Podcast
Questions and Answers
Which of the following best defines the Critical Path Method (CPM)?
Which of the following best defines the Critical Path Method (CPM)?
In project scheduling, what does 'float' represent?
In project scheduling, what does 'float' represent?
Which dependency type is created by the nature of the work and cannot be changed?
Which dependency type is created by the nature of the work and cannot be changed?
What is the main difference between 'free float' and 'total float'?
What is the main difference between 'free float' and 'total float'?
Signup and view all the answers
In the Forward-Backward Pass method, what does the 'Late Finish' (LF) represent?
In the Forward-Backward Pass method, what does the 'Late Finish' (LF) represent?
Signup and view all the answers
What is a primary drawback of using fast-tracking as a schedule compression technique?
What is a primary drawback of using fast-tracking as a schedule compression technique?
Signup and view all the answers
In project scheduling, what does a Gantt chart primarily display?
In project scheduling, what does a Gantt chart primarily display?
Signup and view all the answers
Which scheduling technique involves adding extra resources to reduce the duration of critical path activities?
Which scheduling technique involves adding extra resources to reduce the duration of critical path activities?
Signup and view all the answers
Why is it important to identify the critical path in project scheduling?
Why is it important to identify the critical path in project scheduling?
Signup and view all the answers
What does 'resource leveling' primarily aim to address?
What does 'resource leveling' primarily aim to address?
Signup and view all the answers
You discover that a critical path activity has been delayed by two days. What is the likely impact on the project schedule?
You discover that a critical path activity has been delayed by two days. What is the likely impact on the project schedule?
Signup and view all the answers
Your project schedule shows several activities with negative float. What does this indicate?
Your project schedule shows several activities with negative float. What does this indicate?
Signup and view all the answers
A project sponsor requests that you shorten the project duration by two weeks. Which technique would be most appropriate to consider first?
A project sponsor requests that you shorten the project duration by two weeks. Which technique would be most appropriate to consider first?
Signup and view all the answers
During a review meeting, a stakeholder points out that several tasks are overallocated in the resource calendar. What is your best immediate action?
During a review meeting, a stakeholder points out that several tasks are overallocated in the resource calendar. What is your best immediate action?
Signup and view all the answers
You are using a project scheduling tool that shows an indicator of resource overallocation. What is the potential impact on your project?
You are using a project scheduling tool that shows an indicator of resource overallocation. What is the potential impact on your project?
Signup and view all the answers
You have used fast-tracking to overlap tasks on the critical path, but a team member warns about potential rework. What should you do next?
You have used fast-tracking to overlap tasks on the critical path, but a team member warns about potential rework. What should you do next?
Signup and view all the answers
While performing a backward pass, you find that one activity has a Late Start (LS) date earlier than its Early Start (ES) date. What does this indicate?
While performing a backward pass, you find that one activity has a Late Start (LS) date earlier than its Early Start (ES) date. What does this indicate?
Signup and view all the answers
A stakeholder demands an aggressive deadline that significantly shortens the project timeline. Which scheduling technique would best help assess the feasibility of this request?
A stakeholder demands an aggressive deadline that significantly shortens the project timeline. Which scheduling technique would best help assess the feasibility of this request?
Signup and view all the answers
Your project is nearing completion, but a critical task is delayed due to an unavailable resource. What is the best course of action to avoid project delays?
Your project is nearing completion, but a critical task is delayed due to an unavailable resource. What is the best course of action to avoid project delays?
Signup and view all the answers
You are reviewing a Gantt chart and notice a lag of 5 days added between two critical path activities. What could be the reason for this lag?
You are reviewing a Gantt chart and notice a lag of 5 days added between two critical path activities. What could be the reason for this lag?
Signup and view all the answers
During a project review, you find that one task has both positive total float and negative free float. What does this indicate?
During a project review, you find that one task has both positive total float and negative free float. What does this indicate?
Signup and view all the answers
Your project uses MS Project for scheduling. After running a resource leveling analysis, you notice that the project duration has increased. What is the most likely reason for this change?
Your project uses MS Project for scheduling. After running a resource leveling analysis, you notice that the project duration has increased. What is the most likely reason for this change?
Signup and view all the answers
A team member suggests adding contingency to every task on the critical path. What would be the impact of this approach?
A team member suggests adding contingency to every task on the critical path. What would be the impact of this approach?
Signup and view all the answers
You have identified a new critical path after making changes to the project schedule. What is your immediate next step?
You have identified a new critical path after making changes to the project schedule. What is your immediate next step?
Signup and view all the answers
You are applying crashing to reduce the project duration, but the project costs are increasing significantly. What should you consider before continuing?
You are applying crashing to reduce the project duration, but the project costs are increasing significantly. What should you consider before continuing?
Signup and view all the answers
A project milestone is approaching, but the associated tasks are running behind schedule. What is the most appropriate technique to use in this situation?
A project milestone is approaching, but the associated tasks are running behind schedule. What is the most appropriate technique to use in this situation?
Signup and view all the answers
You find that one of your critical path activities has zero float but is not progressing as planned. What is the best immediate response?
You find that one of your critical path activities has zero float but is not progressing as planned. What is the best immediate response?
Signup and view all the answers
Your project schedule indicates a high level of resource overallocation in the final phase. Which action would be most effective in addressing this issue?
Your project schedule indicates a high level of resource overallocation in the final phase. Which action would be most effective in addressing this issue?
Signup and view all the answers
You are conducting a critical path analysis and discover a secondary critical path with minimal float. How should you proceed?
You are conducting a critical path analysis and discover a secondary critical path with minimal float. How should you proceed?
Signup and view all the answers
You need to shorten the project duration, but further crashing is not cost-effective. What alternative should you consider?
