In PERT, the pessimistic cost estimate is $11,000, and the optimistic cost estimate is $________.

Understand the Problem

The question is asking for the optimistic cost estimate in a PERT (Program Evaluation and Review Technique) analysis, given the pessimistic cost estimate.

Answer

$O = 6E - 4M - P$
Answer for screen readers

The optimistic cost estimate can be found using the formula $O = 6E - 4M - P$ where $P$ is the pessimistic cost estimate and $E$ and $M$ must be known to calculate $O$.

Steps to Solve

  1. Identify the given values

In PERT analysis, we typically have the following estimates:

  • Optimistic cost estimate ($O$)
  • Pessimistic cost estimate ($P$)
  • Most likely cost estimate ($M$)

Since we are provided with the pessimistic cost estimate ($P$), we will need the optimistic cost estimate ($O$) and most likely cost estimate ($M$) in order to calculate the overall expected cost.

  1. Use PERT formula

The PERT expected cost formula is:

$$ E = \frac{O + 4M + P}{6} $$

Where:

  • $E$ is the expected cost
  • $O$ is the optimistic cost estimate
  • $M$ is the most likely cost estimate
  • $P$ is the pessimistic cost estimate
  1. Rearrange to find optimistic estimate

If we only have the pessimistic cost estimate ($P$) and need to find the optimistic estimate ($O$), we rearrange the equation. Assuming we know the most likely estimate ($M$), we can express $O$ as:

$$ O = 6E - 4M - P $$

Here, we need values for $E$ (expected cost) and $M$ (most likely cost) to calculate $O$.

The optimistic cost estimate can be found using the formula $O = 6E - 4M - P$ where $P$ is the pessimistic cost estimate and $E$ and $M$ must be known to calculate $O$.

More Information

In a PERT analysis, the cost estimates provide a range that helps project managers understand the potential variability in project costs. The optimistic estimate allows planners to consider best-case scenarios.

Tips

  • Assuming that only the pessimistic cost estimate is sufficient to calculate the optimistic estimate without knowing the most likely or expected cost.
  • Misunderstanding the PERT formula and its rearrangement.

AI-generated content may contain errors. Please verify critical information

Thank you for voting!
Use Quizgecko on...
Browser
Browser