FPM WEEK 7 - Scenario
45 Questions
0 Views

Choose a study mode

Play Quiz
Study Flashcards
Spaced Repetition
Chat to Lesson

Podcast

Play an AI-generated podcast conversation about this lesson

Questions and Answers

A project involves multiple international locations with fluctuating exchange rates. Cost estimates are calculated in local currencies and aggregated. What should the project manager do to manage cost variability?

  • Use historical exchange rates and update them during project execution.
  • Convert all estimates to a single currency without adding a reserve.
  • Monitor exchange rates but make no adjustments to the budget.
  • Include a contingency reserve specifically for exchange rate fluctuations. (correct)

A project manager notices that indirect costs have been underestimated. The organization has strict cost baselines. What is the best way to address this?

  • Request an increase in the contingency reserve to cover indirect costs.
  • Absorb the additional costs into the management reserve.
  • Adjust the cost baseline by reallocating unused direct costs.
  • Revise indirect cost estimates and submit a change request for baseline adjustment. (correct)

A task on the critical path requires specialized equipment. Renting the equipment for the estimated duration exceeds the task's budget. What should the project manager do?

  • Submit a request to increase the task's budget.
  • Explore alternative equipment providers or sharing agreements. (correct)
  • Reevaluate the duration of the task using bottom-up estimating.
  • Reduce the scope of the task to align with the budget.

A project manager needs to prioritize tasks for a sprint backlog. The team is using relative estimation with the Fibonacci sequence. What should the project manager focus on?

<p>Assign story points based on the complexity and effort required for each task. (D)</p> Signup and view all the answers

A project has a fixed budget, but new requirements have increased the scope. How should the project manager manage the cost baseline?

<p>Prioritize the requirements and trade off lower-value items. (D)</p> Signup and view all the answers

A team member suggests using historical data from a similar project to estimate costs. The historical data lacks documentation on assumptions. What should the project manager do?

<p>Validate assumptions with stakeholders and update the estimates accordingly. (B)</p> Signup and view all the answers

A new subcontractor for a high-risk task is quoting significantly lower rates than the industry standard. What should the project manager prioritize?

<p>Perform a cost-benefit analysis and assess risks before selecting the subcontractor. (C)</p> Signup and view all the answers

The project sponsor insists on tracking cost performance using Earned Value Management (EVM). Team members are unfamiliar with EVM concepts. How should the project manager proceed?

<p>Provide EVM training to the team and integrate it into the cost control process. (D)</p> Signup and view all the answers

A project manager needs to allocate contingency reserves across multiple high-risk tasks. What is the most effective approach?

<p>Use a risk-adjusted method to allocate reserves based on the probability and impact of each risk. (C)</p> Signup and view all the answers

A virtual team faces challenges due to overlapping resource assignments, leading to cost overruns. What is the best solution?

<p>Use resource leveling to balance workloads and optimize resource utilization. (B)</p> Signup and view all the answers

A project manager is managing a large IT project with a fixed price contract. Midway through the project, a supplier requests additional funding due to unforeseen material costs. How should the project manager respond?

<p>Review the supplier's contract terms and enforce the agreed fixed price. (C)</p> Signup and view all the answers

During resource planning, the project manager discovers that a critical resource is consistently overallocated due to commitments on multiple projects. How should the project manager address this?

<p>Use resource leveling to adjust their workload across projects. (A)</p> Signup and view all the answers

A key deliverable has a highly variable cost due to unpredictable market conditions. The team has provided a cost range instead of a fixed estimate. How should the project manager handle this in the cost baseline?

<p>Use the pessimistic estimate and allocate a contingency reserve to cover variability. (C)</p> Signup and view all the answers

A sponsor insists on reducing the project budget while maintaining all deliverables. What should the project manager prioritize?

<p>Facilitate a value engineering session to identify cost-saving opportunities. (D)</p> Signup and view all the answers

A project team is preparing a bottom-up cost estimate. The sponsor asks for a high-level estimate immediately. How should the project manager handle this?

<p>Provide a rough order of magnitude (ROM) estimate and refine it later. (C)</p> Signup and view all the answers

During cost monitoring, the project manager identifies a CPI (Cost Performance Index) of 0.85. What does this indicate, and what should the project manager do?

