How often should try lever tests be performed on power boilers operating below 2760 kPa?

Every six months

What is the purpose of a try lever test for pressure relief valves?

To determine if the valve is fully closed

When should the try lever test be conducted for steam heating boilers?

When the boiler pressure is at least 35 kPa

Where can detailed descriptions of pressure relief valve test procedures be found?

<p>ASME BPVC Sections I, IV, VI, and VII</p> Signup and view all the answers

What is the minimum power boiler pressure required for conducting try lever tests?

<p>At least 75% of the setting of the safety valve</p> Signup and view all the answers

What should be done if the relief valve simmers after a try lever test?

<p>Report to the maintenance department</p> Signup and view all the answers

What should be done if the safety valve continues to simmer after operating the try lever two or three times?

<p>Repair or replace the valve</p> Signup and view all the answers

When should pop tests be performed on a boiler?

<p>Annually</p> Signup and view all the answers

Who is qualified to adjust or repair pressure relief valves according to ASME BPVC sections?

<p>Local Boiler Inspector</p> Signup and view all the answers

What is the purpose of accurately recording the opening and reseating pressures during a pop test?

<p>To determine the exact pressures at which the safety valve opens and closes</p> Signup and view all the answers

What should be done if a defective safety valve is identified during a pop test?

<p>Replace or repair the valve prior to the boiler re-entering service</p> Signup and view all the answers

Why is it important to perform pop tests annually?

<p>To ensure compliance with ASME BPVC sections</p> Signup and view all the answers