R 99 - 3
30 Questions
1 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

According to the text, who is responsible for setting out the Works in relation to original points, lines, and levels of reference specified in the Contract or notified by the Engineer?

  • The Employer
  • An experienced contractor
  • The Engineer
  • The Contractor (correct)
  • If the Contractor suffers delay and/or incurs Cost from executing work necessitated by an error in the items of reference, who should the Contractor give notice to?

  • The Engineer (correct)
  • The Project Manager
  • The Employer
  • The Architect
  • In case of delay in completion due to errors in the specified items of reference, what is the Contractor entitled to, according to SubClause 20.1 [Contractor’s Claims]?

  • No entitlement
  • An extension of time and payment of any Cost plus reasonable profit (correct)
  • Payment of any Cost plus reasonable profit only
  • An extension of time only
  • Who is responsible for any errors in the specified or notified items of reference?

    <p>The Employer</p> Signup and view all the answers

    What should the Contractor use reasonable efforts to verify before they are used?

    <p>The accuracy of specified or notified items of reference</p> Signup and view all the answers

    If completion is or will be delayed due to errors in the specified items of reference, what should the Engineer do after receiving notice from the Contractor?

    <p>Proceed in accordance with SubClause 3</p> Signup and view all the answers

    What should the Contractor do if an experienced contractor could not reasonably have discovered an error in the items of reference and avoided delay and/or Cost?

    <p>Give notice to the Engineer</p> Signup and view all the answers

    According to the text, who is responsible for the Employer's Equipment when the Contractor's Personnel is operating it?

    <p>The Contractor</p> Signup and view all the answers

    How often should progress reports be submitted by the Contractor, according to the text?

    <p>Monthly</p> Signup and view all the answers

    Who determines the appropriate quantities and amounts due for the use of Employer’s Equipment, as per the text?

    <p>The Engineer</p> Signup and view all the answers

    When should the first progress report cover, as per the text?

    <p>The first month following the Commencement Date</p> Signup and view all the answers

    Who is responsible for providing 'free-issue materials' according to the text?

    <p>The Employer</p> Signup and view all the answers

    What should the progress reports include, as per the text?

    <p>Charts and detailed descriptions of progress, photographs showing the status of manufacture, and copies of quality assurance documents</p> Signup and view all the answers

    Who must pay the amounts determined by the Engineer for the use of Employer’s Equipment, based on the text?

    <p>The Contractor</p> Signup and view all the answers

    When should the reporting continue, according to the text?

    <p>Until the Contractor has completed all work</p> Signup and view all the answers

    Who is responsible for rectifying any shortage, defect or default in the free-issue materials, unless otherwise agreed by both Parties?

    <p>The Employer</p> Signup and view all the answers

    According to the FIDIC General Conditions of Contract, who is responsible for the transport of goods to the Site?

    <p>The Contractor</p> Signup and view all the answers

    In the FIDIC General Conditions of Contract, who is responsible for the provision of power, water, and other services at the Site?

    <p>The Contractor</p> Signup and view all the answers

    According to the FIDIC General Conditions of Contract, who is responsible for the suitability and maintenance of access routes to the Site?

    <p>The Contractor</p> Signup and view all the answers

    In the FIDIC General Conditions of Contract, who is responsible for special and temporary rights-of-way needed for the Works?

    <p>The Contractor</p> Signup and view all the answers

    According to the FIDIC General Conditions of Contract, who is responsible for the review of physical conditions encountered in similar parts of the Works to determine reductions in Cost?

    <p>The Engineer</p> Signup and view all the answers

    In the FIDIC General Conditions of Contract, who must take steps to protect the environment and limit damage and nuisance resulting from pollution, noise, and other operations?

    <p>The Contractor</p> Signup and view all the answers

    According to the FIDIC General Conditions of Contract, who is responsible for the indemnification of the Employer against damages, losses, and expenses resulting from any interference with the convenience of the public or the access to and use and occupation of roads and footpaths?

