This document contains practice questions and answers on project management topics, including cost estimation, risk management, and project planning. The questions cover a variety of scenarios and their corresponding solutions.
Full Transcript
A project involves multiple international locations with fluctuating exchange rates. Cost estimates are calculated in local currencies and aggregated. What should the project manager do to manage cost variability?\ a. Include a contingency reserve specifically for exchange rate fluctuations.\ b. Con...
A project involves multiple international locations with fluctuating exchange rates. Cost estimates are calculated in local currencies and aggregated. What should the project manager do to manage cost variability?\ a. Include a contingency reserve specifically for exchange rate fluctuations.\ b. Convert all estimates to a single currency without adding a reserve.\ c. Use historical exchange rates and update them during project execution.\ d. Monitor exchange rates but make no adjustments to the budget.\ Correct Answer: A A project manager notices that indirect costs have been underestimated. The organization has strict cost baselines. What is the best way to address this?\ a. Adjust the cost baseline by reallocating unused direct costs.\ b. Request an increase in the contingency reserve to cover indirect costs.\ c. Revise indirect cost estimates and submit a change request for baseline adjustment.\ d. Absorb the additional costs into the management reserve.\ Correct Answer: C A task on the critical path requires specialized equipment. Renting the equipment for the estimated duration exceeds the task's budget. What should the project manager do?\ a. Reevaluate the duration of the task using bottom-up estimating.\ b. Reduce the scope of the task to align with the budget.\ c. Submit a request to increase the task's budget.\ d. Explore alternative equipment providers or sharing agreements.\ Correct Answer: D The team is using parametric estimating for a construction project. A stakeholder questions the accuracy of the estimates. How should the project manager respond?\ a. Validate the parameters with historical data and provide supporting documentation.\ b. Switch to analogous estimating to address the stakeholder\'s concerns.\ c. Increase the contingency reserve to accommodate possible inaccuracies.\ d. Reduce the level of detail in the estimate to simplify explanations.\ Correct Answer: A A project's cost baseline includes contingency reserves for known risks. A new risk emerges that requires immediate funding. How should the project manager proceed?\ a. Use the management reserve to address the new risk.\ b. Reallocate funds from the contingency reserve.\ c. Absorb the cost into the project budget without adjustments.\ d. Request additional funding from the sponsor.\ Correct Answer: A A project manager needs to prioritize tasks for a sprint backlog. The team is using relative estimation with the Fibonacci sequence. What should the project manager focus on?\ a. Assign story points based on the complexity and effort required for each task.\ b. Estimate all tasks with absolute time commitments instead of story points.\ c. Use the same story points for all tasks to avoid discrepancies.\ d. Ignore relative estimation and focus on delivering tasks sequentially.\ Correct Answer: A A project has a fixed budget, but new requirements have increased the scope. How should the project manager manage the cost baseline?\ a. Prioritize the requirements and trade off lower-value items.\ b. Add a management reserve to the budget to cover additional costs.\ c. Use contingency reserves for all new requirements.\ d. Submit a change request to increase the project budget.\ Correct Answer: A A team member suggests using historical data from a similar project to estimate costs. The historical data lacks documentation on assumptions. What should the project manager do?\ a. Use the data with a high level of contingency to account for unknowns.\ b. Disregard the data and switch to bottom-up estimating.\ c. Validate assumptions with stakeholders and update the estimates accordingly.\ d. Use the data without adjustments to save time.\ Correct Answer: C A new subcontractor for a high-risk task is quoting significantly lower rates than the industry standard. What should the project manager prioritize?\ a. Perform a cost-benefit analysis and assess risks before selecting the subcontractor.\ b. Accept the quote and allocate the savings to other project tasks.\ c. Negotiate a fixed-price contract with the subcontractor.\ d. Reject the subcontractor and use an established vendor.\ Correct Answer: A The project sponsor insists on tracking cost performance using Earned Value Management (EVM). Team members are unfamiliar with EVM concepts. How should the project manager proceed?