You need to shorten the project duration, but further crashing is not cost-effective. What alternative should you consider?
Signup and view all the answers
The project schedule baseline is approved, but frequent changes in task sequencing are being requested by stakeholders. What is your best course of action?
The project schedule baseline is approved, but frequent changes in task sequencing are being requested by stakeholders. What is your best course of action?
Signup and view all the answers
A delay in an external dependency is impacting your project schedule. How should you address this issue?
A delay in an external dependency is impacting your project schedule. How should you address this issue?
Signup and view all the answers
You discover that the critical path duration is longer than the contractual project deadline. What is the most appropriate response?
You discover that the critical path duration is longer than the contractual project deadline. What is the most appropriate response?
Signup and view all the answers
Your project schedule has been adjusted multiple times. What is a potential risk of frequent schedule changes?
Your project schedule has been adjusted multiple times. What is a potential risk of frequent schedule changes?
Signup and view all the answers
The project team has identified a potential new critical path after implementing resource leveling. What should you prioritize?
The project team has identified a potential new critical path after implementing resource leveling. What should you prioritize?
Signup and view all the answers
What does 'lead time' allow for in project scheduling?
What does 'lead time' allow for in project scheduling?
Signup and view all the answers
Which type of dependency is most commonly influenced by project management decisions rather than inherent project requirements?
Which type of dependency is most commonly influenced by project management decisions rather than inherent project requirements?
Signup and view all the answers
In project scheduling, what is the primary purpose of using a milestone?
In project scheduling, what is the primary purpose of using a milestone?
Signup and view all the answers
What is a key characteristic of a Finish-to-Start (FS) dependency?
What is a key characteristic of a Finish-to-Start (FS) dependency?
Signup and view all the answers
Which scheduling technique adjusts task start and finish dates based on resource constraints?
Which scheduling technique adjusts task start and finish dates based on resource constraints?
Signup and view all the answers
When would you use a 'Monte Carlo simulation' in scheduling?
When would you use a 'Monte Carlo simulation' in scheduling?
Signup and view all the answers
What is the primary purpose of 'lag time' in a project schedule?
What is the primary purpose of 'lag time' in a project schedule?
Signup and view all the answers
Which tool is most commonly used to display the project schedule and show task dependencies?
Which tool is most commonly used to display the project schedule and show task dependencies?
Signup and view all the answers
In the context of scheduling, what is a 'hammock activity'?
In the context of scheduling, what is a 'hammock activity'?
Signup and view all the answers
If an activity on the critical path is delayed, what is the immediate impact on the project?
If an activity on the critical path is delayed, what is the immediate impact on the project?
Signup and view all the answers
Which scheduling technique is used when project tasks are performed in parallel to reduce the total duration?
Which scheduling technique is used when project tasks are performed in parallel to reduce the total duration?
Signup and view all the answers
What is the primary disadvantage of crashing a project schedule?
What is the primary disadvantage of crashing a project schedule?
Signup and view all the answers
In project scheduling, what does 'slack time' (or float) represent?
In project scheduling, what does 'slack time' (or float) represent?
Signup and view all the answers
When is a 'Finish-to-Finish' (FF) relationship typically used in scheduling?
When is a 'Finish-to-Finish' (FF) relationship typically used in scheduling?
Signup and view all the answers
What is the main purpose of using 'baseline schedules' in project management?
What is the main purpose of using 'baseline schedules' in project management?
Signup and view all the answers
Study Notes
Critical Path Method (CPM) and Project Scheduling
- CPM definition: The longest path through the project network diagram that determines the minimum project duration.
- Float: The time an activity can be delayed without impacting the project completion date.
- Free float: The time an activity can be delayed without delaying any successor.
- Total float: The time an activity can be delayed without delaying the project.
- Critical path: The sequence of activities that determines the shortest possible project duration.
- Mandatory dependency: A dependency type created by the nature of the work and cannot be changed.
- Crashing: A scheduling technique that involves adding extra resources to reduce the duration of critical path activities.
- Fast-tracking: A schedule compression technique where tasks are overlapped to shorten the project duration.
- Resource leveling: A technique used to adjust the schedule to prevent resource overallocation.
- Gantt chart: A project scheduling tool that displays the timeline of activities and their dependencies.
- Monte Carlo simulation: A technique used to predict the probability of meeting a project schedule based on risk analysis.
- Milestone: A significant event or completion point in a project.
- Lag time: A delay between the finish of one activity and the start of another.
- Hammock activity: A summary activity that spans multiple tasks.
- Baseline schedule: A reference point for measuring project performance against planned performance.
- Project Scheduling: The process of defining, sequencing, scheduling, controlling the project activities within budget, time, and scope, and resource constraints.
Project Scheduling Techniques
- Fast-Tracking: Overlapping tasks on the critical path to reduce project duration.
- Crashing: Adding more resources to shorten critical path activities, leading to increased costs.
- Resource Leveling: Adjusting the schedule to prevent resource overallocation.
Project Schedule Issues
- Critical path delay: Impact of delayed activities on the overall project completion.
- Resource conflicts: Overallocation of resources to tasks, potentially leading to schedule delays and conflicts.
- Negative float: Indicates that activities on the schedule cannot meet the imposed deadline without adjustments.
- Critical Path Length: The length of time it will take to complete all the activities on the critical path.
- Schedule Compression: Strategies to shorten the project duration (e.g., fast-tracking, crashing).
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Related Documents
Description
Test your understanding of the Critical Path Method (CPM) and its key concepts, including float types, dependencies, and scheduling techniques. This quiz will challenge your knowledge about how to efficiently manage project timelines and resources.