What action should the Contractor take if no Key Personnel are stated in the Specification?
What action should the Contractor take if no Key Personnel are stated in the Specification?
What is the consequence if the Engineer does not respond within 14 days after receiving the submission regarding the appointment of a person?
What is the consequence if the Engineer does not respond within 14 days after receiving the submission regarding the appointment of a person?
What is the restriction on the distribution of the document mentioned in the text?
What is the restriction on the distribution of the document mentioned in the text?
What is the purpose of submitting the name and particulars of another person to the Engineer?
What is the purpose of submitting the name and particulars of another person to the Engineer?
Signup and view all the answers
What is the consequence if the Engineer withholds consent for the appointed person?
What is the consequence if the Engineer withholds consent for the appointed person?
Signup and view all the answers
Under what condition does the Sub-Clause not apply?
Under what condition does the Sub-Clause not apply?
Signup and view all the answers
What is the requirement if an appointed person fails to act in the position of Key Personnel?
What is the requirement if an appointed person fails to act in the position of Key Personnel?
Signup and view all the answers
When does the Plant and Materials become the property of the Employer?
When does the Plant and Materials become the property of the Employer?
Signup and view all the answers
What is the Contractor responsible for paying unless otherwise stated in the Specification?
What is the Contractor responsible for paying unless otherwise stated in the Specification?
Signup and view all the answers
When should the Engineer give a Notice to the Contractor stating the Commencement Date?
When should the Engineer give a Notice to the Contractor stating the Commencement Date?
Signup and view all the answers
When should the Contractor submit the initial programme for the execution of the Works to the Engineer?
When should the Contractor submit the initial programme for the execution of the Works to the Engineer?
Signup and view all the answers
What should the initial programme for the execution of the Works include?
What should the initial programme for the execution of the Works include?
Signup and view all the answers
When should the Contractor commence the execution of the Works?
When should the Contractor commence the execution of the Works?
Signup and view all the answers
When should the Contractor complete the whole of the Works?
When should the Contractor complete the whole of the Works?
Signup and view all the answers
When should the Contractor submit a revised programme which accurately reflects the actual progress of the Works?
When should the Contractor submit a revised programme which accurately reflects the actual progress of the Works?
Signup and view all the answers
How many copies of the initial programme and each revised programme should the Contractor submit to the Engineer?
How many copies of the initial programme and each revised programme should the Contractor submit to the Engineer?
Signup and view all the answers
Who has the authority to approve the temporary replacement of Key Personnel?
Who has the authority to approve the temporary replacement of Key Personnel?
Signup and view all the answers
Under what circumstances can the Contractor appoint Key Personnel without the Engineer’s consent?
Under what circumstances can the Contractor appoint Key Personnel without the Engineer’s consent?
Signup and view all the answers
Who is responsible for providing all necessary resources for specified tests efficiently and properly?
Who is responsible for providing all necessary resources for specified tests efficiently and properly?
Signup and view all the answers
Who has full access to the site and natural material sources during working hours?
Who has full access to the site and natural material sources during working hours?
Signup and view all the answers
When must the Contractor notify the Engineer before covering up, putting out of sight, or packaging any materials, plant, or work for inspection?
When must the Contractor notify the Engineer before covering up, putting out of sight, or packaging any materials, plant, or work for inspection?
Signup and view all the answers
Who may vary the details of specified tests or instruct the Contractor to carry out additional tests?
Who may vary the details of specified tests or instruct the Contractor to carry out additional tests?
Signup and view all the answers
How much notice must the Engineer give the Contractor before attending tests?
How much notice must the Engineer give the Contractor before attending tests?
Signup and view all the answers
Who is entitled to EOT and/or payment of Cost Plus Profit if the Contractor suffers delay and/or incurs Cost from complying with any instruction from the Engineer?
Who is entitled to EOT and/or payment of Cost Plus Profit if the Contractor suffers delay and/or incurs Cost from complying with any instruction from the Engineer?
Signup and view all the answers
What happens if the Engineer does not attend the specified tests?
What happens if the Engineer does not attend the specified tests?
Signup and view all the answers
When is the Contractor required to bear the cost of all remedial work?
When is the Contractor required to bear the cost of all remedial work?
Signup and view all the answers
Under what condition is the Contractor entitled to payment for work if the Contractor fails to comply with the Engineer’s instruction?
Under what condition is the Contractor entitled to payment for work if the Contractor fails to comply with the Engineer’s instruction?
Signup and view all the answers
Who is entitled to payment of additional costs if rejection and retesting cause the Employer to incur additional costs?
Who is entitled to payment of additional costs if rejection and retesting cause the Employer to incur additional costs?
