Which abbreviation corresponds to 'Each' in the Units Of Measure?
In which month is the construction of CULVERT scheduled to start?
In which month is the construction of CULVERT scheduled to start?
What is the function of the Global Calendar ROADCAL as described?
What is the function of the Global Calendar ROADCAL as described?
How many planned activities are listed for April 2025?
How many planned activities are listed for April 2025?
What type of resource is labeled as 'DUMPERS' in the project?
What type of resource is labeled as 'DUMPERS' in the project?
Which of the following resources does NOT have a specified unit of measure?
Which of the following resources does NOT have a specified unit of measure?
What is the completion date for the Providing and laying Bituminc activity?
What is the completion date for the Providing and laying Bituminc activity?
Flashcards
Enterprise Project Structure (EPS)
Enterprise Project Structure (EPS)
A hierarchical structure to categorize projects within an enterprise.
Organizational Breakdown Structure (OBS)
Organizational Breakdown Structure (OBS)
A hierarchical chart illustrating reporting relationships and responsibilities.
Global Calendar (ROADCAL)
Global Calendar (ROADCAL)
A calendar outlining project work hours and holidays.
Units of Measure
Units of Measure
Signup and view all the flashcards
Currency Options
Currency Options
Signup and view all the flashcards
Activity ID
Activity ID
Signup and view all the flashcards
Activity Name
Activity Name
Signup and view all the flashcards
Project Start Date
Project Start Date
Signup and view all the flashcards
PUNE ROAD PROJECT
PUNE ROAD PROJECT
Signup and view all the flashcards
Site Clearance
Site Clearance
Signup and view all the flashcards
Excavation
Excavation
Signup and view all the flashcards
Subbase and Base Course
Subbase and Base Course
Signup and view all the flashcards
Construction of Bituminous Course
Construction of Bituminous Course
Signup and view all the flashcards
Construction of Culvert
Construction of Culvert
Signup and view all the flashcards
Road Appurtenances
Road Appurtenances
Signup and view all the flashcards
Project Activities Resources WBS
Project Activities Resources WBS
Signup and view all the flashcards
Study Notes
Project Management Software Documentation
- P6 (Oracle): A software package for project management. Submitted by TS HRIS HIKA (P24706018).
Enterprise Project Structure (EPS)
- EPS: Enterprise Project Structure (EPS) software displays various projects, including TATA, TCS, TATA CONSTRUCTION, TATA POWER, and NEWEPS.
- EPS ID: Unique identifiers for each project within the structure.
- EPS Name: Title of each project (like (New EPS)).
- Responsible Manager: Designation for project leadership (e.g., CEO).
Organizational Breakdown Structure (OBS)
- OBS: Organizational structure displaying hierarchy within projects. Elements include CEO, CHAIRMAN, SENIOR MANAGER, CIVIL HEAD, and MECHANICAL HEAD (New OBS).
- OBS Name: Titles of different roles (like CIVIL HEAD).
- Responsibility: Duties associated with each role.
Calendar
- Global Calendar (ROADCAL): A tool to manage project timelines and work hours, with options to specify holidays and exceptions.
- Work Hours/Day: The total time allocated for project work per day.
- Weekly Hours: Standard work hours per day.
Units of Measure
- Admin Categories: Tools for managing various project aspects (baseline types, expense categories, WBS categories, etc.).
- Units of Measure: Different types of units (e.g., Bags, kg, litres, CPUs, Cubic Yards, Linear feet). Allows for precise measurement.
- New Unit: New units of measure can be added.
Project Schedule (Gantt Chart)
- Projects and Activities: The documents show the activities within numerous projects.
- Start and Finish Dates: Dates for initiating and completing various project phases (using a Gantt-chart format in a project timeline).
Resources
- Resource Type: Categories for project labor (e.g., Labor, Material), equipment, and supplies (like Mason, Supervisor, Steel, Dumper, etc.).
- Unit of Measure: Specific units for each resource (like bags, kg, or hours).
- Primary Role: The role of each resource in the project.
- Default Units/Time: Preset values for resources within the project management software (like labor per day).
WBS (Work Breakdown Structure)
- WBS Code: Unique identifiers for project tasks.
- WBS Name: Descriptions of each task within the project scope (e.g., Site Clearance, Excavation, Subbase construction, Culvert Construction).
- Anticipated Dates: Projected start and completion dates.
- Strategic Priority: The importance level of each project.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Related Documents
Description
This quiz covers essential concepts of project management software, including Oracle P6, Enterprise Project Structure (EPS), and Organizational Breakdown Structure (OBS). It focuses on functionality, project hierarchy, and timeline management features. Test your knowledge on how these tools assist in effective project execution.