Podcast
Questions and Answers
What is the primary purpose of a statutory declaration provided by a contractor?
What is the primary purpose of a statutory declaration provided by a contractor?
What could be a consequence of making a false statutory declaration?
What could be a consequence of making a false statutory declaration?
When must contractors provide statutory declarations to contract administrators?
When must contractors provide statutory declarations to contract administrators?
What is the required percentage of statutory holdback mandated by the Construction Lien Act?
What is the required percentage of statutory holdback mandated by the Construction Lien Act?
Signup and view all the answers
Which statement about deficiency holdback is true?
Which statement about deficiency holdback is true?
Signup and view all the answers
A statutory declaration may be required to preserve which of the following?
A statutory declaration may be required to preserve which of the following?
Signup and view all the answers
What does the holdback amount represent in a construction project?
What does the holdback amount represent in a construction project?
Signup and view all the answers
For which scenarios might a contractor’s statutory declaration be necessary?
For which scenarios might a contractor’s statutory declaration be necessary?
Signup and view all the answers
What is the updated contract price after including the approved change orders for the first progress payment?
What is the updated contract price after including the approved change orders for the first progress payment?
Signup and view all the answers
What is the total gross work done for the first progress payment, including change orders?
What is the total gross work done for the first progress payment, including change orders?
Signup and view all the answers
What percentage is deducted as the deficiency holdback on the net work done for the first progress payment?
What percentage is deducted as the deficiency holdback on the net work done for the first progress payment?
Signup and view all the answers
How much is the statutory holdback amount deducted from the first progress payment?
How much is the statutory holdback amount deducted from the first progress payment?
Signup and view all the answers
What is the total HST added to the cheque amount for the first progress payment?
What is the total HST added to the cheque amount for the first progress payment?
Signup and view all the answers
What is the net amount paid to the contractor after all deductions for the first progress payment?
What is the net amount paid to the contractor after all deductions for the first progress payment?
Signup and view all the answers
What is the gross amount of work done up to the second progress payment?
What is the gross amount of work done up to the second progress payment?
Signup and view all the answers
What is the total holdback amount with the owner after the second progress payment?
What is the total holdback amount with the owner after the second progress payment?
Signup and view all the answers
What is the primary purpose of the schedule of values in a construction contract?
What is the primary purpose of the schedule of values in a construction contract?
Signup and view all the answers
Why are unit prices/unit rates included in the schedule of values?
Why are unit prices/unit rates included in the schedule of values?
Signup and view all the answers
How can unit prices simplify dealing with change orders?
How can unit prices simplify dealing with change orders?
Signup and view all the answers
What is a common tactic that shrewd contractors may use in the schedule of values?
What is a common tactic that shrewd contractors may use in the schedule of values?
Signup and view all the answers
What is the primary benefit of using unit prices for progress payments?
What is the primary benefit of using unit prices for progress payments?
Signup and view all the answers
What does a statutory declaration from a contractor typically represent?
What does a statutory declaration from a contractor typically represent?
Signup and view all the answers
What role does vigilance against front loading play in contract administration?
What role does vigilance against front loading play in contract administration?
Signup and view all the answers
What is one advantage of requesting unit prices during the bidding process?
What is one advantage of requesting unit prices during the bidding process?
Signup and view all the answers
What is the primary purpose of WSIB registration for workers?
What is the primary purpose of WSIB registration for workers?
Signup and view all the answers
What must employers do after registering with WSIB?
What must employers do after registering with WSIB?
Signup and view all the answers
What additional obligation do employers have related to health and safety regulations?
What additional obligation do employers have related to health and safety regulations?
Signup and view all the answers
What determines the amount of premiums an employer pays to WSIB?
What determines the amount of premiums an employer pays to WSIB?
Signup and view all the answers
What type of certificate must contractors provide with each progress payment?
What type of certificate must contractors provide with each progress payment?
Signup and view all the answers
How is a Schedule of Values (SOV) structured in a construction project?
How is a Schedule of Values (SOV) structured in a construction project?
Signup and view all the answers
Which consequence may arise from failing to comply with WSIB registration requirements?
Which consequence may arise from failing to comply with WSIB registration requirements?
Signup and view all the answers
What is the significance of the WSIB compensation in case of workplace injuries?
What is the significance of the WSIB compensation in case of workplace injuries?
Signup and view all the answers
What is the primary purpose of statutory holdback in construction contracts?
What is the primary purpose of statutory holdback in construction contracts?
Signup and view all the answers
When is the statutory holdback returned to the contractor?
When is the statutory holdback returned to the contractor?
Signup and view all the answers
What is required from a contractor for each progress payment?
What is required from a contractor for each progress payment?
Signup and view all the answers
What defines substantial performance of a contract under the Construction Lien Act?
What defines substantial performance of a contract under the Construction Lien Act?
Signup and view all the answers
What percentage is typically held as a statutory holdback in construction contracts?
What percentage is typically held as a statutory holdback in construction contracts?
Signup and view all the answers
What is deficiency holdback?
What is deficiency holdback?
Signup and view all the answers
How is the cost for correcting a known defect determined for substantial completion?
How is the cost for correcting a known defect determined for substantial completion?
Signup and view all the answers
What occurs if the contractor fails to settle lien claims against him?
What occurs if the contractor fails to settle lien claims against him?
Signup and view all the answers
Which document is NOT required for the General Contractor to receive progress payments?
Which document is NOT required for the General Contractor to receive progress payments?
Signup and view all the answers
What is the primary purpose of the MOL Form 1000 in Ontario?
What is the primary purpose of the MOL Form 1000 in Ontario?
Signup and view all the answers
Which of the following is a requirement for WSIB registration in Ontario?