\ a. Provide EVM training to the team and integrate it into the cost control process.\ b. Use simpler methods for cost tracking and justify their effectiveness.\ c. Outsource cost tracking to an EVM expert.\ d. Adjust the project's cost management plan to exclude EVM.\ Correct Answer: A A project manager needs to allocate contingency reserves across multiple high-risk tasks. What is the most effective approach?\ a. Use a risk-adjusted method to allocate reserves based on the probability and impact of each risk.\ b. Divide the contingency reserve equally among all high-risk tasks.\ c. Focus on allocating reserves to tasks on the critical path only.\ d. Request additional reserves for all high-risk tasks.\ Correct Answer: A A virtual team faces challenges due to overlapping resource assignments, leading to cost overruns. What is the best solution?\ a. Use resource leveling to balance workloads and optimize resource utilization.\ b. Increase the budget to accommodate the additional costs.\ c. Reassign resources without considering their workload.\ d. Delay the schedule to resolve resource conflicts.\ Correct Answer: A A project manager is managing a large IT project with a fixed price contract. Midway through the project, a supplier requests additional funding due to unforeseen material costs. How should the project manager respond?\ a. Review the supplier's contract terms and enforce the agreed fixed price.\ b. Approve the additional funding to avoid delays.\ c. Escalate the issue to the sponsor for resolution.\ d. Negotiate a compromise that balances the supplier\'s needs and the project budget.\ Correct Answer: A During resource planning, the project manager discovers that a critical resource is consistently overallocated due to commitments on multiple projects. How should the project manager address this?\ a. Use resource leveling to adjust their workload across projects.\ b. Replace the resource with a less experienced team member to free their time.\ c. Delay critical tasks until the resource becomes available.\ d. Focus on reducing their workload on non-critical projects.\ Correct Answer: A A key deliverable has a highly variable cost due to unpredictable market conditions. The team has provided a cost range instead of a fixed estimate. How should the project manager handle this in the cost baseline?\ a. Use the pessimistic estimate and allocate a contingency reserve to cover variability.\ b. Request a fixed estimate to simplify the budget.\ c. Average the cost range and use it as the baseline.\ d. Exclude the deliverable from the baseline until costs stabilize.\ Correct Answer: A A sponsor insists on reducing the project budget while maintaining all deliverables. What should the project manager prioritize?\ a. Facilitate a value engineering session to identify cost-saving opportunities.\ b. Reduce quality standards to align with the new budget.\ c. Request that the sponsor eliminate lower-priority deliverables.\ d. Add additional resources to meet the reduced budget timeline.\ Correct Answer: A A project team is preparing a bottom-up cost estimate. The sponsor asks for a high-level estimate immediately. How should the project manager handle this?\ a. Provide a rough order of magnitude (ROM) estimate and refine it later.\ b. Delay responding until the bottom-up estimate is complete.\ c. Use parametric estimating to generate a quick estimate.\ d. Exclude contingency reserves to accelerate the estimate process.\ Correct Answer: A During cost monitoring, the project manager identifies a CPI (Cost Performance Index) of 0.85. What does this indicate, and what should the project manager do?\ a. The project is over budget; identify areas to reduce costs without compromising scope.\ b. The project is under budget; allocate surplus funds to enhance quality.\ c. The project is on track; continue executing the cost management plan.\ d. Reallocate contingency reserves to non-critical tasks.\ Correct Answer: A A high-value resource requests additional compensation midway through the project due to market demand. How should the project manager address this?\ a. Evaluate the impact of the request on the budget and negotiate a fair agreement.\ b. Approve the compensation increase to maintain resource engagement.\ c. Replace the resource with a less expensive alternative.\ d. Deny the request to preserve the cost baseline.\ Correct Answer: A A project manager is overseeing a research project funded by a government grant. The funding agency requires strict cost reporting and evidence of expense alignment with project objectives. What is the best approach?\ a. Implement detailed cost tracking with regular audits to ensure compliance.\ b. Use simplified cost tracking and provide high-level reports to save time.\ c. Allocate all costs to a general category for easier reporting.