<p>The project is over budget; identify areas to reduce costs without compromising scope. (C)</p> Signup and view all the answers

A high-value resource requests additional compensation midway through the project due to market demand. How should the project manager address this?

<p>Evaluate the impact of the request on the budget and negotiate a fair agreement. (D)</p> Signup and view all the answers

A project manager is overseeing a research project funded by a government grant. The funding agency requires strict cost reporting and evidence of expense alignment with project objectives. What is the best approach?

<p>Implement detailed cost tracking with regular audits to ensure compliance. (D)</p> Signup and view all the answers

The project sponsor requests a cost forecast for the next quarter, but some activities have highly uncertain costs due to dependencies on external vendors. How should the project manager proceed?

<p>Use three-point estimating to provide a range of forecasts and communicate uncertainties. (D)</p> Signup and view all the answers

A project has significant risk events that could drastically increase costs. What is the best way to reflect these risks in the project budget?

<p>Allocate contingency reserves based on quantitative risk analysis. (B)</p> Signup and view all the answers

A critical supplier's costs have increased by 15%, impacting the project budget. What is the best response?

<p>Negotiate with the supplier to lock in costs or seek alternative suppliers. (B)</p> Signup and view all the answers

A project is 30% complete, and the team's EAC (Estimate at Completion) is higher than the original budget. What should the project manager focus on?

<p>Analyze the root cause of the variance and implement corrective actions. (D)</p> Signup and view all the answers

The project sponsor requests a variance report that explains deviations from the cost baseline. The report shows both positive and negative variances. What is the best way to present this?

<p>Highlight significant variances and explain their root causes, linking them to project risks. (C)</p> Signup and view all the answers

The team is using analogous estimating for a new project phase, but a team member questions its accuracy due to differences in project scope. How should the project manager address this?

<p>Adjust the estimates to account for scope differences and validate assumptions. (B)</p> Signup and view all the answers

A project manager notices that team members are consistently logging fewer hours than planned. What should the project manager do first?

<p>Investigate the cause of the discrepancy to ensure accurate cost tracking. (D)</p> Signup and view all the answers

A key stakeholder insists on using the lowest bidder for a critical project task to save costs. The team raises concerns about quality. How should the project manager proceed?

<p>Conduct a cost-benefit analysis to assess the trade-off between cost and quality. (A)</p> Signup and view all the answers

A project's burn rate exceeds the planned rate, but there are no significant variances in deliverable completion. What should the project manager focus on?

<p>Review resource utilization and indirect cost allocations for inefficiencies. (A)</p> Signup and view all the answers

A project has fixed labor costs but flexible material costs. Material prices are rising due to market conditions. How should the project manager mitigate this risk?

<p>Lock in material prices through long-term contracts with suppliers. (C)</p> Signup and view all the answers

A project manager discovers that the Earned Value (EV) for a critical task is lower than its Planned Value (PV), but the Actual Cost (AC) is significantly higher. How should this be addressed?

<p>Analyze the root cause of the cost overrun and adjust the task schedule or resource allocation. (A)</p> Signup and view all the answers

A project team has underestimated the learning curve for using a new technology, leading to increased labor costs. What should the project manager prioritize?

<p>Allocate additional funds from the contingency reserve for training and extended timelines. (A)</p> Signup and view all the answers

A project sponsor requests a cost breakdown for a key deliverable. The breakdown reveals that overhead costs are disproportionately high. What should the project manager focus on?

<p>Evaluate and optimize overhead allocations to reduce the cost burden. (A)</p> Signup and view all the answers

During execution, a team identifies a task requiring higher-than-expected resource effort, but reallocating resources risks delaying another critical task. How should the project manager proceed?

<p>Apply crashing to reduce the duration of the critical task and reallocate resources. (C)</p> Signup and view all the answers

A project has been running under budget due to efficient resource utilization. The sponsor suggests reallocating surplus funds to add new features. What should the project manager do?

<p>Evaluate the feasibility of the new features and their alignment with project objectives before reallocating funds. (B)</p> Signup and view all the answers

A contractor responsible for a critical component has delayed delivery, and their payment is tied to milestones. What is the best way to manage this issue?

