Construction Site Management Quiz
40 Questions
2 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

Which of the following is a role of the Resident Engineer?

  • Instruct the Contractor on daily tasks
  • Design project architecture
  • Check quality of materials against specifications (correct)
  • Manage financial aspects of the project
  • What should be done with the total of wet days reported for the month?

  • Only recommend 1 day EOT (correct)
  • Require a total of 6 days EOT
  • Determine the average of wet days for future reference
  • Ignore the wet days completely
  • What aspect of the project is NOT typically a responsibility of the Quantity Surveyor (QS)?

  • Describing materials specifications
  • Designing the architecture (correct)
  • Conduct site inspections
  • Preparing tender documents
  • Which of the following describes a common defect in construction?

    <p>Spalling concrete</p> Signup and view all the answers

    When a project does not have an architect, who typically takes on the role of Contract Administrator?

    <p>Another lead Consultant</p> Signup and view all the answers

    What authority does the Resident Engineer have regarding safety on site?

    <p>To stop unsafe work practices</p> Signup and view all the answers

    During the pre-contract administration phase, which of the following is NOT part of the process?

    <p>Finalizing the construction timeline</p> Signup and view all the answers

    Which action is required if the Contractor believes a site memo constitutes a Variation Order (VO)?

    <p>Raise a Request for Variation Orders</p> Signup and view all the answers

    What is the purpose of a Performance Bond in construction projects?

    <p>To provide assurance for the owner in case the contractor fails to perform the work properly.</p> Signup and view all the answers

    During which phase of the project is the Mobilisation period typically scheduled?

    <p>Before commencement of works.</p> Signup and view all the answers

    What is the key responsibility of the architect during the construction period?

    <p>Management of quality of work and time tracking.</p> Signup and view all the answers

    Which is typically NOT part of the post-contract administration phase?

    <p>Issuing the Letter of Acceptance.</p> Signup and view all the answers

    What is the duration of the Maintenance period commonly established in construction contracts?

    <p>12 months, with possible extensions to 18 or 24 months.</p> Signup and view all the answers

    What is one of the main aims of procurement in construction projects?

    <p>To balance cost and quality effectively.</p> Signup and view all the answers

    What does EOT stand for in the context of construction project management?

    <p>Extension of Time.</p> Signup and view all the answers

    Which document is typically issued to signify the completion of a construction project?

    <p>Final Certificate.</p> Signup and view all the answers

    What is preferred over excellent design in certain building projects?

    <p>Early return on capital investment</p> Signup and view all the answers

    Which type of project is NOT suitable for systems like repetitive housing?

    <p>Complex refurbishment work</p> Signup and view all the answers

    Which risk is faced solely by contractors according to the provided information?

    <p>Delay by workmen and sub contractors</p> Signup and view all the answers

    What is the implication of a payment obligation to the contractor?

    <p>Owner bears the responsibility for timely payments</p> Signup and view all the answers

    Which of the following risks would NOT affect the owner?

    <p>Defective design liability</p> Signup and view all the answers

    What type of projects are contractors likely to specialize in?

    <p>Healthcare and lab buildings using pre-fabrication</p> Signup and view all the answers

    In a lump sum contract, who bears the risk of measurement errors?

    <p>The contractors</p> Signup and view all the answers

    What might limit the use of proprietary systems in building projects?

    <p>Importance of design quality for the client</p> Signup and view all the answers

    What is required for all structural drawings submitted to public sectors?

    <p>Evaluation by an Accredited Checker (AC)</p> Signup and view all the answers

    What percentage weightage does the QFM framework typically assign to quality in proposals?

    <p>70-90%</p> Signup and view all the answers

    What mechanism is used in the QFM framework to address fee-diving behavior?

    <p>Exclusion of outlier bids from average fee computations</p> Signup and view all the answers

    Which system is employed in the QFM framework to ensure objective evaluation of tenderers?

    <p>Two-envelope system</p> Signup and view all the answers

    What advantage does the Public Sector Panels of Consultants (PSPC) provide?

    <p>Ensure firms meet capacity and capability requirements</p> Signup and view all the answers

    Which engineering role is not listed as part of the Multi Disciplinary Team (MDT)?

    <p>Cost Estimator</p> Signup and view all the answers

    How does the QFM framework aim to reward the quality of service provided by firms?

    <p>By reducing tendering efforts for high performing firms</p> Signup and view all the answers

    What behavior does the QFM framework discourage among tenderers?

    <p>Fee-diving during the bidding process</p> Signup and view all the answers

    What must occur before the contractor can commence work according to the contractual obligations?

