Podcast
Questions and Answers
For buildings with occupants, the number of persons to be served shall be computed based on the number of rooms and considering each room as occupied by two persons or on the basis of the actual number of persons served by the tank, whichever is the ______
For buildings with occupants, the number of persons to be served shall be computed based on the number of rooms and considering each room as occupied by two persons or on the basis of the actual number of persons served by the tank, whichever is the ______
greater
If 2 or more compartments are used, the first compartment shall have the capacity from one half to two thirds of the total volume of the ______
If 2 or more compartments are used, the first compartment shall have the capacity from one half to two thirds of the total volume of the ______
tank
The septic tank shall have a liquid drawing depth not less than 1.20 meters {4 ______)
The septic tank shall have a liquid drawing depth not less than 1.20 meters {4 ______)
feet
The vertical distance from the liquid level to the inside top of the tank shall be ______
The vertical distance from the liquid level to the inside top of the tank shall be ______
Signup and view all the answers
The septic tank shall be located not less than 25 meters from any well, spring, cistern, or other sources of drinking water supply; not less than 1.5 m.(5 ft.) from any water service line; and not less than 3.0 m.(10 ft.) away from water ______
The septic tank shall be located not less than 25 meters from any well, spring, cistern, or other sources of drinking water supply; not less than 1.5 m.(5 ft.) from any water service line; and not less than 3.0 m.(10 ft.) away from water ______
Signup and view all the answers
Match the following with their respective components of Detailed Engineering as a Prerequisite to Bidding:
Match the following with their respective components of Detailed Engineering as a Prerequisite to Bidding:
Signup and view all the answers
Match the following with their associated activities in Detailed Engineering as a Prerequisite to Bidding:
Match the following with their associated activities in Detailed Engineering as a Prerequisite to Bidding:
Signup and view all the answers
Connect the following tasks to their roles in Detailed Engineering as a Prerequisite to Bidding:
Connect the following tasks to their roles in Detailed Engineering as a Prerequisite to Bidding:
Signup and view all the answers
Match the following steps with their involvement in Detailed Engineering as a Prerequisite to Bidding:
Match the following steps with their involvement in Detailed Engineering as a Prerequisite to Bidding:
Signup and view all the answers
Match the following tasks with their contributions in Detailed Engineering as a Prerequisite to Bidding:
Match the following tasks with their contributions in Detailed Engineering as a Prerequisite to Bidding:
Signup and view all the answers
Match the following sections of the Bidding Documents with their content:
Match the following sections of the Bidding Documents with their content:
Signup and view all the answers
Match the following parts of the Bids and Awards Committee (BAC) with their functions:
Match the following parts of the Bids and Awards Committee (BAC) with their functions:
Signup and view all the answers
Match the following steps in the procurement process with their descriptions:
Match the following steps in the procurement process with their descriptions:
Signup and view all the answers
Match the following contract plans with their purposes:
Match the following contract plans with their purposes:
Signup and view all the answers
Match the following sections VOLUME III - DPWH Manual of Procedures for the Procurement with their contents:
Match the following sections VOLUME III - DPWH Manual of Procedures for the Procurement with their contents:
Signup and view all the answers
Study Notes
Procurement Planning
- Procurement activities are planned in advance, consistent with the approved budget and target dates of implementation.
Detailed Engineering
- Detailed engineering is a pre-requisite to bidding and is initiated by the Procuring Entity.
- Scope includes:
- Setting of design standards
- Conduct of field surveys and investigation
- Conduct of design analyses and preparation of design plan and design report
- Preparation of contract plans
- Preparation of technical specifications
- Preparation of quantity estimates
- Preparation of cost estimates and approved budget for the contract
- Preparation of program of work including schedule
- Determination of contract packages
- Preparation of site or right-of-way (ROW) plans, schedule of acquisition, and resettlement action plans
- Preparation of utilities relocation plan
- Preparation of environmental impact statement
- Preparation of minimum requirements for a construction safety and health program
- Conduct of value engineering studies
- Contract time or duration
- Warranty period
Bidding Documents
- Contents of bidding documents include:
- Invitation to Apply for Eligibility and to Bid (IAEB)
- Eligibility Requirements
- Instruction to Bidders (ITB)
- Bid Data Sheet (BDS)
- General Conditions of the Contract (GCC)
- Special Conditions of the Contract (SCC)
- Specifications
- Drawings
- Bill of Quantities (BOQ)
- Forms
Contract Award
- The contract shall be awarded to the bidder with the Lowest Calculated Responsive Bid (LCRB).
- The Procurement Entity shall notify the winning bidder in writing that its bid has been accepted, through Notice of Award (NOA).
Contract Effectivity
- The contract is effective on the date indicated in the Notice to Proceed (NTP).
- NTP must be issued with a copy of the approved contract, within three (3) calendar days from the date of the approval of the Contract.
Organizational Structure
- Office of the Provincial Engineer
- Planning Division
- Construction Division
- Maintenance Department
- Quality Control Section
- Administrative Support Staff
- Provincial Government Department Head
- Provincial Engineer (SG 26)
Quality Control Section
- Engineer III
- Laboratory Technician II
- Engineering Assistant I (SG 19)
- Engineer IV (SG 22)
- Administrative Aide IV (Clerk II)
Maintenance Division
- Engineer III
- Engineer II
- Engineer I
- Draftsman
- Administrative Aide IV (Clerk II)
Construction Division
- Engineer II
- Engineer I
- Engg Assistant I
- Administrative Aide IV (Clerk II)
Field Operation Section
- Vertical Structure Section
- Engineer III
- Engineer II
- Engineer I
- Draftsman
- Horizontal Structure Section
- Engineer II
- Engineer I
- Engg Assistant I
Other Notes
- Presidential Decree no. 856 (PD 856) Chapter XVII: Sewage Collection and Disposal, Excreta Disposal and Drainage.
- Section 1: Scope of PD 856 applies to all public and private sewage and excreta collection and disposal system projects.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Description
Test your knowledge on procurement planning in infrastructure projects, focusing on activities planned in advance, approved budgets, target dates, and the purpose and scope of procurement planning. This quiz also covers detailed engineering requirements before bidding can take place.