<p>Negotiate milestone adjustments with the contractor to align payments with revised timelines. (D)</p> Signup and view all the answers

A team is tracking their CPI (Cost Performance Index) and SPI (Schedule Performance Index). The project currently has a CPI of 1.1 and an SPI of 0.9. How should the project manager interpret and act on this data?

<p>Address schedule delays while maintaining cost efficiency by reallocating resources. (A)</p> Signup and view all the answers

A project team has used all contingency reserves for known risks, but additional costs are arising due to unforeseen risks. How should the project manager proceed?

<p>Access the management reserve to address unforeseen risks. (A)</p> Signup and view all the answers

The project sponsor demands cost reductions in a resource-intensive phase. The team suggests automating a repetitive task, but the upfront costs are high. What should the project manager prioritize?

<p>Conduct a cost-benefit analysis to determine if automation will yield long-term savings. (A)</p> Signup and view all the answers

A project requires hiring temporary contractors for peak workloads. However, the hourly rates are much higher than initially budgeted. How should the project manager handle this?

<p>Negotiate a bulk discount or long-term contract with the contractors. (C)</p> Signup and view all the answers

A fixed-price contract includes cost penalties for late delivery. A vendor informs the project manager that delays are unavoidable due to supply chain disruptions. What is the best course of action?

<p>Renegotiate the contract terms to account for external delays. (B)</p> Signup and view all the answers

The project team's cost estimates are consistently lower than the actuals for completed tasks. What should the project manager prioritize to address this trend?

<p>Revisit the estimating methodology and include contingency for future tasks. (C)</p> Signup and view all the answers

A project requires purchasing specialized software. The licensing costs exceed the initial budget allocation. What is the best way to resolve this?

<p>Request additional funds through a formal change request. (C)</p> Signup and view all the answers

A resource optimization plan reduces costs by consolidating roles. However, the workload increases for critical team members, leading to burnout risks. What should the project manager do?

<p>Use resource smoothing to balance workloads while maintaining cost efficiency. (D)</p> Signup and view all the answers

The project is on track for cost and schedule, but the management reserve has been partially used. The sponsor requests a report on reserve utilization. How should the project manager handle this?

<p>Provide a detailed report explaining how the reserve was used and remaining risks. (C)</p> Signup and view all the answers

A contractor offers a discount if the project pays in advance for services. This reduces costs but increases financial risk. How should the project manager proceed?

<p>Evaluate the risks of advance payment and propose a partial advance payment as a compromise. (C)</p> Signup and view all the answers

A cost performance review shows that one high-value task is consistently under budget. The sponsor suggests reallocating these funds to another phase. How should the project manager respond?

<p>Request a change control process to adjust the budget formally. (A)</p> Signup and view all the answers

Flashcards

Contingency Reserve for Exchange Rates

A reserve specifically for unexpected exchange rate fluctuations. It helps manage cost variability when projects operate in multiple international locations with fluctuating exchange rates.

Adjusting Cost Baseline for Indirect Costs

The process of adjusting the cost baseline by re-evaluating indirect cost estimates and submitting a change request for approval. This ensures the project's budget accurately reflects the actual indirect cost requirements.

Finding Alternative Equipment Solutions

Exploring alternative equipment providers or sharing agreements to find a cost-effective solution when renting specialized equipment exceeds the task's budget.

Validating Parametric Estimates

Using historical data to validate the parameters used in parametric estimating and provide supporting documentation. This addresses stakeholder concerns about the accuracy of the estimates.

Signup and view all the flashcards

Using Management Reserve for New Risks

The use of the management reserve to address unexpected risks that require immediate funding. This utilizes a predefined safety net for unforeseen events that fall outside the scope of known risks.

Signup and view all the flashcards

Prioritizing Tasks with Story Points

Assigning story points based on the complexity and effort required for each task. Using relative estimation with the Fibonacci sequence allows prioritizing tasks effectively in a sprint backlog.

Signup and view all the flashcards

Prioritizing Requirements in Fixed Budget

Prioritizing requirements and trading off lower-value items to manage the cost baseline when new requirements increase the scope of a project with a fixed budget.

Signup and view all the flashcards

Validating Assumptions in Historical Data

Validating assumptions with stakeholders and updating cost estimates based on the collected information when using historical data for cost estimation.

Signup and view all the flashcards

Prioritizing Cost-Benefit Analysis for Subcontractors

Performing a cost-benefit analysis and assessing risks before selecting a subcontractor offering significantly lower rates. This balances cost saving with project success.

