Podcast
Questions and Answers
What action should the Contractor take if an error, fault, or defect is found in the Employer’s Requirements after the specified period?
What action should the Contractor take if an error, fault, or defect is found in the Employer’s Requirements after the specified period?
When should the Contractor give a Notice to the Engineer if an error, fault, or defect is found in the Employer’s Requirements?
When should the Contractor give a Notice to the Engineer if an error, fault, or defect is found in the Employer’s Requirements?
What is the Engineer's responsibility upon receiving a Notice from the Contractor regarding an error, fault, or defect in the Employer’s Requirements?
What is the Engineer's responsibility upon receiving a Notice from the Contractor regarding an error, fault, or defect in the Employer’s Requirements?
What should the Contractor consider when scrutinizing the Employer’s Requirements before submitting the Tender?
What should the Contractor consider when scrutinizing the Employer’s Requirements before submitting the Tender?
Signup and view all the answers
Who is responsible for the design of the Works?
Who is responsible for the design of the Works?
Signup and view all the answers
What should the Contractor do upon discovery of any finding?
What should the Contractor do upon discovery of any finding?
Signup and view all the answers
Under what circumstances is the Contractor entitled to EOT and/or payment of Cost?
Under what circumstances is the Contractor entitled to EOT and/or payment of Cost?
Signup and view all the answers
Who must the designers and design Subcontractors be available to attend discussions with?
Who must the designers and design Subcontractors be available to attend discussions with?
Signup and view all the answers
What must the Contractor do with the wreckage, rubbish, and Temporary Works no longer required?
What must the Contractor do with the wreckage, rubbish, and Temporary Works no longer required?
Signup and view all the answers
What should the Contractor do if the designers do not have the necessary experience, capability, and competence for the design?
What should the Contractor do if the designers do not have the necessary experience, capability, and competence for the design?
Signup and view all the answers
Who is entitled to issue instructions for dealing with any findings?
Who is entitled to issue instructions for dealing with any findings?
Signup and view all the answers
Who warrants that the designers and design Subcontractors have the necessary experience, capability, and competence for the design?
Who warrants that the designers and design Subcontractors have the necessary experience, capability, and competence for the design?
Signup and view all the answers
What happens if the Engineer does not respond within 14 days after receiving a submission about a proposed subcontractor?
What happens if the Engineer does not respond within 14 days after receiving a submission about a proposed subcontractor?
Signup and view all the answers
When must the Contractor notify the Engineer about the intended start date of each subcontractor's work?
When must the Contractor notify the Engineer about the intended start date of each subcontractor's work?
Signup and view all the answers
What is a 'Nominated Subcontractor' according to the contract?
What is a 'Nominated Subcontractor' according to the contract?
Signup and view all the answers
What must the Contractor ensure about the Accepted Contract Amount?
What must the Contractor ensure about the Accepted Contract Amount?
Signup and view all the answers
What must the Contractor promptly notify to the Engineer during the execution of the Works?
What must the Contractor promptly notify to the Engineer during the execution of the Works?
Signup and view all the answers
When is the Contractor responsible for clearing away and removing equipment, surplus material, and hazardous waste from the site?
When is the Contractor responsible for clearing away and removing equipment, surplus material, and hazardous waste from the site?
Signup and view all the answers
What is the Contractor's responsibility after the issue of a Taking-Over Certificate?
What is the Contractor's responsibility after the issue of a Taking-Over Certificate?
Signup and view all the answers
When may the Contractor retain necessary goods at agreed locations on the site?
When may the Contractor retain necessary goods at agreed locations on the site?
Signup and view all the answers
What should be done with any fossils, coins, or items of geological or archaeological interest found on the site?
What should be done with any fossils, coins, or items of geological or archaeological interest found on the site?
Signup and view all the answers
When must the Contractor obtain a Performance Security?
When must the Contractor obtain a Performance Security?
Signup and view all the answers
What is the Contractor responsible for regarding the adequacy, stability, and safety of the Works?
What is the Contractor responsible for regarding the adequacy, stability, and safety of the Works?
Signup and view all the answers
Under what circumstances can the Contractor delegate powers, functions, and authority?
Under what circumstances can the Contractor delegate powers, functions, and authority?
Signup and view all the answers
When can subcontractors be appointed by the Contractor?
When can subcontractors be appointed by the Contractor?
Signup and view all the answers
What must the Contractor ensure about the Contractor’s Documents and design documents?
