Project Management Concepts

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to Lesson

Podcast

Play an AI-generated podcast conversation about this lesson
Download our mobile app to listen on the go
Get App

Questions and Answers

Which type of diagram is utilized by PERT?

  • Activity diagram
  • Network diagram (correct)
  • Organizational diagram
  • Sequential diagram

What dimensions does the project management magic triangle define?

  • Cost, duration, risk
  • Duration, cost, outline level
  • Time, cost, resources
  • Time, cost, scope (correct)

The Critical Chain method is theoretically grounded in which of the following?

  • Drum Buffer Rope
  • Theory of Constraints (correct)
  • Multitasking
  • Parkinson's Law

Which approach is effective in resolving resource conflicts during project execution?

<p>Changing task work contour (B)</p>
Signup and view all the answers

In the Critical Path Method (CPM), independent slack of an activity:

<p>Can be negative, positive, or 0 (C)</p>
Signup and view all the answers

The 'student syndrome' concept within Critical Chain methodology relates most closely to:

<p>Procrastination effect (B)</p>
Signup and view all the answers

A network graph in project management is best described as:

<p>Finite, continuous, directed, acyclic with one beginning and one end node (A)</p>
Signup and view all the answers

Which of the following is a key parameter in Earned Value Analysis (EVA)?

<p>SV (B)</p>
Signup and view all the answers

In Critical Chain project management, what does a project buffer represent?

<p>A time reserve intended to compensate for project delays (D)</p>
Signup and view all the answers

In earned value management, what does SPI less than 1 indicate?

<p>Project behind schedule (C)</p>
Signup and view all the answers

For a GERT model, when is node number 2 considered inclusively stochastic?

<p>All the activities ending there are finished (B)</p>
Signup and view all the answers

In the PERT method, activity duration is calculated using:

<p>Pessimistic, optimistic, most likely duration estimate (C)</p>
Signup and view all the answers

What is one advantage of Activity-on-Node (AON) diagrams compared to Activity-on-Arrow (AOA) diagrams?

<p>Possibility to model various types of links between tasks (B)</p>
Signup and view all the answers

What is the main difference between PERT and GERT?

<p>GERT allows loops and conditional branches, while PERT does not (B)</p>
Signup and view all the answers

What is the best graphical tool for timeline display?

<p>Gantt Chart (B)</p>
Signup and view all the answers

In an AON graph, if a(AB)=4 and b(BA)=-5, it means:

<p>B must start no earlier than 5 units after A ends (A)</p>
Signup and view all the answers

Which type of buffer compensates for resource delays in CCPM?

<p>Resource buffer (B)</p>
Signup and view all the answers

In stochastic simulation, task duration is:

<p>Random variable (C)</p>
Signup and view all the answers

Which of the following is a component of the Metra Potential Method?

<p>Determining task dependencies (C)</p>
Signup and view all the answers

What is a primary disadvantage of the Waterfall methodology in dynamic project environments?

<p>Limited ability to respond to changes (D)</p>
Signup and view all the answers

Flashcards

PERT Diagram Type

A diagram that visually represents project activities and their dependencies.

Project Magic Triangle Dimensions

Time, Cost, and Scope representing the constraints in project management.

Theory of Constraints

A management philosophy that focuses on identifying and removing constraints to improve system performance.

Changing Task Work Contour

Modifying the effort distribution of a task over time to resolve resource conflicts.

Signup and view all the flashcards

Independent Slack in CPM

The amount of time an activity can be delayed without impacting other activities; can be negative, positive or zero.

Signup and view all the flashcards

Procrastination Effect

A behavior where tasks are delayed until the last possible moment before a deadline.

Signup and view all the flashcards

Network Graph Properties

A directed graph that is finite, continuous, and acyclic, featuring one start and one end node.

Signup and view all the flashcards

SV Meaning in EVM

Schedule Variance, a measure of schedule performance in earned value management.

Signup and view all the flashcards

Project Buffer in Critical Chain

A time cushion to absorb delays, protecting the project timeline.

Signup and view all the flashcards

BCWS (EV) Meaning

The calculated value of Budgeted Cost of Work Scheduled.

Signup and view all the flashcards

GERT Model Stochastic Node

In GERT, all activities leading to node 2 must be completed for it to be stochastic.

Signup and view all the flashcards

Activity Duration in PERT

Uses a weighted average of pessimistic, optimistic, and most likely durations.

Signup and view all the flashcards

Advantage of AON vs AOA

Ability to model various types of links between tasks.

Signup and view all the flashcards

SPI < 1 Meaning

Project is behind schedule.

Signup and view all the flashcards

PERT vs GERT Difference

GERT allows loops and conditional branches, which PERT does not.

Signup and view all the flashcards

Gantt Chart

A visual timeline showing project activities and their durations.

Signup and view all the flashcards

AON graph a(AB)=4, b(BA)=-5

Activity B must start no earlier than 5 units after activity A ends

Signup and view all the flashcards

Resource buffer

Compensates resource delays in Critical Chain Project Management (CCPM)

Signup and view all the flashcards

Stochastic Simulation

Task duration is a random variable.

Signup and view all the flashcards

Metra Potential Method

Determining task dependencies

Signup and view all the flashcards

Study Notes

  • PERT uses network diagrams.
  • The project magic triangle includes time, cost, and scope.
  • The Critical Chain method is based on the Theory of Constraints.
  • Changing task work contour is effective for resolving resource conflicts.
  • Independent slack in the CPM method can be negative, positive or zero.
  • Student's syndrome relates closely to procrastination within the Critical Chain method.
  • Network graphs are finite, continuous, directed, acyclic with one beginning and one end node
  • Schedule Variance (SV) is a parameter of the earned value analysis.
  • A project buffer in Critical Chain is a time reserve to compensate for possible project delays.
  • The BCWS parameter is 300 000 CZK.
  • For the GERT model, if node number 2 is inclusively stochastic, all activities ending there are finished
  • The activity duration in PERT is calculated using pessimistic, optimistic, and most likely duration estimates
  • AON allows you to model various types of links between tasks compared to AOA.
  • If SPI < 1, the Project is behind schedule.
  • GERT allows loops and conditional branches, while PERT does not.
  • The best graphical tool for timeline display is a Gantt Chart
  • If an AON graph a(AB)=4, b(BA)=-5, then B must start no earlier than 5 units after A ends.
  • A resource buffer compensates for resource delays in CCPM.
  • In stochastic simulation, task duration is a random variable
  • Determining task dependencies is part of the Metra Potential Method
  • Waterfall methodology has limited ability to respond to changes in dynamic environments
  • While resolving resource conflicts, an effective method is to change the task work contour.
  • If AON a(AB)=6, b(BA)=-5, B >= 5 units after A ends.
  • Student's syndrome is closely related to procrastination.

Studying That Suits You

Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

Quiz Team

Related Documents

More Like This

Use Quizgecko on...
Browser
Browser