Podcast
Questions and Answers
What distinguishes PERT from CPM in project management?
What distinguishes PERT from CPM in project management?
- PERT is deterministic, while CPM is probabilistic.
- PERT is better suited for repetitive projects, while CPM handles non-repetitive ones.
- PERT was developed by DuPont, while CPM was created by the U.S. Navy.
- PERT focuses solely on time variables, whereas CPM considers time-cost trade-offs. (correct)
In project network diagrams, what is the primary purpose of a 'dummy activity'?
In project network diagrams, what is the primary purpose of a 'dummy activity'?
- To serve as a buffer for unexpected delays in the critical path.
- To shorten the project duration by overlapping activities.
- To represent activities that consume no time or resources but maintain logical relationships. (correct)
- To indicate activities with uncertain time estimates.
Which statement accurately describes the role of events and activities in project network diagrams:
Which statement accurately describes the role of events and activities in project network diagrams:
- Events represent specific accomplishments at a point in time, while activities consume time and resources. (correct)
- Both events and activities represent tasks that need to be completed, but only activities are depicted with arrows.
- Both events and activities consume time and resources, but events have a duration of zero.
- Events consume time and resources, while activities represent specific accomplishments.
When constructing a project network diagram, what guideline is essential to follow regarding activity representation?
When constructing a project network diagram, what guideline is essential to follow regarding activity representation?
What is the significance of the critical path in project management?
What is the significance of the critical path in project management?
What does 'slack time' refer to in the context of project scheduling?
What does 'slack time' refer to in the context of project scheduling?
In the forward pass calculation, what does the Earliest Expected Time (ET) represent for an event in a project network?
In the forward pass calculation, what does the Earliest Expected Time (ET) represent for an event in a project network?
During the backward pass calculation, how is the Latest Allowable Time (LT) determined for an event?
During the backward pass calculation, how is the Latest Allowable Time (LT) determined for an event?
How do you identify critical events in a project network diagram using ET (Earliest Time) and LT (Latest Time) values?
How do you identify critical events in a project network diagram using ET (Earliest Time) and LT (Latest Time) values?
What is total float in project management, and how is it calculated?
What is total float in project management, and how is it calculated?
Which of the following is the correct formula for calculating Free Float (FF) for an activity (i, j)?
Which of the following is the correct formula for calculating Free Float (FF) for an activity (i, j)?
In PERT, what does the 'optimistic time estimate' (denoted by 'a') represent?
In PERT, what does the 'optimistic time estimate' (denoted by 'a') represent?
What is the correct formula to calculate the expected time ($t_e$) of an activity in PERT when given the optimistic (a), most likely (m), and pessimistic (b) time estimates?
What is the correct formula to calculate the expected time ($t_e$) of an activity in PERT when given the optimistic (a), most likely (m), and pessimistic (b) time estimates?
In PERT analysis, if an activity has time estimates of a = 2, m = 5, and b = 14, what is the calculated variance ($\sigma^2$)?
In PERT analysis, if an activity has time estimates of a = 2, m = 5, and b = 14, what is the calculated variance ($\sigma^2$)?
In PERT, what formula is used to calculate the probability of completing a project by a target date (x)?
In PERT, what formula is used to calculate the probability of completing a project by a target date (x)?
Flashcards
PERT/CPM
PERT/CPM
PERT and CPM are project management techniques used to plan, schedule, and control projects.
Gantt Chart
Gantt Chart
A visual representation of work over time, but lacks the ability to show inter-dependencies between activities effectively.
Network Analysis
Network Analysis
A method using network systems to graphically represent projects, showing relationships between activities and events.
Activity
Activity
Signup and view all the flashcards
Event
Event
Signup and view all the flashcards
Predecessor Activity
Predecessor Activity
Signup and view all the flashcards
Successor Activity
Successor Activity
Signup and view all the flashcards
Concurrent Activity
Concurrent Activity
Signup and view all the flashcards
Dummy Activity
Dummy Activity
Signup and view all the flashcards
Critical Path
Critical Path
Signup and view all the flashcards
Earliest Expected Time (ET)
Earliest Expected Time (ET)
Signup and view all the flashcards
Latest Allowable Time (LT)
Latest Allowable Time (LT)
Signup and view all the flashcards
Total Float
Total Float
Signup and view all the flashcards
Deterministic Time Estimates
Deterministic Time Estimates
Signup and view all the flashcards
Probabilistic Time Estimates
Probabilistic Time Estimates
Signup and view all the flashcards
Study Notes
Introduction to PERT/CPM
- Program Evaluation and Review Technique (PERT) and Critical Path Method (CPM) are widely used in project management.
