Podcast
Questions and Answers
What should the Contractor do promptly after receiving a Notice under Sub-Clause 8.1?
What should the Contractor do promptly after receiving a Notice under Sub-Clause 8.1?
When does Sub-Clause 1.9 [Errors in the Employer’s Requirements] apply?
When does Sub-Clause 1.9 [Errors in the Employer’s Requirements] apply?
What should the Contractor’s Documents comprise?
What should the Contractor’s Documents comprise?
In what language should the Contractor’s Documents be written?
In what language should the Contractor’s Documents be written?
Signup and view all the answers
When are published standards referenced in the FIDIC Contract applicable?
When are published standards referenced in the FIDIC Contract applicable?
Signup and view all the answers
What should the Contractor do if new standards come into force after the Base Date?
What should the Contractor do if new standards come into force after the Base Date?
Signup and view all the answers
Under what circumstances may the Engineer initiate a Variation?
Under what circumstances may the Engineer initiate a Variation?
Signup and view all the answers
What is the Contractor responsible for regarding the training of Employer's employees?
What is the Contractor responsible for regarding the training of Employer's employees?
Signup and view all the answers
When should Provisional O&M Manuals be submitted?
When should Provisional O&M Manuals be submitted?
Signup and view all the answers
When must Final O&M Manuals be submitted?
When must Final O&M Manuals be submitted?
Signup and view all the answers
What should the format and details of the as-built records and O&M Manuals comply with?
What should the format and details of the as-built records and O&M Manuals comply with?
Signup and view all the answers
What action may the Contractor take if the Engineer fails to give a Notice of resumption of work within 28 days?
What action may the Contractor take if the Engineer fails to give a Notice of resumption of work within 28 days?
Signup and view all the answers
If the suspension affects the whole of the Works, what action may the Contractor take?
If the suspension affects the whole of the Works, what action may the Contractor take?
Signup and view all the answers
What does the Contractor need to provide for the training of Employer's employees?
What does the Contractor need to provide for the training of Employer's employees?
Signup and view all the answers
When should the Contractor maintain complete 'as-built' records of the Works?
When should the Contractor maintain complete 'as-built' records of the Works?
Signup and view all the answers
What is the Contractor's responsibility regarding the submission of as-built records and O&M Manuals?
What is the Contractor's responsibility regarding the submission of as-built records and O&M Manuals?
Signup and view all the answers
What is the time frame for the Contractor to commence the Tests on Completion?
What is the time frame for the Contractor to commence the Tests on Completion?
Signup and view all the answers
When should the Contractor revise the test programme if it does not comply with the Contract?
When should the Contractor revise the test programme if it does not comply with the Contract?
Signup and view all the answers
When can the Contractor commence the Tests on Completion?
When can the Contractor commence the Tests on Completion?
Signup and view all the answers
What should the Contractor do after receiving a Notice from the Engineer to proceed with the suspended work?
What should the Contractor do after receiving a Notice from the Engineer to proceed with the suspended work?
Signup and view all the answers
Who should jointly examine the Works and the Plant and Materials affected by the suspension?
Who should jointly examine the Works and the Plant and Materials affected by the suspension?
Signup and view all the answers
What should the Engineer do in case of any deterioration, loss, damage, or defect in the Works or Plant or Materials during the suspension?
What should the Engineer do in case of any deterioration, loss, damage, or defect in the Works or Plant or Materials during the suspension?
Signup and view all the answers
When should the Contractor make good any deterioration, loss, damage, or defect in the Works?
When should the Contractor make good any deterioration, loss, damage, or defect in the Works?
Signup and view all the answers
When should the Contractor carry out the Tests on Completion?
When should the Contractor carry out the Tests on Completion?
Signup and view all the answers
Who is responsible for preparing all Contractor’s Documents necessary for the design and execution of the Works?
Who is responsible for preparing all Contractor’s Documents necessary for the design and execution of the Works?
Signup and view all the answers
What is the maximum 'Review Period' for Contractor’s Documents unless otherwise stated in the Employer’s Requirements?
What is the maximum 'Review Period' for Contractor’s Documents unless otherwise stated in the Employer’s Requirements?
Signup and view all the answers
When is it deemed that the Engineer has given a Notice of No-objection to the Contractor’s Document?
When is it deemed that the Engineer has given a Notice of No-objection to the Contractor’s Document?
Signup and view all the answers
When can the construction of a part of the Works requiring Contractor’s Documents for Review commence?
When can the construction of a part of the Works requiring Contractor’s Documents for Review commence?
Signup and view all the answers
When must the completed Works, including defects remedied by the Contractor, comply with the technical standards and Laws of the country?