Signup and view all the flashcards

Training Team on EVM for Cost Tracking

Providing EVM training to the team and integrating it into the cost control process when the sponsor insists on using EVM, even if the team is unfamiliar with the concepts.

Signup and view all the flashcards

Allocating Contingency Reserves Based on Risk

Using a risk-adjusted method to allocate contingency reserves based on the probability and impact of each risk. This ensures effective risk management and prioritizes high-risk tasks.

Signup and view all the flashcards

Resource Leveling for Virtual Teams

Using resource leveling to balance workloads and optimize resource utilization when a virtual team faces challenges due to overlapping resource assignments leading to cost overruns.

Signup and view all the flashcards

Enforcing Fixed Price in Contracts

Reviewing the supplier's contract terms and enforcing the agreed fixed price when a supplier requests additional funding due to unforeseen material costs in a fixed-price contract.

Signup and view all the flashcards

Resource Leveling for Overallocated Resources

Using resource leveling to adjust the workload across projects when a critical resource is consistently overallocated due to commitments on multiple projects.

Signup and view all the flashcards

Managing Variable Costs with Contingency

Using the pessimistic estimate and allocating a contingency reserve to cover variability when a key deliverable has a highly variable cost due to unpredictable market conditions.

Signup and view all the flashcards

Value Engineering for Budget Reduction

Facilitating a value engineering session to identify cost-saving opportunities when a sponsor insists on reducing the project budget while maintaining all deliverables.

Signup and view all the flashcards

Providing ROM Estimate

Providing a rough order of magnitude (ROM) estimate and refining it later when a sponsor asks for a high-level estimate but the team is preparing a bottom-up cost estimate.

Signup and view all the flashcards

Addressing Cost Overruns

Identifying areas to reduce costs without compromising scope when the Cost Performance Index (CPI) indicates the project is over budget.

Signup and view all the flashcards

Negotiating Resource Compensation

Evaluating the impact of the request on the budget and negotiating a fair agreement when a high-value resource requests additional compensation midway through the project.

Signup and view all the flashcards

Detailed Cost Tracking for Grants

Implementing detailed cost tracking with regular audits to ensure compliance when working on a research project funded by a government grant requiring strict cost reporting and evidence of expense alignment with project objectives.

Signup and view all the flashcards

Three-Point Estimating for Uncertain Costs

Using three-point estimating to provide a range of forecasts and communicate uncertainties when a sponsor requests a cost forecast for the next quarter but some activities have uncertain costs due to dependencies on external vendors.

Signup and view all the flashcards

Risk-Based Contingency Allocation

Allocating contingency reserves based on quantitative risk analysis to reflect significant risk events which could drastically increase costs in a project.

Signup and view all the flashcards

Mitigating Critical Supplier Cost Increases

Negotiating with the supplier to lock in costs or seek alternative suppliers when a critical supplier's costs have increased significantly, impacting the project budget.

Signup and view all the flashcards

Analyzing EAC Variance and Corrective Actions

Analyzing the root cause of the variance and implementing corrective actions when the Estimate at Completion (EAC) is higher than the original budget during cost monitoring.

Signup and view all the flashcards

Presenting Variance Report with Risk Analysis

Highlighting significant variances and explaining their root causes, linking them to project risks when presenting a variance report to the sponsor which shows both positive and negative variances.

Signup and view all the flashcards

Adjusting Analogous Estimates for Scope

Adjusting the estimates to account for scope differences and validating assumptions when using analogous estimating, and a team member questions its accuracy due to differences in project scope.

Signup and view all the flashcards

Investigating Discrepancies in Time Tracking

Investigating the cause of the discrepancy to ensure accurate cost tracking when noticing team members are consistently logging fewer hours than planned during cost monitoring.

Signup and view all the flashcards

Cost-Benefit Analysis for Lowest Bidder

Conducting a cost-benefit analysis to assess the trade-off between cost and quality when a key stakeholder insists on using the lowest bidder for a critical project task, raising concerns about quality.

Signup and view all the flashcards

Analyzing Resource Utilization and Indirect Costs

Reviewing resource utilization and indirect cost allocations for inefficiencies when the project burn rate exceeds the planned rate, but there are no significant variances in deliverable completion.

