Who is required to certify construction after completion of work up to the plinth level?
Who is required to certify construction after completion of work up to the plinth level?
- Collector
- Town Planning Officer only
- Structural Auditor only
- Architect / Licensed Engineer / Supervisor (correct)
Which Appendix of UDCPR contains the prescribed format for plinth certification intimation?
Which Appendix of UDCPR contains the prescribed format for plinth certification intimation?
- Appendix G
- Appendix F (correct)
- Appendix E
- Appendix D
To whom is the plinth level intimation submitted?
To whom is the plinth level intimation submitted?
- District Survey Office
- Concerned Branch Office of Town Planning / Authority (correct)
- High Power Committee
- State Government
What percentage of plinth-certified cases shall be inspected by the concerned Authority?
What percentage of plinth-certified cases shall be inspected by the concerned Authority?
After submitting plinth certification, what action can the Project Proponent take?
After submitting plinth certification, what action can the Project Proponent take?
ITP projects may be permissible in which zones of a sanctioned RP/DP?
ITP projects may be permissible in which zones of a sanctioned RP/DP?
In Development Plan areas, if the ITP is proposed in non-residential, non-commercial, non-U zones, what fee must be paid?
In Development Plan areas, if the ITP is proposed in non-residential, non-commercial, non-U zones, what fee must be paid?
Which table in UDCPR specifies the premium rates for ITPs in certain zones?
Which table in UDCPR specifies the premium rates for ITPs in certain zones?
The premium condition for non-permissible zones is applicable to:
The premium condition for non-permissible zones is applicable to:
Which of the following is NOT required at the time of plinth level intimation?
Which of the following is NOT required at the time of plinth level intimation?
Flashcards
Who certifies plinth level completion?
Who certifies plinth level completion?
An Architect, Licensed Engineer, or Supervisor
Plinth certification format location?
Plinth certification format location?
Appendix F of UDCPR
Where is plinth level intimation submitted?
Where is plinth level intimation submitted?
Submitted to the Concerned Branch Office of Town Planning / Authority
Inspection percentage of plinth-certified cases?
Inspection percentage of plinth-certified cases?
Signup and view all the flashcards
Action after submitting plinth certification?
Action after submitting plinth certification?
Signup and view all the flashcards
ITP projects permissible in which zones?
ITP projects permissible in which zones?
Signup and view all the flashcards
Payment for ITP in non-zones?
Payment for ITP in non-zones?
Signup and view all the flashcards
Premium rates table for ITPs?
Premium rates table for ITPs?
Signup and view all the flashcards
Premium condition applicability?
Premium condition applicability?
Signup and view all the flashcards
Not required at plinth intimation?
Not required at plinth intimation?
Signup and view all the flashcards
Study Notes
- This is a set of MPSC ATP-level MCQs based only on the topics of Plinth Certification and Planning Consideration for Integrated Township Projects (ITP) under UDCPR.
Plinth Certification
- After completing work up to the plinth level, the construction must be certified by an Architect, Licensed Engineer, or Supervisor.
- Appendix F of UDCPR has the prescribed format for plinth certification intimation.
- The plinth level intimation has to be submitted to the Concerned Branch Office of Town Planning/Authority.
- The concerned Authority should inspect 10% of plinth-certified cases.
- After submitting plinth certification, the Project Proponent can continue construction work further.
Planning Consideration
- ITP projects are permissible in any land-use zone of a sanctioned RP/DP.
- In Development Plan areas, if the ITP is proposed in non-residential, non-commercial, non-U zones, premium must be paid.
- Table 14A in UDCPR specifies the premium rates for ITPs in certain zones.
- The premium condition for non-permissible zones is applicable only to new ITPs in Development Plan areas.
- An Official Gazette Notification is not required at the time of plinth level intimation. The following are required:
- Certification by Architect
- Submission in Appendix F
- Submission to Authority or Town Planning Office