When must the completed Works, including defects remedied by the Contractor, comply with the technical standards and Laws of the country?
Signup and view all the answers
When must the Contractor’s design, documents, and completed Works comply with the Laws of the Country and the documents forming the Contract?
When must the Contractor’s design, documents, and completed Works comply with the Laws of the Country and the documents forming the Contract?
Signup and view all the answers
Under what circumstances may the Contractor modify any design or Contractor’s Documents previously submitted for Review?
Under what circumstances may the Contractor modify any design or Contractor’s Documents previously submitted for Review?
Signup and view all the answers
When must the Contractor comply with the technical standards, building, construction, and environmental Laws of the country?
When must the Contractor comply with the technical standards, building, construction, and environmental Laws of the country?
Signup and view all the answers
When must the Contractor revise and resubmit a Contractor’s Document at their own cost?
When must the Contractor revise and resubmit a Contractor’s Document at their own cost?
Signup and view all the answers
When are all technical or other standards and Laws applicable to the Works required to be in force?
When are all technical or other standards and Laws applicable to the Works required to be in force?
Signup and view all the answers
What must the Contractor do if the Engineer instructs that further Contractor’s Documents are required to demonstrate compliance with the Contract?
What must the Contractor do if the Engineer instructs that further Contractor’s Documents are required to demonstrate compliance with the Contract?
Signup and view all the answers
Study Notes
FIDIC Contract: Obligations and Procedures for Contractors
- Published standards referenced in the contract are applicable as of the Base Date, unless otherwise stated.
- If new standards come into force after the Base Date, the Contractor must promptly notify the Engineer and propose compliance.
- The Engineer may initiate a Variation if compliance with new standards requires changes to the execution of the Works.
- The Contractor is responsible for training employees of the Employer in the operation and maintenance of the Works as specified in the Employer’s Requirements.
- The Contractor must provide qualified staff, facilities, and materials for the training as necessary.
- The Contractor is required to maintain complete "as-built" records of the Works and submit them to the Engineer for review.
- The Contractor must prepare and keep up-to-date operation and maintenance manuals for the Works as per the Employer’s Requirements.
- Provisional O&M Manuals are to be submitted before Tests on Completion, with any errors or defects promptly rectified at the Contractor’s cost.
- Final O&M Manuals must be submitted before the issue of any Taking-Over Certificate.
- The format and details of the as-built records and O&M Manuals should comply with the Employer’s Requirements.
- If the Engineer fails to give a Notice of resumption of work within 28 days, the Contractor may treat the suspension as an omission of the affected part of the Works.
- If the suspension affects the whole of the Works, the Contractor may give a Notice of termination.
Contractor's Documents and Review Process in Construction Contracts
- The Contractor is responsible for preparing all Contractor’s Documents necessary for the design and execution of the Works and for instructing the Contractor’s Personnel.
- The Employer’s Personnel have the right to inspect the preparation of these documents, including any investigation, modeling, and testing.
- The "Review Period" for Contractor’s Documents is a maximum of 21 days from the date the Engineer receives the document and a Contractor’s Notice, unless otherwise stated in the Employer’s Requirements.
- A "Contractor’s Document" excludes any documents not specified in the Employer’s Requirements or these Conditions but includes all documents on which a specified Contractor’s Document relies for completeness.
- If the Engineer gives no Notice within the Review Period, it is deemed that the Engineer has given a Notice of No-objection to the Contractor’s Document.
- If the Engineer instructs that further Contractor’s Documents are required to demonstrate compliance with the Contract, the Contractor must prepare and submit them promptly at their own cost.
- If the Engineer gives a Notice that the Contractor’s Document fails to comply with the requirements, the Contractor must revise and resubmit it at their own cost and is not entitled to an extension of time for any resulting delay.
- Construction of a part of the Works requiring Contractor’s Documents for Review cannot commence until a Notice of No-objection is given by the Engineer for all relevant documents and must be in accordance with these documents.
- The Contractor may modify any design or Contractor’s Documents previously submitted for Review by giving a Notice to the Engineer with reasons.
- The completed Works, including defects remedied by the Contractor, must comply with the technical standards, building, construction, and environmental Laws of the country, as well as other standards specified in the Employer’s Requirements or defined by applicable Laws.
- All technical or other standards and Laws applicable to the Works must be those in force when the Works are taken over by the Employer.
- The Contractor’s design, documents, and completed Works must comply with the Laws of the Country and the documents forming the Contract, as altered or modified by Variations.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Related Documents
Description
Learn about the obligations and procedures for contractors as specified in the FIDIC contract, including responsibilities for complying with standards, training employees, maintaining records, and submitting documents for review.