Signup and view all the flashcards

Locking in Material Prices

Locking in material prices through long-term contracts with suppliers when project has fixed labor costs but flexible material costs and material prices are rising due to market conditions.

Signup and view all the flashcards

Addressing EV/PV/AC Discrepancies

Analyzing the root cause of the cost overrun and adjusting the task schedule or resource allocation when the EV (Earned Value) for a critical task is lower than the PV (Planned Value), but the AC (Actual Cost) is significantly higher.

Signup and view all the flashcards

Adjusting Budget for Learning Curve

Allocating additional funds from the contingency reserve for training and extended timelines when a project team has underestimated the learning curve for using a new technology, leading to increased labor costs.

Signup and view all the flashcards

Optimizing Overhead Allocations

Evaluating and optimizing overhead allocations to reduce the cost burden when a cost breakdown for a key deliverable reveals that overhead costs are disproportionately high.

Signup and view all the flashcards

Crashing Critical Tasks for Resource Optimization

Applying crashing to reduce the duration of the critical task and reallocate resources when a team identifies a task requiring higher-than-expected resource effort, but reallocating resources risks delaying another critical task.

Signup and view all the flashcards

Evaluating Feature Requests with Surplus Funds

Evaluating the feasibility of the new features and their alignment with project objectives before reallocating funds when a project is running under budget, and the sponsor suggests reallocating surplus funds to add new features.

Signup and view all the flashcards

Negotiating Milestone Adjustments

Negotiating milestone adjustments with the contractor to align payments with revised timelines when a contractor responsible for a critical component has delayed delivery, and their payment is tied to milestones.

Signup and view all the flashcards

Addressing Schedule Delays with Cost Efficiency

Address schedule delays while maintaining cost efficiency by reallocating resources when the project currently has a CPI of 1.1 and an SPI of 0.9.

Signup and view all the flashcards

Using Management Reserve for Unforeseen Risks

Access the management reserve to address unforeseen risks when the project team has used all contingency reserves for known risks, but additional costs are arising due to unforeseen risks.

Signup and view all the flashcards

Cost-Benefit Analysis for Automation

Conduct a detailed cost-benefit analysis to determine if automation will yield long-term savings when a sponsor demands cost reductions on a resource-intensive phase, and the team suggests automating a repetitive task, but the upfront costs are high.

Signup and view all the flashcards

Negotiating Contractor Rates

Negotiate a bulk discount or long-term contract with the contractors when a project requires hiring temporary contractors for peak workloads, and the hourly rates are much higher than initially budgeted.

Signup and view all the flashcards

Renegotiating Contract Terms for External Delays

Renegotiate the contract terms to account for external delays when a fixed-price contract includes cost penalties for late delivery, and a vendor informs the project manager that delays are unavoidable due to supply chain disruptions.

Signup and view all the flashcards

Revising Estimating Methodology

Revisit the estimating methodology and include contingency for future tasks when a project team's cost estimates are consistently lower than the actuals for completed tasks.

Signup and view all the flashcards

Requesting Additional Funds for Software Purchase

Request additional funds through a formal change request when a project requires purchasing specialized software and the licensing costs exceed the initial budget allocation.

Signup and view all the flashcards

Resource Smoothing for Workload Balancing

Use resource smoothing to balance workloads while maintaining cost efficiency when a resource optimization plan reduces costs by consolidating roles, but the workload increases for critical team members, leading to burnout risks.

Signup and view all the flashcards

Reporting Management Reserve Utilization

Provide a detailed report explaining how the reserve was used and remaining risks when a project is on track for cost and schedule, but the management reserve has been partially used and the sponsor requests a report on reserve utilization.

Signup and view all the flashcards

Managing Advance Payment Risk

Evaluate the risks of advance payment and propose a partial advance payment as a compromise when a contractor offers a discount if the project pays in advance for services, which reduces costs but increases financial risk.

Signup and view all the flashcards

Change Control for Budget Reallocation

Request a change control process to adjust the budget formally when a cost performance review shows that one high-value task is consistently under budget, and the sponsor suggests reallocating these funds to another phase.

Signup and view all the flashcards

Addressing Schedule Advance with Cost Overruns

The project is ahead of schedule but over budget; focus on reducing future costs when a project nearing completion shows an SPI (Schedule Performance Index) of 1.05 and a CPI (Cost Performance Index) of 0.95.