    <p>The provisions of clauses 4, 5, 8, and 10 must be met.</p> Signup and view all the answers

    What document is required when the commencement date is revised?

    <p>Certificate of Revised Date of Commencement</p> Signup and view all the answers

    If no Date of Commencement is indicated in the Appendix, when does the contractor commence work?

    <p>On the deemed Date of Commencement agreed upon by the parties.</p> Signup and view all the answers

    What happens if the employer cannot provide the site to the contractor on the agreed date?

    <p>An extension of time may be granted, but the contract period remains unchanged.</p> Signup and view all the answers

    Under what circumstances can the contractor receive a written instruction to commence work?

    <p>If no specific date is mentioned in the Letter of Acceptance.</p> Signup and view all the answers

    Which clauses relate specifically to the calculation of the Date of Completion?

    <p>Clauses 4, 5, 8, and 10</p> Signup and view all the answers

    What is a potential consequence of changing the commencement date of a contract?

    <p>The entire program must be adjusted while maintaining the original contract period.</p> Signup and view all the answers

    What is the role of the Superintending Officer regarding the commencement of works?

    <p>To provide written instructions for commencing work when not specified.</p> Signup and view all the answers

    Study Notes

    Roles and Responsibilities in Construction Projects

    • Total of 6 wet days in a month; only one day for Extension of Time (EOT) is recommended, not the full 6.
    • Site inspections should address defects as per material specifications and construction drawings, such as leaking concrete, spalling, or incorrect material thickness.
    • Site and contract disputes must be resolved promptly.

    Role of Architects

    • Architects are responsible for designing and supervising works, as well as acting as Contract Administrators.
    • In the absence of an Architect, lead consultants assume the role of Contract Administrator, excluding Quantity Surveyors who do not design.

    Resident Engineer and Team Functions

    • Resident Engineer (RE) and Resident Architect (RA) monitor site activities and ensure compliance with contract specifications.
    • They evaluate the quality of materials and construction work, reporting abnormalities to the consulting team.
    • While they can enforce safety measures, they lack authority to instruct contractors directly.
    • Site memos may be issued but must be responded to properly to avoid contract variations.

    Construction Project Timeline

    • Pre-Contract Administration:

      • Involves design development, consultant appointments, feasibility studies, and tender period preparations.
      • Tender documents are created, and projects are publicly tendered with evaluations leading to recommendations for awards.
    • Post-Contract Administration:

      • Mobilization Period: Involves obtaining insurance, performance bonds, site setup, and securing permits.
      • Construction Period: The formal contract period is marked by progress claims, payment responses, instructions, and variations.
      • Maintenance Period: Typically lasts 12-24 months, focusing on EOT management, defect rectification, and settlement of final accounts.

    Understanding Procurement in Construction

    • Procurement involves acquiring goods, services, or works, primarily through tender processes.
    • The aim is to achieve the best possible price, factoring quality, and price competitiveness.

    Accreditation and Evaluation in Public Sectors

    • Accredited Checker (AC) must review all structural drawings in public sector projects to ensure compliance.
    • QFM Framework emphasizes quality, with a focus on evaluating contractor and consultant capabilities over fee concerns.

    Key Principles of Quality Focused Management (QFM)

    • Quality takes precedence over cost in the evaluation of tenders (Quality 70-90%, Fees 30-10%).
    • Objective evaluation processes are maintained with a two-envelope system for quality and fee proposals.

    Types of Risks in Construction Projects

    • Payment risks are borne by the owner, while contractors face risks for completion and defective designs.
    • Material and labor price increases typically fall on contractors unless stated otherwise in contract clauses.
    • Delays due to subcontractors may incur liquidated damages for the contractor.

    Commencement of Works and Contractual Terms

    • Contractual terms state that work commences on specified dates, or reasonable dates if no date is provided.
    • If commencement dates change, a "Certificate of Revised Date of Commencement" may be issued to adjust project timelines without altering the overall contract duration.

    Possession of Site and Project Management

    • Works must commence promptly as specified in the Letter of Acceptance or as instructed by the Superintending Officer if no date is provided.

    Studying That Suits You

    Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

    Quiz Team

    Related Documents

    PF4102 Notes PDF

    Description

    Test your knowledge on construction site management with this quiz. Focused on defect inspection and environmental conditions, you'll explore common issues like material specifications and contract disputes. Ideal for professionals in the construction industry.

    More Like This

    Use Quizgecko on...
    Browser
    Browser