What must the Contractor ensure about the Contractor’s Documents and design documents?
Signup and view all the answers
When is the Contractor entitled to an Extension of Time (EOT) and/or payment of costs plus profit?
When is the Contractor entitled to an Extension of Time (EOT) and/or payment of costs plus profit?
Signup and view all the answers
What should the Contractor submit details of to the Engineer?
What should the Contractor submit details of to the Engineer?
Signup and view all the answers
When can the Contractor make significant alterations to the proposed arrangements and methods for executing the Works?
When can the Contractor make significant alterations to the proposed arrangements and methods for executing the Works?
Signup and view all the answers
What is the Contractor responsible for if they do not complete the Works?
What is the Contractor responsible for if they do not complete the Works?
Signup and view all the answers
What is the validity period of the Performance Security?
What is the validity period of the Performance Security?
Signup and view all the answers
What must the Contractor do before making any significant alterations to the proposed arrangements and methods for executing the Works?
What must the Contractor do before making any significant alterations to the proposed arrangements and methods for executing the Works?
Signup and view all the answers
Who may the Contractor delegate powers, functions, and authority to?
Who may the Contractor delegate powers, functions, and authority to?
Signup and view all the answers
Study Notes
FIDIC 2017 Plant and Design-Build Contract - Key Points
- The Contractor must obtain the Engineer's prior consent for proposed subcontractors, except for suppliers of materials or a subcontractor named in the contract.
- If the Engineer does not respond within 14 days after receiving a submission about a proposed subcontractor, consent is deemed to be given.
- The Contractor must notify the Engineer at least 28 days before the intended start date of each subcontractor's work.
- "Nominated Subcontractor" is a subcontractor named in the Employer's Requirements or instructed by the Engineer under Sub-Clause 13.4.
- The Contractor must ensure that the Accepted Contract Amount is sufficient for the execution of the Works and is based on all relevant data and interpretations.
- Unforeseeable physical conditions, excluding climatic conditions, encountered at the site during the execution of the Works must be promptly notified to the Engineer by the Contractor.
- The Contractor is responsible for clearing away and removing equipment, surplus material, and hazardous waste from the site after the issue of a Taking-Over Certificate.
- The Contractor must leave the site clean and safe after the issue of a Taking-Over Certificate.
- The Contractor may retain necessary goods at agreed locations on the site during the Defects Notification Period (DNP).
- Any fossils, coins, or items of geological or archaeological interest found on the site shall be placed under the care and authority of the Employer.
Contractor's Obligations and Responsibilities Under FIDIC 2017
- The Contractor is responsible for rectifying any errors or defects in documents prepared for the Works, at their own cost and risk.
- The Contractor is required to provide the Plant, spare parts, Contractor’s Documents, and all other necessary personnel and materials to fulfill their obligations under the Contract.
- The Works must meet the requirements specified in the Employer’s Requirements, Contractor’s Proposal, and Schedules, and the Contractor is responsible for their adequacy, stability, and safety.
- The Contractor must obtain a Performance Security to ensure proper performance of the Contract, in the amount and currency stated in the Contract Data, and deliver it to the Employer within 28 days of receiving the Letter of Acceptance.
- The Performance Security must remain valid and enforceable until the issue of the Performance Certificate and compliance with Sub-Clause 11.11 [Clearance of Site].
- The Contractor is obliged to execute the Works in accordance with the Contract and ensure they are fit for their intended purpose as defined in the Employer’s Requirements.
- The Contractor’s Representative may delegate powers, functions, and authority to competent individuals, subject to the Engineer’s consent and notification.
- Subcontractors may be appointed by the Contractor, subject to the Engineer's prior consent, and the Contractor remains responsible for their work.
- If the Contractor does not complete the Works, a suitable replacement must be temporarily appointed, subject to the Engineer’s prior consent.
- The Contractor shall retain copyright and intellectual property rights in the Contractor’s Documents and design documents.
- If the Contractor suffers delay or incurs costs due to errors, faults, or defects, they are entitled to an Extension of Time (EOT) and/or payment of such costs plus profit, subject to Sub-Clause 20.2 [Claims For Payment and/or EOT].
- The Contractor must submit details of proposed arrangements and methods for executing the Works to the Engineer and cannot make significant alterations without the Engineer's approval.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Related Documents
Description
Learn about key points and contractor's obligations under the FIDIC 2017 Plant and Design-Build Contract, including subcontractor consent, unforeseen conditions, site clearance, performance security, and intellectual property rights.