Signup and view all the flashcards

Cost-Benefit Analysis for Process Automation

Conduct a detailed cost-benefit analysis and present the findings to the sponsor when a sponsor demands cost reductions on a resource-heavy phase of the project, and the project manager identifies that automating a process will require significant upfront costs but long-term savings.

Signup and view all the flashcards

Addressing EAC Exceeding Budget

Reassess remaining tasks and implement cost-saving measures where possible when a project has completed 40% and EAC (Estimate at Completion) forecasts show the total cost to exceed the budget.

Signup and view all the flashcards

Study Notes

Project Management Cost Control

  • Managing Cost Variability: Include a contingency reserve specifically for exchange rate fluctuations when dealing with multiple international locations.
  • Addressing Cost Underestimation: Revise indirect cost estimates and submit a formal change request for baseline adjustment.
  • Budgetary Constraints on Equipment: Explore alternative equipment providers or sharing agreements to avoid exceeding the task budget.
  • Parametric Estimating Accuracy: Validate parameters with historical data and supporting documentation to address stakeholder concerns.
  • New Risk Emergencies: Use the management reserve to address unforeseen risks needing immediate funding.

Project Management Prioritization

  • Prioritizing Tasks for Sprints: Assign story points based on task complexity and effort.
  • Scope Increases with Fixed Budgets: Prioritize requirements and trade off lower-value items to maintain the budget.
  • Historical Data for Cost Estimation: Validate assumptions with stakeholders and update estimates accordingly if historical data lacks documentation.
  • Subcontractor Pricing: Prioritize performing a cost-benefit analysis and assessing risks before selecting a subcontractor whose rates are significantly lower than industry standards.

Cost Performance Management

  • Cost Tracking Compliance: Implement detailed cost tracking with regular audits to ensure compliance with project objectives and funding agency requirements.
  • Uncertain Cost Forecasting: Use three-point estimating to account for uncertainties, providing a range of forecasts.
  • Reflecting Risk in Budgets: Use quantitative risk analysis to allocate contingency reserves based on the probability and impact of risk events.
  • Supplier Cost Increases: Negotiate with suppliers to lock in costs or explore alternative suppliers when dealing with cost increases if the project is negatively affected by the external factors.

Project Cost Variance Management

  • Variance Reports: Highlight significant variances and explain their root causes, linking them to project risks when responding to a sponsor request for a variance report.
  • Analogous Estimating Accuracy: Account for scope differences and validate assumptions when concerns are raised regarding the accuracy of similar project analog estimating.
  • Team Member Hour Discrepancies: Investigate the cause of discrepancies to ensure accurate cost tracking.
  • Cost-Quality Trade-offs: Conduct a cost-benefit analysis to assess the trade-off between cost and quality when stakeholders demand the lowest bidder.
  • Burn Rate Exceeding Plan: Review resource utilization and indirect cost allocations for inefficiencies to identify the cause.

Cost Management Strategies

  • Resource Optimization: If automating a task is in the plan, conduct a cost-benefit analysis to determine if automation will yield long-term savings.
  • Contractor Rate Increases: Negotiate a contract, bulk discount, or long-term contract with the contractor to handle the higher-than-budgeted hourly rates.
  • Penalties and Delays: Negotiate to account for the delays in the contract or request the sponsor's intervention to waive the penalties when a supplier informs the project manager of unavoidable external delays.
  • Under Budget Deliverables and Cost Performance: Retain the funds in the task budget to absorb potential future risks, and only move the funds based on the sponsor's request after a formal change control process is instituted.
  • Cost Estimates Discrepancy: Revisit the estimating methodology and include contingency for future tasks if the project team's cost estimates are consistently lower than the actuals.

Studying That Suits You

Use AI to generate personalized quizzes and flashcards to suit your learning preferences.

Quiz Team

Related Documents

Module 7 - Chat GBT PDF

Description

This quiz covers essential strategies in project management focusing on cost control and effective prioritization of tasks. Learn how to manage cost variability, address underestimation, and handle unexpected risks while maintaining budget constraints. Gain insights into using historical data for informed decision-making in project sprints.

More Like This

Use Quizgecko on...
Browser
Browser