Questions and Answers

What does a negative CV indicate?

  • The project is underbudget
  • Higher cost than planned (correct)
  • Lower actual cost than budgeted
  • The project is ahead of schedule
  • What does CPI < 1 indicate?

  • The project is over budget or overrun (correct)
  • The project is progressing well against the schedule
  • The project is under budget
  • The project is on budget
  • What is the definition of SPI (Schedule Variance Index)?

  • Measure of current cost efficiency of the project
  • Difference between earned value and actual cost
  • Conformance of actual progress to planned progress (correct)
  • Amount of funds necessary to finish the project
  • If SPI > 1, what does it indicate?

    <p>The project is ahead of schedule</p> Signup and view all the answers

    What does ETC (Estimate to Complete) represent?

    <p>Amount of funds necessary to finish the project</p> Signup and view all the answers

    In TCPI < 1, what does it signify?

    <p>Efficiency required for future work to stay on budget</p> Signup and view all the answers

    If EV equals AC, what does it mean for the project budget?

    <p>The project is on budget</p> Signup and view all the answers

    What does a positive VAC value indicate?

    <p>The project is under budget</p> Signup and view all the answers

    What does a negative VAC value imply?

    <p>The project is over budget</p> Signup and view all the answers

    How does the VAC value influence budget accuracy?

    <p>The closer to zero, the higher the budget accuracy</p> Signup and view all the answers

    What does a TCPI value greater than 1 indicate?

    <p>Less funds and more work remaining</p> Signup and view all the answers

    What does TCPI = 1 signify for a project?

    <p>Just enough funds to complete the work</p> Signup and view all the answers

    How would you describe a project with TCPI < 1?

    <p>Under budget with more work remaining</p> Signup and view all the answers

    In what scenario would TCPI be exactly equal to 1?

    <p>Just enough funds to complete the work</p> Signup and view all the answers

    'To Complete Performance Index' (TCPI) primarily measures:

    <p>Planned vs. actual cost performance</p> Signup and view all the answers

    'Variance at Completion' (VAC) becoming close to zero indicates:

    <p>'Budget at Completion' (BAC) accuracy</p> Signup and view all the answers

    What does a VAC value higher than zero suggest for a project?

    <p>The project is right on track according to estimates.</p> Signup and view all the answers

    More Like This

    Project Management Chapter 1 Quiz
    4 questions
    Project Management Process Groups
    14 questions

    Project Management Process Groups

    WellConnectedComputerArt avatar
    WellConnectedComputerArt
    Project Management Fundamentals
    20 questions
    Project Management Flashcards
    12 questions

    Project Management Flashcards

    IllustriousHoneysuckle avatar
    IllustriousHoneysuckle
    Use Quizgecko on...
    Browser
    Browser