Who is responsible for granting the Location Clearance for Integrated Township Projects?
Who is responsible for granting the Location Clearance for Integrated Township Projects?
- Collector
- MHADA
- Divisional Commissioner
- State Government in consultation with HPC (correct)
What is the maximum duration allowed for issuing Location Clearance?
What is the maximum duration allowed for issuing Location Clearance?
- 60 days
- 120 days
- 90 days (correct)
- 30 days
If a Letter of Intent (LOI) is not applied for, how long is the Location Clearance valid?
If a Letter of Intent (LOI) is not applied for, how long is the Location Clearance valid?
- 3 years
- 2 years (correct)
- 1 year
- 5 years
Who has the authority to extend Location Clearance, and for what aggregate duration?
Who has the authority to extend Location Clearance, and for what aggregate duration?
Which authority issues the Letter of Intent (LOI)?
Which authority issues the Letter of Intent (LOI)?
What is the time limit for the Collector to issue the LOI?
What is the time limit for the Collector to issue the LOI?
What is the standard validity period for a Letter of Intent (LOI)?
What is the standard validity period for a Letter of Intent (LOI)?
Who is authorized to renew the LOI, and for what duration?
Who is authorized to renew the LOI, and for what duration?
Which entity approves the Master Layout Plan for an Integrated Township Project?
Which entity approves the Master Layout Plan for an Integrated Township Project?
What is the time limit for forwarding the Master Layout Plan to the JDTP?
What is the time limit for forwarding the Master Layout Plan to the JDTP?
How much time is allotted for JDTP compliance?
How much time is allotted for JDTP compliance?
What is the procedure if a JDTP is already stationed within the Authority’s office?
What is the procedure if a JDTP is already stationed within the Authority’s office?
How long should the approval of a Building Plan take by a branch office or authority?
How long should the approval of a Building Plan take by a branch office or authority?
Which authority is responsible for issuing the Occupancy Certificate to buildings?
Which authority is responsible for issuing the Occupancy Certificate to buildings?
What is the specified time limit for issuing an Occupancy Certificate to buildings?
What is the specified time limit for issuing an Occupancy Certificate to buildings?
Flashcards
Who grants Location Clearance for ITPs?
Who grants Location Clearance for ITPs?
The State Government, in consultation with the HPC, grants location clearance for ITPs.
Maximum time to issue Location Clearance?
Maximum time to issue Location Clearance?
The maximum time allowed to issue Location Clearance is 90 days.
Validity of Location Clearance (no LOI)?
Validity of Location Clearance (no LOI)?
Location Clearance is valid for 2 years if a Letter of Intent (LOI) is not applied for.
Who extends Location Clearance?
Who extends Location Clearance?
Signup and view all the flashcards
Who issues the Letter of Intent (LOI)?
Who issues the Letter of Intent (LOI)?
Signup and view all the flashcards
Time limit for Collector to issue LOI?
Time limit for Collector to issue LOI?
Signup and view all the flashcards
Validity of LOI?
Validity of LOI?
Signup and view all the flashcards
Who renews the LOI?
Who renews the LOI?
Signup and view all the flashcards
Who approves Master Layout Plan?
Who approves Master Layout Plan?
Signup and view all the flashcards
Time to forward plan to JDTP?
Time to forward plan to JDTP?
Signup and view all the flashcards
Time for JDTP compliance?
Time for JDTP compliance?
Signup and view all the flashcards
JDTP within Authority's office?
JDTP within Authority's office?
Signup and view all the flashcards
Building Plan approval time?
Building Plan approval time?
Signup and view all the flashcards
Who issues Occupancy Certificate?
Who issues Occupancy Certificate?
Signup and view all the flashcards
Time limit for Occupancy Certificate?
Time limit for Occupancy Certificate?
Signup and view all the flashcards
Study Notes
- These questions are about Activities & Timelines for Integrated Township Projects (ITP) under UDCPR.
Location Clearance
- The State Government, after consulting with the HPC (High Powered Committee), grants location clearance for ITPs.
- The maximum time allowed to issue Location Clearance is 90 days.
- Location Clearance is valid for 2 years if a Letter of Intent (LOI) is not applied for.
- The Deputy Director of Town Planning can extend Location Clearance for up to 2 years in aggregate.
Letter of Intent (LOI)
- The Collector issues the Letter of Intent (LOI).
- The time limit for the Collector to issue an LOI is 45 days.
- The validity of the LOI is 2 years.
- The Collector can renew the LOI for 2 years.
Master Layout Plan
- The Collector/Authority, after consulting with the JDTP (Joint Director of Town Planning), approves the Master Layout Plan for an ITP.
- There is a 10 day time limit for forwarding the plan to JDTP.
- JDTP compliance is given 1 month.
- There is no need to refer to Divisional JDTP if JDTP is already posted within the Authority’s office.
Building Plan and Occupancy Certificate
- Approval of the Building Plan by a branch office or authority should be completed in 30 days.
- The Assistant Director of Town Planning / Authority issues the Occupancy Certificate to buildings.
- The time limit to issue an Occupancy Certificate to buildings is 30 days.