What is the primary purpose of a Work Breakdown Structure (WBS) Dictionary?
What is the primary purpose of a Work Breakdown Structure (WBS) Dictionary?
- To provide a list of project stakeholders
- To describe each element within the WBS (correct)
- To manage project risks
- To schedule project activities
In PMI numbering, where does the numbering start from?
In PMI numbering, where does the numbering start from?
- Level 1
- Control Accounts (correct)
- Project Title
- Work packages
What is the purpose of Control Accounts in project management?
What is the purpose of Control Accounts in project management?
- To monitor scope changes
- To create project budgets
- To allocate project resources
- To establish a baseline for performance measurement (correct)
Which document is an output of the Create WBS process?
Which document is an output of the Create WBS process?
What does the WBS Dictionary contain?
What does the WBS Dictionary contain?
According to PMI numbering, at which level is the project title located?
According to PMI numbering, at which level is the project title located?
What comes immediately after Control Accounts in PMI numbering?
What comes immediately after Control Accounts in PMI numbering?
In a Work Breakdown Structure (WBS), what is the purpose of a Work Package?
In a Work Breakdown Structure (WBS), what is the purpose of a Work Package?
What type of information is NOT typically found in a WBS Dictionary?
What type of information is NOT typically found in a WBS Dictionary?
Why is having a detailed WBS Dictionary beneficial for a project?
Why is having a detailed WBS Dictionary beneficial for a project?
Study Notes
Work Breakdown Structure (WBS)
- A WBS is a deliverable-oriented hierarchical decomposition of the work to be accomplished by the project team to meet project objectives.
- It is a task-oriented decomposition of work that identifies tasks and the resources required to accomplish the task.
Characteristics of WBS
- It is a detailed project plan that includes effort and resource dates.
- It does not show the dependencies between tasks.
- A detailed project schedule can be created only after creating the WBS.
Decomposition of WBS
- Decompose until the WBS element cannot be logically decomposed further.
- Decompose until the WBS element can be estimated accurately.
- Decompose until the WBS element has a meaningful conclusion.
Importance of Validate Scope Process
- It must be completed in a project to ensure that the scope is complete and accurate.
- Lack of a good WBS may miss critical work.
Levels of WBS
Level 1
- The first and top level of WBS is the project title.
Level 2
- The second level of WBS is Control Accounts.
- Control accounts are a project's major parts, systems, phases, or deliverables.
- PMI numbering system is allotted from here.
Level 3
- The third level of WBS is Work Packages.
- Work packages come together to constitute Control Accounts.
- It is a point where it can be reliably scheduled, cost-estimated, monitored, and controlled.
Level 4
- The last level of WBS is Activities.
- Activities are the tasks assigned to project team members to complete the work package.
Final Step
- After breaking down the scope into tasks, a project manager should identify staff working on the project tasks, their roles and responsibilities, and the tasks' due dates.
Studying That Suits You
Use AI to generate personalized quizzes and flashcards to suit your learning preferences.
Description
Test your knowledge on the Work Breakdown Structure (WBS) in project management with this practice question. Understand the concept of decomposing work into tasks and resources required for project completion.