Calculating Latest Start Time for Project Activities
3 Questions
1 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

What method can the project manager use to calculate the latest start time of each activity?

  • Backward Pass (correct)
  • Forward pass
  • Earliest start time (EST)
  • Total Float
  • Which term refers to the duration of each activity in the project?

  • Backward Pass
  • Total Float
  • Forward pass (correct)
  • Earliest start time (EST)
  • What does the project manager need to calculate the latest start time of each activity?

  • Backward Pass
  • Total Float (correct)
  • Earliest start time (EST)
  • Forward pass
  • Study Notes

    Calculating Latest Start Time

    • The project manager can calculate the latest start time of each activity using the backward pass method.

    Activity Duration

    • The term activity duration refers to the length of time required to complete an activity in the project.

    Calculating Latest Start Time Requirements

    • To calculate the latest start time of each activity, the project manager needs to know the latest finish time of each activity and its duration.

    Studying That Suits You

    Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

    Quiz Team

    Description

    Learn how a project manager can calculate the latest start time for each activity in a project by using backward pass technique. Understand the process of determining the latest possible start time to ensure project completion within the given duration.

    More Like This

    Master Project Scheduling Techniques
    10 questions

    Master Project Scheduling Techniques

    WellPositionedChrysoprase avatar
    WellPositionedChrysoprase
    PTT Week 4 - Scheduling
    50 questions
    Project Scheduling Techniques
    45 questions
    Use Quizgecko on...
    Browser
    Browser