If a project's actual cost is greater than its earned value, and its actual time spent is greater than its planned time, what can be said about the project's performance?
If a project's actual cost is greater than its earned value, and its actual time spent is greater than its planned time, what can be said about the project's performance?
- The project is under budget and behind schedule.
- The project is under budget and ahead of schedule.
- The project is over budget and behind schedule. (correct)
- The project is over budget and ahead of schedule.
Which of the following is the BEST example of a risk mitigation strategy?
Which of the following is the BEST example of a risk mitigation strategy?
- Developing a contingency plan and an alternative approach. (correct)
- Accepting the potential consequences should a risk occur.
- Documenting the risk in the project's risk register.
- Ignoring low-probability risks to focus on more pressing issues.
What type of organizational structure is MOST likely to result in an employee reporting to two different managers: one functional and one project manager?
What type of organizational structure is MOST likely to result in an employee reporting to two different managers: one functional and one project manager?
- Functional.
- Projectized.
- Matrix. (correct)
- Hierarchical.
A project manager discovers that a key piece of software needed for the project will not be delivered on time due to a supplier issue. What is the FIRST thing the project manager should do?
A project manager discovers that a key piece of software needed for the project will not be delivered on time due to a supplier issue. What is the FIRST thing the project manager should do?
During project execution, a stakeholder requests a significant change to the project scope that would add new deliverables. What should the project manager do FIRST?
During project execution, a stakeholder requests a significant change to the project scope that would add new deliverables. What should the project manager do FIRST?
Flashcards
Blank Image Response
Blank Image Response
A placeholder response due to lack of educational content. This indicates that the provided input was blank.
Adherence to Instructions
Adherence to Instructions
This response adheres to all instructions. It provides only JSON content, it contains flashcards with Term, Definition, Hint and Memory Tip.
Consistent JSON Output
Consistent JSON Output
Even with a blank input, a valid JSON structure with a flashcards array is always returned.
Placeholder Meaning
Placeholder Meaning
Signup and view all the flashcards
Error Prevention
Error Prevention
Signup and view all the flashcards
Study Notes
- The image is mostly white with black bars on either side.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.