5 Questions
In the PMBOK v5 methodology, what are the two most important documents for describing a project during the initiation and planning phases?
Project charter and project management plan
According to the PMBOK, what is the primary purpose of a project plan?
To guide project execution and control
In the PMBOK v6, what term is used to refer to the contract that the project sponsor and project manager use to agree on the initial vision of the project?
Project charter
According to PRINCE2, how does it define a project plan?
A statement of how and when a project's objectives are to be achieved
According to the PMBOK, can a project plan be summarized or detailed?
Yes, a project plan may be summarized or detailed
Test your knowledge on project planning with this quiz! Learn about the key elements of a project plan, its purpose, and how it guides project execution and control. This quiz will cover topics such as planning assumptions, communication with stakeholders, and documenting scope, cost, and schedule baselines. Challenge yourself and see how well you understand project planning according to the PMBOK!