\ d. Delay reporting until project completion for comprehensive documentation.\ Correct Answer: A The project sponsor requests a cost forecast for the next quarter, but some activities have highly uncertain costs due to dependencies on external vendors. How should the project manager proceed?\ a. Use three-point estimating to provide a range of forecasts and communicate uncertainties.\ b. Submit a forecast based only on optimistic estimates to satisfy the sponsor.\ c. Exclude uncertain costs from the forecast and revisit them later.\ d. Request additional time to finalize all estimates before providing a forecast.\ Correct Answer: A A project has significant risk events that could drastically increase costs. What is the best way to reflect these risks in the project budget?\ a. Allocate contingency reserves based on quantitative risk analysis.\ b. Add a flat 10% increase to the overall budget for risk events.\ c. Include risk costs as part of the direct costs for each task.\ d. Address risks during project execution rather than during budgeting.\ Correct Answer: A A critical supplier's costs have increased by 15%, impacting the project budget. What is the best response?\ a. Negotiate with the supplier to lock in costs or seek alternative suppliers.\ b. Absorb the additional cost into the contingency reserve.\ c. Submit a change request to increase the project budget.\ d. Reassign tasks to internal resources to eliminate reliance on the supplier.\ Correct Answer: A A project is 30% complete, and the team's EAC (Estimate at Completion) is higher than the original budget. What should the project manager focus on?\ a. Analyze the root cause of the variance and implement corrective actions.\ b. Accept the variance and request additional funds from the sponsor.\ c. Reduce the project scope to align with the original budget.\ d. Ignore the variance and proceed with the current cost management plan.\ Correct Answer: A The project sponsor requests a variance report that explains deviations from the cost baseline. The report shows both positive and negative variances. What is the best way to present this?\ a. Highlight significant variances and explain their root causes, linking them to project risks.\ b. Focus only on positive variances to demonstrate cost savings.\ c. Combine all variances into an average and present it as a single figure.\ d. Exclude minor variances to simplify the report.\ Correct Answer: A The team is using analogous estimating for a new project phase, but a team member questions its accuracy due to differences in project scope. How should the project manager address this?\ a. Adjust the estimates to account for scope differences and validate assumptions.\ b. Switch to bottom-up estimating to improve accuracy.\ c. Use the same estimate and apply contingency to account for discrepancies.\ d. Ignore the concerns and proceed with analogous estimates.\ Correct Answer: A A project manager notices that team members are consistently logging fewer hours than planned. What should the project manager do first?\ a. Investigate the cause of the discrepancy to ensure accurate cost tracking.\ b. Reduce task budgets to reflect the lower effort.\ c. Reallocate saved hours to non-critical tasks.\ d. Add the saved hours to the management reserve.\ Correct Answer: A A key stakeholder insists on using the lowest bidder for a critical project task to save costs. The team raises concerns about quality. How should the project manager proceed?\ a. Conduct a cost-benefit analysis to assess the trade-off between cost and quality.\ b. Accept the lowest bid to align with the stakeholder's request.\ c. Add additional quality checks to mitigate risks associated with the lowest bidder.\ d. Propose using the second-lowest bidder to balance cost and quality.\ Correct Answer: A A project's burn rate exceeds the planned rate, but there are no significant variances in deliverable completion. What should the project manager focus on?\ a. Review resource utilization and indirect cost allocations for inefficiencies.\ b. Request additional funds to address the increased burn rate.\ c. Delay future tasks to control spending.\ d. Reallocate contingency reserves to offset the burn rate.\ Correct Answer: A A project has fixed labor costs but flexible material costs. Material prices are rising due to market conditions. How should the project manager mitigate this risk?\ a. Lock in material prices through long-term contracts with suppliers.\ b. Absorb the rising costs into the project's contingency reserve.\ c. Request additional funding to cover the price increase.\ d. Delay material procurement until prices stabilize.\ Correct Answer: A A project manager discovers that the Earned Value (EV) for a critical task is lower than its Planned Value (PV), but the Actual Cost (AC) is significantly higher. How should this be addressed?