CCDC 3 -2016 Part 5
25 Questions
3 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

Who is responsible for paying customs, taxes, and duties during the performance of the work?

  • The Place of the Work
  • The Owner
  • The Contract Documents
  • The Contractor (correct)
  • Who is responsible for obtaining and paying for development approvals, building permit, and other necessary approvals and permits?

  • The Contractor
  • The Place of the Work
  • The Owner (correct)
  • The Contract Documents
  • Who is responsible for the procurement of permits, licenses, inspections, and certificates necessary for the performance of the work?

  • The Contract Documents
  • The Contractor (correct)
  • The Place of the Work
  • The Owner
  • Who is responsible for verifying that the Contract Documents are in compliance with the applicable laws, ordinances, rules, regulations, or codes relating to the Work?

    <p>The Owner</p> Signup and view all the answers

    Who is responsible for making changes to the Contract Documents if there are variances or changes in applicable laws?

    <p>The Contractor</p> Signup and view all the answers

    What happens if the Contractor fails to advise the Consultant in writing and perform work knowing it to be contrary to any laws, ordinances, rules, regulations, or codes?

    <p>The Contractor will be responsible for correcting the violations and bearing the costs</p> Signup and view all the answers

    Who is responsible for paying the royalties and patent license fees required for the performance of the Contract?

    <p>The Contractor</p> Signup and view all the answers

    Who is responsible for providing evidence of compliance with workers' compensation legislation at the Place of the Work?

    <p>The Contractor</p> Signup and view all the answers

    Which type of insurance coverage is required for completed operations hazards?

    <p>Broad form property insurance</p> Signup and view all the answers

    When should the Broad form property insurance be provided?

    <p>From the date of Substantial Performance of the Work until the commencement of use or occupancy of any part or section of the Work</p> Signup and view all the answers

    Which parties should be included as insureds in the Broad form property and boiler and machinery policies?

    <p>All Subcontractors</p> Signup and view all the answers

    How long should Contractors' Equipment Insurance be provided?

    <p>From the date of commencement of the Work until 1 year after Substantial Performance of the Work</p> Signup and view all the answers

    Which document must contain a CCDC 3 copyright seal to avoid copyright infringement?

    <p>CCDC 3 document</p> Signup and view all the answers

    Who is responsible for indemnifying and holding harmless the Owner from claims arising from the Subcontractor's performance?

    <p>Contractor</p> Signup and view all the answers

    What is the timeframe for giving Notice in Writing of a claim for indemnity or to be held harmless?

    <p>Within the sixth calendar day before the expiry of the lien period</p> Signup and view all the answers

    What claims are waived and released by the Contractor as of the fifth calendar day before the expiry of the lien period?

    <p>Only claims for acts or omissions which occur after the date of Substantial Performance of the Work</p> Signup and view all the answers

    When must the Contractor receive Notice in Writing of a claim from the Owner?

    <p>No later than the sixth calendar day before the expiry of the lien period</p> Signup and view all the answers

    When can the Owner assert a right of indemnification against the Contractor for claims advanced by third parties?

    <p>Only if the claims arise prior to Substantial Performance</p> Signup and view all the answers

    When can the Owner assert a right of indemnity against the Contractor?

    <p>Only if the Owner receives Notice in Writing of the claims</p> Signup and view all the answers

    What type of damages can arise from the Contractor's actions?

    <p>Damages resulting in substantial defects or deficiencies</p> Signup and view all the answers

    When must the Owner receive Notice in Writing of a claim from the Contractor?

    <p>On the date of Substantial Performance</p> Signup and view all the answers

    Which type of insurance policies are required for the Work?

    <p>Policies with insurers licensed to underwrite insurance in the jurisdiction of the Place of the Work</p> Signup and view all the answers

    Under what circumstances can the Owner request increased insurance coverage from the Contractor?

    <p>If a revised version of CCDC 41 – INSURANCE REQUIREMENTS is published, which specifies increased insurance requirements</p> Signup and view all the answers

    Can a Change Directive be used to change the insurance requirements in response to the revision of CCDC 41 – INSURANCE REQUIREMENTS?

    <p>No</p> Signup and view all the answers

    What is the maximum limit of indemnity for losses suffered by the Owner and the Contractor for which insurance is not required to be provided by either party?

    <p>The greater of the Contract Price or $2,000,000, but in no event greater than $20,000,000</p> Signup and view all the answers

    More Like This

    Mastering Construction Contracts
    11 questions
    Standard Form Construction Contracts Quiz
    10 questions
    Construction Contracts Overview
    40 questions
    Use Quizgecko on...
    Browser
    Browser