According to the text, disputes arising from the interpretation, application, or administration of the contract shall be settled through

  • amicable negotiations
  • the courts
  • mediation or arbitration (correct)
  • any other agreed form of dispute resolution

According to the text, if the parties do not agree to mediation or arbitration, they may refer the unresolved dispute to

  • amicable negotiations
  • no resolution is possible
  • any other agreed form of dispute resolution (correct)
  • the courts

According to the text, the Owner is responsible for obtaining and maintaining general liability insurance with limits of

  • $5,000,000 per occurrence
  • $15,000,000 per occurrence
  • $1,000,000 per occurrence
  • $10,000,000 per occurrence (correct)

According to the text, the deductible for the general liability insurance should not exceed

<p>$15,000 (C)</p> Signup and view all the answers

According to the text, what is the minimum deductible for the 'Broad Form' property insurance policy?

<p>$10,000 (A)</p> Signup and view all the answers

According to the text, how long should the liability coverage be provided for completed operations hazards following the Project In-Use Date?

<p>6 years (D)</p> Signup and view all the answers

According to the text, what is the minimum limit per occurrence for bodily injury, death, and damage to property under the Aircraft or Watercraft Liability Insurance policy?

<p>$10,000,000 (C)</p> Signup and view all the answers

According to the text, who is responsible for providing, maintaining, and paying for general liability insurance with limits of not less than $5,000,000 per occurrence?

<p>The Construction Manager (A)</p> Signup and view all the answers

According to GC 9.2 - WAIVER OF CLAIMS, what must be included in a claim to preserve a right of action?

<p>All of the above (D)</p> Signup and view all the answers

When should the party giving Notice in Writing of a claim submit a detailed account of the amount claimed?

<p>Within a reasonable time (B)</p> Signup and view all the answers

What is the consequence if a Notice in Writing of claim pursuant to paragraph 9.2.1.1 is received on the 18th or 19th calendar day after the Project In-Use Date?

<p>The period within which Notice in Writing of claim pursuant to paragraph 9.2.1.1 shall be extended (B)</p> Signup and view all the answers

If the event giving rise to a claim has a continuing effect, what should the party making the claim do?

<p>Submit further interim accounts at reasonable intervals (C)</p> Signup and view all the answers

Which party waives and releases the other party from all claims arising from their involvement in the project?

<p>The Owner (A)</p> Signup and view all the answers

What types of claims are waived and released by the Construction Manager against the Owner, except for certain exceptions?

<p>Claims resulting from acts or omissions which occur prior to or on the Project In-Use Date (A)</p> Signup and view all the answers

Which claims are not waived and released by the Construction Manager against the Owner?

<p>Claims referred to in paragraph 9.2.1.2 (C)</p> Signup and view all the answers

What is the time period within which the Owner can make claims against the Construction Manager, except for certain exceptions?

<p>Six years from the Project In-Use Date (A)</p> Signup and view all the answers

What is the time period within which a claim for indemnification must be made under this Contract?

<p>Within 6 years from the date of Project In-Use Date (A)</p> Signup and view all the answers

What is the limit of indemnity for losses suffered by the Owner and the Construction Manager for which insurance is to be provided by either party pursuant to GC 8.1 – INSURANCE?

<p>The insurance limit for the loss so covered as prescribed in GC 8.1 – INSURANCE (C)</p> Signup and view all the answers

What is the limit of indemnity for losses suffered by the Owner and the Construction Manager for which insurance is not required to be provided by either party in accordance with GC 8.1 – INSURANCE?

<p>The Construction Manager’s compensation as recorded in Article A-5 of the Agreement – COMPENSATION FOR SERVICES (A)</p> Signup and view all the answers

What is the obligation of either party to indemnify the other in respect to claims by third parties for direct loss resulting from bodily injury, sickness, disease or death, or to injury to or destruction of tangible property?

<p>Without limit (B)</p> Signup and view all the answers

More Like This

CCDC 3 -2016 Part 1
30 questions

CCDC 3 -2016 Part 1

UndisputedGrace avatar
UndisputedGrace
CCDC 3 -2016 Part 5
25 questions

CCDC 3 -2016 Part 5

UndisputedGrace avatar
UndisputedGrace
CCDC 5A Part 1
30 questions

CCDC 5A Part 1

UndisputedGrace avatar
UndisputedGrace
Use Quizgecko on...
Browser
Browser