Questions and Answers
Which tool or technique is NOT used in the Estimate Costs process?
Which tool or technique is NOT used in the Estimate Costs process?
- Published estimating data
- Expert judgment
- Resource Breakdown Structure (correct)
- Bottom-up estimating
What is the purpose of the Activity Resource Requirements?
What is the purpose of the Activity Resource Requirements?
- To identify types and quantities of resources needed (correct)
- To determine project risks and uncertainties
- To evaluate the project's financial budget
- To establish timelines for each activity
Which of the following is NOT a significant quality of an excellent interior designer?
Which of the following is NOT a significant quality of an excellent interior designer?
- Creativity
- Interpersonal skills
- Technical writing skills (correct)
- Problem-solving skills
Which of the following statements accurately describes the Resource Breakdown Structure?
Which of the following statements accurately describes the Resource Breakdown Structure?
What is necessary for each activity when creating a schedule?
What is necessary for each activity when creating a schedule?
What is considered the most valuable resource in a project?
What is considered the most valuable resource in a project?
Which process involves defining the tasks and milestones needed to complete a project?
Which process involves defining the tasks and milestones needed to complete a project?
What role does cost play in project time management?
What role does cost play in project time management?
Which of the following is NOT one of the processes involved in project time management?
Which of the following is NOT one of the processes involved in project time management?
What is one of the outputs of the Define Activities process?
What is one of the outputs of the Define Activities process?
Which tool is commonly used in the Sequence Activities process?
Which tool is commonly used in the Sequence Activities process?
What is increased by controlling the time it takes to build deliverables within a project?
What is increased by controlling the time it takes to build deliverables within a project?
What task is involved in estimating activity resources?
What task is involved in estimating activity resources?
Which technique is primarily used for determining the longest path through a project schedule?
Which technique is primarily used for determining the longest path through a project schedule?
What does schedule compression aim to achieve within a project?
What does schedule compression aim to achieve within a project?
Which output is produced when applying the critical path method?
Which output is produced when applying the critical path method?
What is the primary focus of resource leveling?
What is the primary focus of resource leveling?
What aspect primarily drives schedule control in project management?
What aspect primarily drives schedule control in project management?
Which of the following is NOT considered an input in schedule network analysis?
Which of the following is NOT considered an input in schedule network analysis?
Identifying major milestones in a project is essential for what purpose?
Identifying major milestones in a project is essential for what purpose?
Which factor is NOT mentioned as a concern for schedule changes?
Which factor is NOT mentioned as a concern for schedule changes?
What is the primary focus of schedule control in project management?
What is the primary focus of schedule control in project management?
Which of the following is NOT an input to the schedule control process?
Which of the following is NOT an input to the schedule control process?
What does corrective action in schedule management aim to achieve?
What does corrective action in schedule management aim to achieve?
Which technique is used to ensure that tasks are completed effectively?
Which technique is used to ensure that tasks are completed effectively?
What is a recommended practice for time management according to the content?
What is a recommended practice for time management according to the content?
Which of the following is a tip for effective project time management?
Which of the following is a tip for effective project time management?
A good corrective action requires which of the following steps?
A good corrective action requires which of the following steps?
What is a common misconception about time management?
What is a common misconception about time management?
Flashcards
Define Activities
Define Activities
The first step in the project time management process, which involves identifying and defining the specific tasks, milestones, and activities needed to complete the project.
Decomposition
Decomposition
A technique used to break down large tasks into smaller, more manageable sub-tasks.
Rolling Wave Planning
Rolling Wave Planning
A method used to create a project schedule that is progressively elaborated as more information becomes available.
Sequence Activities
Sequence Activities
Signup and view all the flashcards
Precedence Diagramming Method (PDM)
Precedence Diagramming Method (PDM)
Signup and view all the flashcards
Estimate Activity Resources
Estimate Activity Resources
Signup and view all the flashcards
Estimate Activity Durations
Estimate Activity Durations
Signup and view all the flashcards
Control Schedule
Control Schedule
Signup and view all the flashcards
Activity Resource Requirements
Activity Resource Requirements
Signup and view all the flashcards
Resource Breakdown Structure
Resource Breakdown Structure
Signup and view all the flashcards
Activity Duration Estimating
Activity Duration Estimating
Signup and view all the flashcards
Targeted Schedule
Targeted Schedule
Signup and view all the flashcards
Planned Schedule
Planned Schedule
Signup and view all the flashcards
Critical Path Method (CPM)
Critical Path Method (CPM)
Signup and view all the flashcards
Resource Leveling
Resource Leveling
Signup and view all the flashcards
What-if Scenario Analysis
What-if Scenario Analysis
Signup and view all the flashcards
Schedule Compression
Schedule Compression
Signup and view all the flashcards
Project Schedule Network Diagram
Project Schedule Network Diagram
Signup and view all the flashcards
Project Milestones
Project Milestones
Signup and view all the flashcards
Schedule Control
Schedule Control
Signup and view all the flashcards
Space
Space
Signup and view all the flashcards
Corrective Action
Corrective Action
Signup and view all the flashcards
Schedule Management
Schedule Management
Signup and view all the flashcards
Schedule Management Plan
Schedule Management Plan
Signup and view all the flashcards
Study Notes
Project Time Management
- Time is the most valuable resource in a project.
- Improper time management can lead to project failure.
- Project time management involves managing the time of the entire project team, not just the project manager.
- Scheduling is a key aspect of project time management.
- Cost plays a crucial role alongside estimates and resource allocation when managing time.
Processes Involved
- Define Activities: Identifying tasks, milestones, and other activities needed to complete a project. Tools and techniques include decomposition, rolling wave planning, templates, and expert judgment. Outputs include an activity list, activity attributes, and a milestone list.
- Sequence Activities: Determining the logical relationships and order of project activities. Tools and techniques include precedence diagramming method (PDM), dependency determination, applying leads and lags, and schedule network templates.
- Estimate Activity Resources: Estimating the materials, people, equipment, and supplies required for each activity. This process is closely coordinated with estimating costs. Tools and techniques include expert judgment, alternative analysis, published estimating data, bottom-up estimating, and project management software.
- Estimate Activity Durations: Estimating the amount of work effort and resources needed to complete an activity. Techniques include expert judgment, analogous estimating, and three-point estimating.
- Develop Schedule: Creating a detailed schedule with start and end dates for each activity. The schedule can be detailed or summarized and may be presented graphically or in a table format. Tools include schedule network analysis, critical path method, resource leveling, what-if scenario analysis, and schedule compression.
- Control Schedule: Managing changes to the project schedule. This involves identifying factors that could cause schedule changes (e.g., project team, stakeholders, management, etc.) and managing any actual changes.
Additional Points
- A key event or major milestone schedule summarizes schedules identifying significant project milestones and completion dates.
- The most integral element of interior design is space because interior design focuses on transforming spaces to be visually appealing.
- Interior design is about people, how they live, attractive environments, and meaning, not just fashion or current trends.
- Schedule control is a part of integrated change management.
- Key aspects to effective time management include setting achievable goals, prioritizing tasks based on importance and urgency, setting time limits, organizing tasks, removing non-essential tasks/activities, and planning ahead.
- Several tips for interior designers to improve their time management include tracking time, using the right software, making lists, using a calendar, creating deadlines, avoiding multitasking, and celebrating accomplishments.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Related Documents
Description
Test your knowledge on key concepts in project management with this quiz. Topics include cost estimation, resource requirements, and quality attributes of interior design. Challenge yourself and see how well you understand the Resource Breakdown Structure and scheduling essentials.