\ a. Analyze the root cause of the cost overrun and adjust the task schedule or resource allocation.\ b. Increase the budget for the task to accommodate the additional costs.\ c. Reallocate resources from non-critical tasks to the critical task.\ d. Focus on completing other tasks to balance the project's cost performance.\ **Correct Answer**: A A project team has underestimated the learning curve for using a new technology, leading to increased labor costs. What should the project manager prioritize?\ a. Allocate additional funds from the contingency reserve for training and extended timelines.\ b. Negotiate with the sponsor for additional resources to expedite learning.\ c. Replace team members with experts in the new technology.\ d. Reduce project scope to balance the increased costs.\ **Correct Answer**: A A project sponsor requests a cost breakdown for a key deliverable. The breakdown reveals that overhead costs are disproportionately high. What should the project manager focus on?\ a. Evaluate and optimize overhead allocations to reduce the cost burden.\ b. Shift overhead costs to contingency reserves.\ c. Justify the overhead costs as part of the project's fixed expenses.\ d. Eliminate overhead costs from the deliverable to reduce overall expenses.\ **Correct Answer**: A During execution, a team identifies a task requiring higher-than-expected resource effort, but reallocating resources risks delaying another critical task. How should the project manager proceed?\ a. Apply crashing to reduce the duration of the critical task and reallocate resources.\ b. Extend the schedule to allow for additional resource effort on the non-critical task.\ c. Focus on completing the critical task on time and absorb delays on the non-critical task.\ d. Use resource smoothing to minimize overall delays.\ **Correct Answer**: A A project has been running under budget due to efficient resource utilization. The sponsor suggests reallocating surplus funds to add new features. What should the project manager do?\ a. Evaluate the feasibility of the new features and their alignment with project objectives before reallocating funds.\ b. Reject the sponsor's request to preserve the original cost baseline.\ c. Allocate the surplus funds directly to contingency reserves for future risks.\ d. Use the funds to enhance the quality of existing deliverables instead of adding features.\ **Correct Answer**: A A contractor responsible for a critical component has delayed delivery, and their payment is tied to milestones. What is the best way to manage this issue?\ a. Negotiate milestone adjustments with the contractor to align payments with revised timelines.\ b. Withhold all payments until the contractor delivers the component.\ c. Advance partial payments to motivate the contractor.\ d. Replace the contractor with an alternative vendor to maintain the schedule.\ **Correct Answer**: A A team is tracking their CPI (Cost Performance Index) and SPI (Schedule Performance Index). The project currently has a CPI of 1.1 and an SPI of 0.9. How should the project manager interpret and act on this data?\ a. Address schedule delays while maintaining cost efficiency by reallocating resources.\ b. Focus on reducing costs to align the CPI with the SPI.\ c. Delay critical path activities to improve the SPI.\ d. Shift resources from cost-saving measures to non-critical tasks.\ **Correct Answer**: A A project team has used all contingency reserves for known risks, but additional costs are arising due to unforeseen risks. How should the project manager proceed?\ a. Access the management reserve to address unforeseen risks.\ b. Reduce project scope to accommodate the additional costs.\ c. Negotiate with the sponsor for additional contingency reserves.\ d. Absorb the costs into the existing cost baseline.\ **Correct Answer**: A The project sponsor demands cost reductions in a resource-intensive phase. The team suggests automating a repetitive task, but the upfront costs are high. What should the project manager prioritize?\ a. Conduct a cost-benefit analysis to determine if automation will yield long-term savings.\ b. Reject the automation proposal to avoid immediate cost increases.\ c. Delay the resource-intensive phase to explore other cost-cutting measures.\ d. Reduce resource allocation without considering automation.\ **Correct Answer**: A A project requires hiring temporary contractors for peak workloads. However, the hourly rates are much higher than initially budgeted. How should the project manager handle this?\ a. Negotiate a bulk discount or long-term contract with the contractors.\ b. Absorb the higher rates into the project budget without changes.\ c. Reallocate internal resources to reduce reliance on contractors.\ d. Eliminate non-critical tasks to offset the cost increase.