Which of the following is a requirement for WSIB registration in Ontario?
Signup and view all the answers
What entity is responsible for overseeing labor-related matters such as occupational health and safety in Ontario?
What entity is responsible for overseeing labor-related matters such as occupational health and safety in Ontario?
Signup and view all the answers
Which of the following is NOT a document to be submitted to the Contract Administrator for progress payment approval?
Which of the following is NOT a document to be submitted to the Contract Administrator for progress payment approval?
Signup and view all the answers
When is the MOL Form 1000 required to be present at a construction site?
When is the MOL Form 1000 required to be present at a construction site?
Signup and view all the answers
What does WSIB stand for?
What does WSIB stand for?
Signup and view all the answers
Which document provides a breakdown of the contract's budgeted costs?
Which document provides a breakdown of the contract's budgeted costs?
Signup and view all the answers
Study Notes
Lecture 7: Progress Payments
- Lecture objectives include familiarizing students with start-up document requirements for progress payments, the Construction Lien Act and enabling students to successfully handle progress payments on construction job sites.
- Essential documents for start-up, which must be prepared by the GC (general contractor) and submitted for approval, include
- Project Schedule
- Health and Safety Policy & Program
- MOL form 1000 (Registration of Constructors & Employers Engaged in Construction)
- Certificate of Liability Insurance
- Proof of WSIB Registration
- Schedule of Values
- Statutory Declaration
MOL Form 1000
- In Ontario, the Ministry of Labour, Immigration, Training, and Skills Development (formerly Ministry of Labour) is responsible for labor-related affairs, including employment standards, occupational health and safety, and workers' rights.
- Each contractor/employer in Ontario must complete MOL Form 1000, Registration of Constructors and Employers Engaged in Construction, and this form must be physically present at the project site.
Proof of WSIB Registration
- WSIB stands for the Workplace Safety and Insurance Board.
- WSIB registration is the process by which employers register with a government agency responsible for worker compensation and workplace safety and insurance in the province.
- Registration process includes completing an online application or direct contact with WSIB
- Compulsory in Ontario; required for safety and compensation to workers
- Includes information such as business type, number of employees, the nature of work, and payroll details
- Payment of premiums to WSIB, based on business type, industry, and payroll amounts, funds the workers' compensation system.
- Requires an annual reconciliation statement and the relevant payroll information, including details for the annual premium payments
- Compliance with health and safety regulations is paramount for preventing workplace accidents and injuries.
Schedule of Values (SOV)
-
A Schedule of Values (SOV) is a detailed breakdown of total contract amounts into individual line items/categories, each representing a portion of the work—for a given construction project.
-
Each detailed line item is associated with a dollar amount, representing the value/cost of each work/activity
-
Total Sum of all individual line items equals the total contract amount
-
SOV is used for billing, payment, budgeting, and cost control, as well as progress tracking and documentation of project costs.
-
Used to track the progress of the construction project, where different parts of the project are completed, in progress, or yet to start
-
Project stakeholders (contract administrator and contractor), use the SOV to manage progress, payments, and control costs.
-
If any changes to the scope of the project occur during the progress of the project, the SOV can be updated to reflect these changes
-
The schedule of values serves as a formal document, preventing disputes and misunderstandings arising in the construction project
Unit Prices/Unit Rates
- Schedule of Values (SOV) used to calculate units (like doors, windows, pavement, etc.)
- The total costs of labor, materials, equipment, and profit are included in the unit prices
- These prices help owners effectively compare bids from varied contractors
Statutory Declaration
- Statutory declaration—is a sworn affidavit usually made by the contractor.
- Made in written format
- Deponent/individual making the declaration says information is true and accurate
- Legal action is a possibility, upon conviction, if the declaration is not done correctly
- Required from contractors for progress payments as well as lien claim purposes
- It's mandatory to provide this declaration from the 2nd progress payment onwards
Holdbacks
- Holdback is money that the owner holds back from payments due to contractors according to their contract
- Statutory holdback (10% of progress payment): required by the Construction Lien Act—to safeguard the owner from lien claims.
- A separate holdback account is specifically for this money.
- Release of the holdback: usually 45 days after the newspaper publication of substantial completion of the project; but not if a lien is still pending for the property
- Deficiency holdback: optional, additional holdback negotiated between contractor and owner, above the 10%
- Holdback is released to the contractor at a later stage when certain conditions are met
Substantial Completion
- Substantial completion definition of a contract in reference to section 2 (1) of the Construction Lien Act
- Indicates that the contract or the substantial portion of the contract is ready for use(or being used) based on its intended purpose
- Calculation of Substantial Completion
- Based on the contract amount, with limits to defects (not more than 3% of the first 1 million, 2 percent of the next million and 1 percent of the remaining contract amount for the final calculation)
- Certificate of Substantial Completion issued by the contract administrator after substantial completion of work
- A published date is included in the substantial completion certificate to start a 45-day hold back or release of 10% statutory hold back.
- Sets the start of the contract warranty period and stops possible liquidated damage liabilities
Progress Payments
- Applications for progress payments are normally done monthly by the general contractor to the contract administrator
- General contractors will consolidate invoices from trades, suppliers, etc., at the end of each month and submit for approval before progress payments can be made
- Once approved, the owner issues a payment check, which is paid out directly to the required trades/suppliers by the general contractor.
- Timeline to process progress payments approximately 30-45 days.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Related Documents
Description
This quiz covers the essential requirements and documents necessary for handling progress payments in construction projects, as outlined in Lecture 7. It emphasizes the importance of compliance with the Construction Lien Act and the preparation of various start-up documents by general contractors.