    <p>The Contractor</p> Signup and view all the answers

    What is the responsibility of the Contractor regarding unforeseeable physical conditions?

    <p>The Contractor must notify the Engineer if they encounter adverse physical conditions that they consider to be unforeseeable.</p> Signup and view all the answers

    What is the Contractor entitled to if they encounter unforeseeable physical conditions and suffer delay or cost?

    <p>An extension of time and payment of associated costs, subject to the Contractor’s Claims provisions.</p> Signup and view all the answers

    What is the responsibility of the Engineer regarding unforeseeable physical conditions?

    <p>Determining whether the physical conditions were unforeseeable and to what extent, after receiving notice and inspecting or investigating the physical conditions.</p> Signup and view all the answers

    What is the Contractor required to do regarding safety procedures?

    <p>Comply with all safety regulations, take care of persons on site, and provide necessary safety measures such as fencing and lighting.</p> Signup and view all the answers

    What is the responsibility of the Contractor regarding the Accepted Contract Amount?

    <p>The Contractor is deemed to have satisfied themselves with the correctness and sufficiency of the Accepted Contract Amount.</p> Signup and view all the answers

    What is the Contractor's responsibility regarding quality assurance?

    <p>The Contractor is required to institute a quality assurance system to demonstrate compliance with the contract requirements.</p> Signup and view all the answers

    What data must the Employer provide to the Contractor?

    <p>Relevant data on sub-surface and hydrological conditions at the site.</p> Signup and view all the answers

    Study Notes

    Contractor's Obligations and Responsibilities under FIDIC Contract

    • Contractor must comply with all safety regulations, take care of persons on site, and provide necessary safety measures such as fencing and lighting.
    • The Contractor is required to institute a quality assurance system to demonstrate compliance with the contract requirements.
    • The Employer must provide relevant data on sub-surface and hydrological conditions at the site to the Contractor.
    • The Contractor is responsible for interpreting the site data and obtaining necessary information about risks and contingencies that may affect the tender or works.
    • The Contractor is deemed to have satisfied themselves with the correctness and sufficiency of the Accepted Contract Amount.
    • The Contractor is obligated to notify the Engineer if they encounter adverse physical conditions that they consider to be unforeseeable.
    • The Contractor must continue executing the works using proper and reasonable measures for the physical conditions and comply with any instructions from the Engineer.
    • If the Contractor encounters unforeseeable physical conditions and suffers delay or incurs cost, they are entitled to an extension of time and payment of the associated costs, subject to the Contractor’s Claims provisions.
    • The Engineer is responsible for determining whether the physical conditions were unforeseeable and to what extent, after receiving notice and inspecting or investigating the physical conditions.
    • The Engineer must also agree or determine the matters related to the extent of the unforeseeable physical conditions.
    • The Contractor's obligations and responsibilities under the FIDIC Contract encompass safety procedures, quality assurance, interpretation of site data, sufficiency of the Accepted Contract Amount, and unforeseeable physical conditions.
    • The FIDIC Contract outlines the procedures and responsibilities for the Contractor and the Engineer in the event of unforeseeable physical conditions encountered during the execution of the works.

    Studying That Suits You

    Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

    Quiz Team

    Related Documents

    Red 1999-21-84-11-15 PDF

    Description

    Test your knowledge of the Contractor's obligations and responsibilities under the FIDIC Contract with this quiz. Explore key aspects such as safety procedures, quality assurance, interpretation of site data, and handling unforeseeable physical conditions during project execution.

    More Like This

    R 2017 - 8
    37 questions

    R 2017 - 8

    AstoundedHamster avatar
    AstoundedHamster
    Y 99 - 1
    36 questions

    Y 99 - 1

    AstoundedHamster avatar
    AstoundedHamster
    Y 2017 - 1
    33 questions

    Y 2017 - 1

    AstoundedHamster avatar
    AstoundedHamster
    Y 2017 - 2
    35 questions

    Y 2017 - 2

    AstoundedHamster avatar
    AstoundedHamster
    Use Quizgecko on...
    Browser
    Browser