MERALCO Electrical Design Standards Quiz
19 Questions
0 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

What is the required height for accessing a transformer on the 2nd floor when hoisting?

  • 2m measured from the top of the transformer
  • 3m measured from the floor to the bottom of the I-beam
  • 3m measured from the bottom of the concrete
  • 4m measured from the bottom of the I-beam to the floor (correct)
  • For a two-bank padmount transformer vault located on the ground floor, what are the minimum dimensions?

  • 8m X 4m
  • 8m X 6m (correct)
  • 5m X 4m
  • 6m X 6m
  • Which of the following is NOT a requirement for the customer vault layout?

  • Minimum headroom must be maintained according to the specifications
  • Access door must be encased in concrete
  • Transformer dimensions must be clearly marked (correct)
  • Access door must be directly accessible from outside the building
  • What is the minimum depth required for a one-bank deadfront distribution transformer vault on the ground floor?

    <p>5m</p> Signup and view all the answers

    What is the minimum depth requirement for a two-bank transformer vault located on the 1st basement floor?

    <p>3m</p> Signup and view all the answers

    What is the preferred minimum road width for vault accessibility?

    <p>6.5 meters</p> Signup and view all the answers

    Which of the following is NOT a requirement for standard vault specifications?

    <p>Openings to the building interior</p> Signup and view all the answers

    What type of transformers are available for vault installation with a secondary voltage of 240Y/139 V?

    <p>Three-phase, 34.5 GrdY/20 kV transformers</p> Signup and view all the answers

    What is the minimum size requirement for ducts in accordance with PNS 14?

    <p>110 mm in diameter</p> Signup and view all the answers

    Which of the following is an incorrect specification regarding the transformer vault location?

    <p>Vaults may be located in an inner section of the building.</p> Signup and view all the answers

    What safety measure is mandated for transformers regarding liquid confinement?

    <p>A door sill of 150 mm</p> Signup and view all the answers

    What is the primary function of a loop sectionalizing switch in transformers?

    <p>To allow for maintenance and safety isolation</p> Signup and view all the answers

    Which of the following characteristics pertains to deadfront primary transformers?

    <p>Protection features like fuses</p> Signup and view all the answers

    What is the recommended cooling capacity for the recommended exhaust fan in a transformer vault?

    <p>2500 CFM</p> Signup and view all the answers

    Which of the following statements is true about primary and secondary cables in service voltages?

    <p>Primary cables operate at voltages up to 34.5 kV.</p> Signup and view all the answers

    What is a common requirement for overhead lines according to the standards?

    <p>Require surge arresters</p> Signup and view all the answers

    What must be included in cable termination for both overhead and underground systems?

    <p>Permanent connections</p> Signup and view all the answers

    What is the maximum kVA capacity for three-phase transformers with a 240Y/139-V secondary?

    <p>1000 kVA</p> Signup and view all the answers

    Which feature distinguishes Meralco-supplied Deadfront Distribution Transformers?

    <p>Round tank construction</p> Signup and view all the answers

    Study Notes

    MERALCO Standards: Electrical Design

    • Standards for electrical design are outlined in MERALCO's Power Up Forum Series.
    • Electrical Design Team, led by Engr. Eduard Mercado, develops these standards.

    Service Voltages

    • Secondary metering: 240V, 400V, 460V
    • Primary metering: 34.5kV, 13.8kV (in Cavite & Bulacan), 115kV (subtransmission)

    Facilities

    • Overhead: Pole-mounted transformers, padmount transformers, vault-type distribution transformers (DT)
    • Underground: Padmount transformers, vault-type DT

    Single Line Diagrams

    • Diagrams illustrate electrical connections for overhead and underground lines feeding a transformer vault.
    • Key components shown: surge arresters, fuse cutouts/power fuses, cable terminations, primary underground cables, padmounted transformers, secondary cables, current transformers (CTs), and metering devices (often including an elbow arrester and transformer vault).
    • Civil works, such as concrete-encased PVC ducts, are to be provided by the applicant/customer.

    Transformers for Vault Installation

    • Meralco-Supplied Padmounted Transformers: Three-phase, 34.5GrdY/20kV, or 13.2GrdY/7.62kV. Secondary voltages available are 240Y/139-V (75-1000kVA), 480Y/277-V (500-2000kVA), and 416Y/240-V (500-1000kVA).
    • Meralco-Supplied Deadfront Distribution Transformers: Single-phase, 34.5GrdY/20kV, or 13.2GrdY/7.62kV. Available in 167–333kVA.
    • Deadfront primary: Features prominent front for access.
    • Round tank construction: Design of the tank housing the transformer.
    • Less flammable liquid filled: Liquid used in the transformer to cool it, is less flammable.
    • Completely self-protected with fuses: Transformers have internal protection systems integrated with fuses.
    • Provided with loop sectionalizing switch: Additional safety feature for isolating sections of the circuit.

    Standard Vault Location

    • Preferred: Ground floor; second floor (for DT/padmount XF with hoisting facilities), First basement (for buildings with multiple basements).
    • Perimeter Location: Vault should be on the building perimeter, near streets/roadways, to access by Meralco trucks/cranes.
    • Minimum Road Width: 6.5 meters

    Standard Vault Specifications/Requirements

    • Walls and roof: Reinforced concrete, minimum thickness 150mm

    • No openings: Vault should have no openings to the building interior.

    • Doorsil: 150mm doorsil required for liquid confinement.

    • Ventilation: Adequate and permanent ventilation (exhaust fan) with rated capacity of 3/4 HP with 71 cubic meters per minute (2500 CFM).

    • Clear headroom: 4 meters (minimum) between the bottom of the I-beam and the top of the vault, with 30° sling angle (for hoisting facilities).

    • Ducts: Primary/secondary ducts, diameter 110mm, thick-walled, red-orange, unplasticized polyvinyl chloride (UPVC), adhering to PNS 14, concrete-encased.

    • Personnel access pathway: Direct access from outside the building.

    Customer Vault Layouts

    • Specifications for 1-bank and 2-bank padmount transformers in vaults for ground, 2nd floor and 1st basement locations, with minimum dimensions.
    • Vertical clearances are critical for installing/removing transformers.

    Primary Metering

    • Pole metering structure, follow standards drawing CODE: P-MN03U
    • Materials, equipment, and labor to be provided by customer.
    • Components involved.
    • Diagrams for both overhead (OH) and underground (UG) primary metering layouts.

    3 Way RMU with Metering Module

    • Diagrams showing different vault layouts

    Studying That Suits You

    Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

    Quiz Team

    Related Documents

    Description

    Explore the standards outlined by MERALCO for electrical design in this quiz. Delve into service voltages, facilities, and single line diagrams as established by Engr. Eduard Mercado. Test your knowledge on critical components and their specifications in electrical infrastructure.

    More Like This

    CAD Standards in Electrical Design Quiz
    12 questions
    Electrical Reticulation for Mining Design
    16 questions
    Electrical Systems Design Fundamentals
    15 questions
    Use Quizgecko on...
    Browser
    Browser