- Project management aims for on-time project completion within budget and according to specifications.
- A project is a human endeavor with a clear beginning and end.
- Project managers plan, schedule, and control work, detailing activities, resources, time, and inter-relationships.
- Scheduling involves setting start and end dates for activities.
- Project control requires status updates and trade-off analysis.
- Key project questions include completion time, impact of delays, resource allocation, and completion probability.
- Gantt charts were the popular scheduling technique, developed by Henry L. Gantt around 1900.
- Gantt charts graphically represent work vs. time, but struggle to show inter-dependencies.
- PERT and CPM were introduced in the late 1950s to overcome Gantt chart limitations.
- PERT and CPM were developed independently by the U.S. Navy and DuPont.
- PERT originated from the U.S. Navy's Polaris program; CPM was used in chemical plant construction.
- PERT was initially for research and development, while CPM was for construction.
- Both PERT and CPM use a critical path and network analysis to control critical activities for on-time completion.
- PERT suits non-repetitive, complex projects with uncertain time estimates.
- CPM is better for repetitive, non-complex projects with reliable time estimates.
- Technique selection depends on the certainty of time estimates and the consequences of delays.
- PERT focuses on time, whereas CPM includes time-cost trade-offs.
Network Analysis
- Network systems are fundamental to PERT and CPM.
- Networks graphically represent problems or proposed projects.
- Activity represents tasks requiring time and resources, depicted as arrows (arcs).
- Arrow length is for clarity, not time representation; arrowheads indicate flow.
- Activities cannot start before preceding activities finish.
- Clearly defined activities have identifiable start and end points.
- Events mark specific project accomplishments at a point in time, consuming no resources.
- Events are typically represented by circles (nodes).
- Events signify the end of one activity and the start of another.
- Activities represent the passage of time, whereas events are points in time.
- Activity arrows begin and end with event nodes.
- Predecessor activities must be completed before another activity starts.
- Successor activities cannot start until other activities finish.
- Concurrent activities can be done simultaneously.
- Activities can be predecessors, successors, or concurrent.
- Dummy activities address concurrent activities with the same start and end events, consuming no resources or time.
- Dummy activities are represented by dashed arrows.
- Dummy activities makes activities with common starting and finishing events distinguishable.
Guidelines for Constructing Network Diagrams
- Each activity has one arrow in the network.
- No two activities share the same beginning and end events; dummy activities are used to resolve such conflicts.
- Events are numbered so that higher numbers follow lower numbers.
- Dangling, which improperly identifies precedence and inter-relationships, must be avoided in network diagrams.
- Logical sequence and inter-relationships are ensured by answering questions about preceding, following, and concurrent activities.
Deterministic Time Estimates
- PERT/CPM analysis depends on whether activity time estimates are deterministic or probabilistic.
- Deterministic estimates are reliable, with minimal deviation.
- Probabilistic estimates vary, acknowledges these uncertainties.
- Network analysis is initially described with deterministic time estimates and, later, with probabilistic ones.
Developing a Project Network
- PERT/CPM networks contain activities and events.
- Networks illustrate activity sequence and relationships.
- Example: Activities A and B start immediately with no predecessors from event 1.
- Activity G has two predecessors, D and E, satisfying all relationships.
Project Duration and Critical Path
- The longest path in the network is the critical path, determining project duration.
- Delays on the critical path delay the entire project.
- Networks have at least one critical path, and sometimes multiple.
- Project duration and critical path can be identified.
- The critical path can be found by enumerating completion times.
- Activities on the critical path are critical, and cause overall project delays.
- Slack time defines how long an activity can be delayed.
Forward Pass (Earliest Expected Time)
- The forward pass calculates the earliest time an event can occur.
- The calculation depends on the latest completion time of activities ending at that event.
- The longest path is the earliest expected time for the event to occur.
Backward Pass (Latest Allowable Time)
- The backward pass calculates the latest time an event can be delayed.
- The time will not delay project completion.
- These calculations start from the end event, proceeding backward.
- The value for event is calculated by subtracting the duration times of all activities coming into the event.
Float
- Float is the time available for an activity beyond its duration, important for managers.
- As the start and end events of an activity have earliest and latest times, an activity has four associated times.
Probabilistic Time Estimates
- Activity times are often random variables, making PERT effective.
- PERT assumes activity times are statistically independent.
- Total activity times are normally distributed.
- Three time estimates can be obtained for each activity: optimistic (a), most likely (m), and pessimistic (b).
- The mean duration time (te) and variance (σ²) can be computed with those three time estimates.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.