Signup and view all the answers
What happens if the Contractor fails to promptly submit a proposal for necessary remedial work?
What happens if the Contractor fails to promptly submit a proposal for necessary remedial work?
Signup and view all the answers
When can the Engineer instruct the Contractor to carry out any remedial work urgently required for the safety of the Works?
When can the Engineer instruct the Contractor to carry out any remedial work urgently required for the safety of the Works?
Signup and view all the answers
If the Engineer does not attend specified tests, what is the consequence?
If the Engineer does not attend specified tests, what is the consequence?
Signup and view all the answers
When is the Contractor entitled to an extension of time (EOT) and payment of costs?
When is the Contractor entitled to an extension of time (EOT) and payment of costs?
Signup and view all the answers
What happens if the Contractor fails to promptly forward duly certified test reports to the Engineer?
What happens if the Contractor fails to promptly forward duly certified test reports to the Engineer?
Signup and view all the answers
Under what circumstances is the Contractor required to bear the cost of all remedial work?
Under what circumstances is the Contractor required to bear the cost of all remedial work?
Signup and view all the answers
What is the consequence if the Contractor fails to comply with the Engineer’s instruction for remedial work?
What is the consequence if the Contractor fails to comply with the Engineer’s instruction for remedial work?
Signup and view all the answers
When is the Contractor responsible for payment of costs arising from the Contractor's failure to comply with the Engineer’s instruction?
When is the Contractor responsible for payment of costs arising from the Contractor's failure to comply with the Engineer’s instruction?
Signup and view all the answers
What happens if the Engineer endorses the Contractor’s test certificate upon passing specified tests?
What happens if the Engineer endorses the Contractor’s test certificate upon passing specified tests?
Signup and view all the answers
Study Notes
FIDIC 2017 Construction Contract Key Personnel and Work Execution
- The Contractor cannot revoke or appoint Key Personnel without the Engineer’s consent, except in cases of death, illness, disability, or resignation.
- Key Personnel must be based at the site or the location of the works throughout the execution of the works.
- Temporary replacement of Key Personnel during their absence requires the Engineer’s prior consent.
- Key Personnel must be fluent in the language for communications defined in Sub-Clause 1.4 [Law and Language].
- The Contractor is responsible for the manufacture, supply, installation, testing, and commissioning of Plant, materials, and workmanship in a proper workmanlike manner.
- The Contractor must submit samples of materials to the Engineer for consent before using them in the works.
- The Employer’s Personnel have full access to the site and natural material sources during working hours.
- The Employer’s Personnel are entitled to examine, inspect, measure, test materials, plant, and workmanship, and carry out other specified duties and inspections.
- The Contractor must notify the Engineer before covering up, putting out of sight, or packaging any materials, plant, or work for inspection.
- The Contractor is responsible for providing all necessary resources for specified tests efficiently and properly.
- The Engineer may vary the details of specified tests or instruct the Contractor to carry out additional tests under Clause 13 [Variations and Adjustments].
- The Engineer must give the Contractor at least 72 hours' notice of intention to attend tests.
Contractor's Obligations and Remedial Work in Construction Contracts
- If the Engineer does not attend specified tests, the Contractor can proceed, and the Engineer will be deemed to have accepted the readings as accurate
- The Contractor is entitled to an extension of time (EOT) and payment of costs if the Engineer causes delay or incurs costs due to the Contractor's compliance with instructions or delays for which the Employer is responsible
- If the Contractor delays specified tests causing the Employer to incur costs, the Employer is entitled to payment of these costs by the Contractor
- The Contractor must promptly forward duly certified test reports to the Engineer
- The Engineer endorses the Contractor’s test certificate upon passing specified tests
- If any part of the Works fails to pass a specified test, Sub-Clause 7.5 [Defects and Rejection] applies
- If any Plant, Materials, design, or workmanship is found defective, the Engineer gives a Notice to the Contractor, who must promptly submit a proposal for necessary remedial work
- If the Engineer does not object within 14 days, it is deemed as a Notice of No-objection
- The Contractor must comply with the Engineer's instruction for remedial work and bear the cost, except for work required for safety due to an accident or unforeseeable event
- After remedying defects, if retesting is required, it is at the Contractor’s risk and cost
- If the Contractor fails to comply with the Engineer’s instruction, the Employer may employ others at the Contractor's cost
- The Employer is entitled to payment by the Contractor for all costs arising from the Contractor's failure to comply with the Engineer’s instruction
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Related Documents
Description
This quiz covers the FIDIC 2017 Construction Contract clauses related to the appointment and responsibilities of Key Personnel, execution of works, specified tests, and the Contractor's obligations and remedial work. Test your knowledge of the key provisions and requirements in construction contracts.