\ **Correct Answer**: A A fixed-price contract includes cost penalties for late delivery. A vendor informs the project manager that delays are unavoidable due to supply chain disruptions. What is the best course of action?\ a. Renegotiate the contract terms to account for external delays.\ b. Impose the penalties and find alternative suppliers.\ c. Absorb the penalties into the project's contingency reserve.\ d. Request the sponsor's intervention to waive the penalties.\ **Correct Answer**: A The project team's cost estimates are consistently lower than the actuals for completed tasks. What should the project manager prioritize to address this trend?\ a. Revisit the estimating methodology and include contingency for future tasks.\ b. Continue using the same methodology and adjust the baseline as needed.\ c. Shift to analogous estimating to simplify cost predictions.\ d. Reallocate funds from non-critical tasks to cover the overruns.\ **Correct Answer**: A A project requires purchasing specialized software. The licensing costs exceed the initial budget allocation. What is the best way to resolve this?\ a. Request additional funds through a formal change request.\ b. Negotiate a lower licensing cost with the software vendor.\ c. Replace the software with an open-source alternative.\ d. Delay software purchase until sufficient funds are available.\ **Correct Answer**: A A resource optimization plan reduces costs by consolidating roles. However, the workload increases for critical team members, leading to burnout risks. What should the project manager do?\ a. Use resource smoothing to balance workloads while maintaining cost efficiency.\ b. Revert to the original resource plan to reduce workload stress.\ c. Add contingency funds to hire additional resources temporarily.\ d. Assign non-critical tasks to junior team members without balancing workloads.\ **Correct Answer**: A The project is on track for cost and schedule, but the management reserve has been partially used. The sponsor requests a report on reserve utilization. How should the project manager handle this?\ a. Provide a detailed report explaining how the reserve was used and remaining risks.\ b. Avoid reporting partial reserve usage to minimize sponsor concerns.\ c. Request additional reserves to cover remaining project risks.\ d. Use the contingency reserve to restore the management reserve balance.\ **Correct Answer**: A A contractor offers a discount if the project pays in advance for services. This reduces costs but increases financial risk. How should the project manager proceed?\ a. Evaluate the risks of advance payment and propose a partial advance payment as a compromise.\ b. Reject the discount offer to avoid financial risk.\ c. Accept the advance payment terms and reallocate saved funds.\ d. Use contingency reserves to secure the payment.\ **Correct Answer**: A A cost performance review shows that one high-value task is consistently under budget. The sponsor suggests reallocating these funds to another phase. How should the project manager respond?\ a. Retain the surplus funds in the task budget to absorb potential future risks.\ b. Approve the reallocation to align with the sponsor's request.\ c. Move the funds to the management reserve for flexibility.\ d. Request a change control process to adjust the budget formally.\ **Correct Answer**: D A project nearing completion shows an SPI (Schedule Performance Index) of 1.05 and a CPI (Cost Performance Index) of 0.95. How should the project manager interpret this?\ a. The project is ahead of schedule but over budget; focus on reducing future costs.\ b. The project is under budget and on track; continue as planned.\ c. The project is delayed but within budget; focus on catching up on schedule.\ d. Reallocate contingency reserves to address cost overruns.\ **Correct Answer**: A A sponsor demands cost reductions on a resource-heavy phase of the project. The project manager identifies that automating a process will require significant upfront costs but long-term savings. How should they proceed?\ a. Conduct a detailed cost-benefit analysis and present the findings to the sponsor.\ b. Absorb the upfront costs and proceed with automation to meet long-term savings.\ c. Reject the automation due to immediate cost constraints.\ d. Delay automation and manually manage tasks to meet short-term budget goals.\ **Correct Answer**: A A project team has completed 40% of the project, and EAC (Estimate at Completion) forecasts show the total cost to exceed the budget. What is the best course of action?\ a. Reassess remaining tasks and implement cost-saving measures where possible.\ b. Increase the project budget to align with the EAC forecast.\ c. Submit a change request to reduce the project scope.\ d. Use management reserves to offset the forecasted overruns.\ **Correct Answer**: A